Bonita_Creek_Road_Specifications_1.pdf

PDF 745 KB Posted

Attached to
GILA BOX GAOA BONITA CREEK RD REPAIR
Solicitation number
140L0624R0030
Issued by

About this file

This document provides specifications for repairing Gila Box GAOA Bonita Creek Road located in Graham County, Arizona. The Department of the Interior Bureau of Land Management is soliciting bids to improve and repair approximately 15 miles of the road, including all necessary labor, materials, equipment, and supervision. Bids are due under Solicitation Number 140L0624R0030 by the date specified in the draft plans and specifications. The selected contractor will be responsible for completing the repairs in accordance with the technical requirements outlined in the provided project description and specifications document.

View the file

Other files

File Type Posted
Bonita_Creek_Road_Plans_1.pdf PDF
A14_Sources_Sought_140L0624R0030_1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BONITA CREEK ROAD

Technical Specifications

GLHN PROJECT #20049.01

November 1, 2023

GLHN Architects & Engineers, Inc. |2939 E Broadway Blvd, Tucson, AZ 85716

T 520.881.4546 | F 520.795.1822 | GLHN.com

Gila Box Bonita Creek Road

Bureau of Land Management TOC - 1 Table of Gila Box Bonita Creek Road GLHN #20049.01 Contents

TABLE OF CONTENTS

DIVISION 01 – GENERAL REQUIREMENTS

011000 Summary of Work 011060 Permits 011500 Measurement and Payment 013100 Project Management and Coordination 013200 Construction Progress Documentation 013300 Submittal Procedures 014000 Quality Control/Quality Assurance 015000 Traffic Control 017000 Contract Closeout 017419 Construction Waste Management and Disposal 017839 Project Record Documents

DIVISION 02 – EXISTING CONDITIONS

024119 Selective Demolition

DIVISION 31 – EARTHWORK

311000 Site Clearing 312000 Earth Moving 312500 Gabions 315000 Excavation Support and Protection

DIVISION 32 – EXTERIOR IMPROVEMENTS

321313 Concrete Paving

DIVISION 33 – UTILITIES

334200 Stormwater Conveyance

Bureau of Land Management TOC - 2 Table of Gila Box Bonita Creek Road GLHN #20049.01 Contents

THIS PAGE INTENTIONALLY LEFT BLANK

Bureau of Land Management 011000 - 1 Summary of Gila Box Bonita Creek Road GLHN #20049.01 Work

SECTION 011000 – SUMMARY OF WORK

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

B. BLM Manual 9100 – Facility Planning, Design, Construction and Maintenance

C. BLM Manual 9113 – Roads

1.2 SUMMARY

A. Section Includes:

1. Project information.

2. Work covered by Contract Documents.

3. Work by Government.

4. Work under separate contracts.

5. Future work.

6. Government-furnished products.

7. Access to site.

8. Coordination with occupants.

9. Work restrictions.

10. Specification and drawing conventions.

11. Miscellaneous provisions.

1.3 PROJECT INFORMATION

A. Owner: Bureau of Land Management – Bonita Creek Roadway Project.

1. Project Location: 10 miles northeast of Safford, Arizona. Take highway 191, turn north on Sanchez Road, 6 miles to Bonita Creek Road intersection.

1.4 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work of the Project is defined by the Contract Documents and consists of the following:

1. Install concrete low water crossing at STA 70+00 with upstream and downstream erosion protection.

2. Restore inside curve downside slope below road at STA 106+00. Fill at 3 horizontal to 1 vertical slopes and protect with riprap. Install gabion baskets at bottom of slope under pipe outlet. Install new additional 24” CMP culvert.

3. Cut back hillside slope above the road at STA 167+00 to improve visibility sight lines for drivers.

Bureau of Land Management 011000 - 2 Summary of

4. Install upstream sediment control jersey barriers at STA 173+50.

5. Install rock check dams in roadside swale between STA 177+00 and 181+00.

6. Cut back hillside slope above the road at STA 194+00 to improve visibility sight lines for drivers. Install rock check dams in roadside swale.

1.5 ACCESS TO SITE

A. Contractor shall have limited use of Project site for construction operations.

B. Confine operations to the site of the proposed Work or within the areas provided and shown on the drawings. Construction camps and staging areas outside the construction area must be approved by the Contracting Officer (CO). Obtain advance approval from the CO of all staging areas, material stockpile and waste areas and camp areas.

C. It shall be understood that responsibility for protection and safekeeping of equipment and materials on or near the site will be entirely that of the CONTRACTOR and that no claim shall be made against the GOVERNMENT by reason of any act of an employee or trespasser whether GOVERNMENT has paid CONTRACTOR for equipment or materials in storage or not. It shall be further understood should any occasion arise necessitating access by the GOVERNMENT to the sites occupied by these stored materials and equipment, the CONTRACTOR owning or responsible for the stored materials or equipment shall immediately provide same. No materials or equipment may be placed upon the property of the GOVERNMENT until the CO has agreed to the location proposed by the CONTRACTOR to be used for storage. CONTRACTOR is solely responsible for obtaining and shall pay all costs in connection with any additional work area, storage sites, access to the site, or temporary right-of-way, which may be required for proper completion of the Work.

D. Confine operations to normal government business days and hours, exclusive of Federal holidays, unless provided written permission from the GOVERNMENT to work on the site outside of those days and hours.

1.6 PROTECTION OF EXISTING STRUCTURES

A. Where excavation will be required adjacent to existing structures, the CONTRACTOR is solely responsible to maintain the structural integrity of the existing structures. Take whatever means necessary to ensure the existing structures are not damaged. Repair all damage to the existing structures at CONTRACTOR's expense. Repair any fences, posts or signs damaged during construction to the satisfaction of the owner. Unless otherwise noted on the Construction Drawings, restore all existing drainageways disturbed by construction to their original size, line, and grade.

B. The paved road, signage and culverts shall also be protected during construction. Immediately sweep away any spilled soil, rock or gravel material. Restore or repair to original condition roads, culverts, cattle guards and fences or any other structures damaged by the CONTRACTOR’s activities and access to the sites at no additional cost to the project.

Bureau of Land Management 011000 - 3 Summary of

1.7 FIELD CHECK OF EXISTING STRUCTURES

A. Dimensions and elevations of existing structures and locations of existing fences, pipelines, and vegetation shown on the drawings were taken from available records and are not guaranteed for accuracy. Check all dimensions and elevations of existing structures or other existing items, both above and below ground, affected by or affecting the Work under this contract, prior to the start of construction or ordering materials and equipment affected thereby.

1.8 FIELD SURVEY AND SITE LAYOUT

A. Contractor shall locate, identify and protect in place all project control points (refer to plans).

B. Protect in place all construction staking. Stakes that have been removed or damaged shall be replaced at contractor’s expense.

C. Engage a State of Arizona licensed professional surveyor to lay out the Work using accepted surveying practices.

D. Certified Survey: On completion of construction, prepare an as built plan stamped by the surveyor.

1.9 SITE ACCESS

A. Determine the adequacy of all roads, culverts, cattle guards, and bridges used in moving or gaining access for equipment and materials to the construction site. Provide alternative methods of access, such as a temporary crossing for any equipment that exceeds the structural limits of existing facilities. Improvements for road access including fill, culverts, and fencing to remain after project completion as approved by CO.

1.10 FIELD OFFICES AND SHEDS

A. Provide field office and storage areas or sheds if required for completion of the work. Locate these temporary structures in areas approved by the CO. All expenses for telephone, utilities, security and waste disposal are the responsibility of the CONTRACTOR. Provide the name and phone number of a representative who may be contacted after hours in case of emergency.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 011010

Bureau of Land Management 011000 - 4 Summary of

Bureau of Land Management 011060 - 1 Permits Gila Box Bonita Creek Road GLHN #20049.01

SECTION 011060 – PERMITS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

B. BLM Manual 9100 – Facility Planning, Design, Construction and Maintenance

1.2 WORK INCLUDED

A. Prepare, maintain, and proceed in conformity with Storm Water Discharge Permit/Storm Water Pollution Prevention Plan as required by the US Environmental Protection Agency. The CONTRACTOR will apply for and obtain this permit by submitting a Notice of Intent and pay all fees associated with the Storm Water Discharge Permit. During construction the CONTRACTOR is responsible for all maintenance to the pollution prevention plan.

B. When the CONTRACTOR has completed all work on the project and prior to issuance of final payment, remove all BMP’s from the site. When all criteria have been met, the CONTRACTOR will file the Notice of Termination for the permit.

C. Except as otherwise noted, identify, obtain, maintain, and proceed in conformity with any and all additional required permits necessary for completion of the Work. Any costs associated with these Permits are included as part of the Contract Price as incidental costs.

1.3 SUBMITTALS

A. The CONTRACTOR shall supply to the Government a draft Storm Water Discharge Permit within 10 days after issuance of the Notice to Proceed. The Government will have 10 days to review and provide comments back to the Contractor. The Contractor then has 10 additional days to submit the final Storm Water Discharge Permit to the Government. Work may proceed after the final Storm Water Discharge Permit has been returned to the Contractor with an acceptance letter from the Government. The Contractor shall perform all compliance testing required by all permits.

Submit results of compliance testing directly to the appropriate review agency. Provide copies of all results to the Government. Submit copies of any additional required permits to the Government when they are acquired.

PART 2 - PRODUCTS

NOT USED

Bureau of Land Management 011060 - 2 Permits Gila Box Bonita Creek Road GLHN #20049.01

PART 3 - EXECUTION

NOT USED

END OF SECTION 011060

Bureau of Land Management 011500 - 1 Measurement Gila Box Bonita Creek Road GLHN #20049.01 and Payment

SECTION 011500 – MEASUREMENT AND PAYMENT

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

B. The appended SUBMITTALS SCHEDULE for this project applies to this Section.

C. BLM Manual 9100 – Facility Planning, Design, Construction and Maintenance

D. BLM Manual 9113 – Roads

E. Manual of Uniform Traffic Control Standards (MUTCD) Current Edition.

1.2 SCOPE

A. The method of measurement and basis of payment is described in this section.

1.3 GENERAL

A. Bid price for each item of the Contract covers all Work shown on the Drawings and required by the specifications and other Contract Documents.

B. All costs are included in the unit and lump-sum prices bid including all materials, equipment, supplies and appurtenances; all construction plant, equipment, and tools; and all labor and supervision necessary to fully complete the Work.

C. No item that is required by the Contract Documents, for the proper and successful completion of the Work, will be paid for outside of or in addition to the prices submitted in the Bid.

D. All work not specifically set forth as a pay item in the Bid Form is considered an incidental obligation of the CONTRACTOR, and all costs in connection therewith shall be included in the unit prices bid.

1.4 ESTIMATED QUANTITIES

A. All quantities in the Price Schedule of the Bid Form or other Contract Documents, which are to be paid per field measurement, are approximate only, and are to be used only as:

1. A basis for estimating the probable cost of the Work, and

2. For the purpose of comparing Bids submitted for the Work.

Bureau of Land Management 011500 - 2 Measurement Gila Box Bonita Creek Road GLHN #20049.01 and Payment

B. Actual work performed, and materials furnished under the unit-price items for those items to be field measured may differ from the estimated quantities.

C. Basis of payment for work and materials will be the actual amount of work done and materials furnished to the pay lines defined in this section.

D. Payment will be paid at the unit price bid for listed items successfully completed according to Contract requirement.

E. Lump-sum items and those based on neat-line plan dimensions are not field-measured. They will be paid at neat-line or the lump-sum price bid for the items listed.

1.5 AUTHORITY

A. Contracting Officer (CO) will perform all measurements and compute quantities for payment.

CO will verify measurements and quantities provided by CONTRACTOR.

B. CONTRACTOR provides access to work areas for survey measurements, as required.

1.6 MEASURED QUANTITIES

A. Measurement by Volume: Measured by cubic dimension using mean length, width, and height or thickness.

1. Measurement for payment of excavations upon or against which concrete or cementitious backfill is not to be placed will be limited to the lines and grades shown on the Drawings or to the most practical lines, grades, and dimensions established by the CO, in writing.

No measurement will be made of over excavations beyond design lines and grades.

2. Fill quantities will be computed using the average-end-area method or other computation method approved of by the CO.

B. Measurement by Area: Measured by square dimension using mean length and width. Items that are measured by area will be measured parallel to the ground surface.

C. Linear Measurement: Measured by linear dimension at the item centerline or mean chord. Items that are measured by the lineal foot will be measured parallel to the ground surface, unless otherwise specified.

D. Stipulated Sum/Price Items: Measured by weight, volume, area, or linear means, or combination, as appropriate, as completed items or units of the work.

E. Lump-Sum Items: Will not be measured for payment. Interim measurements may be made to monitor work progress.

1.7 SCHEDULE OF VALUES

A. A schedule of values or “allocation of contract price” is required for all lump sum items.

B. The schedule of values is used only to help assess the intermediate value of work completed for the purpose of making progress payments. The schedule of values is not considered as a commitment to prices in the event of later negotiations.

Bureau of Land Management 011500 - 3 Measurement Gila Box Bonita Creek Road GLHN #20049.01 and Payment

PART 2 - PRODUCTS (Not Used)

END OF SECTION 011500

Bureau of Land Management 011500 - 4 Measurement Gila Box Bonita Creek Road GLHN #20049.01 and Payment

Bureau of Land Management 013100 - 1 Project Management and Gila Box Bonita Creek Road GLHN #20049.01 Coordination

SECTION 013100 – PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

B. BLM Manual 9100 – Facility Planning, Design, Construction and Maintenance

C. BLM Manual 9113 - Roads

1.2 SUMMARY

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Coordination drawings.

2. Requests for Information (RFIs).

1.3 DEFINITIONS

A. RFI: Request from Owner, Engineer, or Contractor seeking information from each other during construction.

1.4 COORDINATION

A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, that depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

1. Prepare similar memoranda for Owner and separate contractors if coordination of their Work is required.

Bureau of Land Management 013100 - 2 Project Management and Gila Box Bonita Creek Road GLHN #20049.01 Coordination

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's construction schedule.

2. Preparation of the schedule of values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of submittals.

5. Progress meetings.

6. Preinstallation conferences.

7. Project closeout activities.

8. Startup and adjustment of systems.

9. Project closeout activities.

1.5 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.

1. Engineer will return RFIs submitted to Engineer by other entities controlled by Contractor with no response.

2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. Project name.

2. Project number.

3. Date.

4. Name of Contractor.

5. Name of Engineer.

6. RFI number, numbered sequentially.

7. RFI subject.

8. Specification Section number and title and related paragraphs, as appropriate.

9. Drawing number and detail references, as appropriate.

10. Field dimensions and conditions, as appropriate.

11. Contractor's suggested resolution. If Contractor's solution(s) impacts the Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

12. Contractor's signature.

13. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop

Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

C. RFI Forms: Software-generated form with substantially the same content as indicated above, acceptable to Engineer.

D. Engineer's Action: Engineer will review each RFI, determine action required, and respond. Allow seven working days for Engineer's response for each RFI. RFIs received by Engineer after 1:00 p.m.

will be considered as received the following working day.

1. The following RFIs will be returned without action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

Bureau of Land Management 013100 - 3 Project Management and Gila Box Bonita Creek Road GLHN #20049.01 Coordination

c. Requests for coordination information already indicated in the Contract Documents.

d. Requests for adjustments in the Contract Time or the Contract Sum.

e. Requests for interpretation of Engineer's actions on submittals.

f. Incomplete RFIs or inaccurately prepared RFIs.

2. Engineer's action may include a request for additional information, in which case Engineer's time for response will date from time of receipt of additional information.

3. Engineer's action on RFIs that may result in a change to the Contract Time or the Contract Sum may be eligible for Contractor to submit Change Proposal according to Division 01 Section "Contract Modification Procedures."

a. If Contractor believes the RFI response warrants change in the Contract Time or the Contract Sum, notify Engineer in writing within 10 days of receipt of the RFI response.

E. On receipt of Engineer's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Engineer within seven days if Contractor disagrees with response.

PART 2 - PRODUCTS (Not Used)

END OF SECTION 013100

Bureau of Land Management 013100 - 4 Project Management and Gila Box Bonita Creek Road GLHN #20049.01 Coordination

Bureau of Land Management 013200 - 1 Construction Progress Gila Box Bonita Creek Road GLHN #20049.01 Documentation

SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:

1. Startup construction schedule.

2. Contractor's Construction Schedule.

3. Construction schedule updating reports.

4. Daily construction reports.

5. Material location reports.

6. Site condition reports.

7. Unusual event reports.

1.3 DEFINITIONS

A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction Project. Activities included in a construction schedule consume time and resources.

1. Critical Activity: An activity on the critical path that must start and finish on the planned early start and finish times.

2. Predecessor Activity: An activity that precedes another activity in the network.

3. Successor Activity: An activity that follows another activity in the network.

B. Cost Loading: The allocation of the schedule of values for completing an activity as scheduled.

The sum of costs for all activities must equal the total Contract Sum.

C. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.

D. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.

E. Event: The starting or ending point of an activity.

F. Float: The measure of leeway in starting and completing an activity.

1. Float time is not for the exclusive use or benefit of either Government or Contractor, but is a jointly owned, expiring Project resource available to both parties as needed to meet schedule milestones and Contract completion date.

Bureau of Land Management 013200 - 2 Construction Progress Gila Box Bonita Creek Road GLHN #20049.01 Documentation

2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity.

3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.

G. Resource Loading: The allocation of manpower and equipment necessary for completing an activity as scheduled.

1.4 INFORMATIONAL SUBMITTALS

A. Format for Submittals: Submit required submittals in the following format:

1. Working electronic copy of schedule file, where indicated.

2. PDF file.

3. 3 paper copies, of sufficient size to display entire period or schedule, as required.

B. Startup construction schedule.

1. Submittal of cost-loaded, startup construction schedule will not constitute approval of schedule of values for cost-loaded activities.

C. Startup Network Diagram: Of size required to display entire network for entire construction period.

Show logic ties for activities.

D. Contractor's Construction Schedule: Initial schedule, of size required to display entire schedule for entire construction period.

1. Submit a working digital copy of schedule, using software indicated, and labeled to comply with requirements for submittals.

E. CPM Reports: Concurrent with CPM schedule, submit each of the following reports. Format for each activity in reports shall contain activity number, activity description, cost and resource loading, original duration, remaining duration, early start date, early finish date, late start date, late finish date, and total float in calendar days.

1. Activity Report: List of activities sorted by activity number and then early start date, or actual start date if known.

2. Logic Report: List of preceding and succeeding activities for each activity, sorted in ascending order by activity number and then by early start date, or actual start date if known.

3. Total Float Report: List of activities sorted in ascending order of total float.

4. Earnings Report: Compilation of Contractor's total earnings from commencement of the

Work until most recent Application for Payment.

F. Construction Schedule Updating Reports: Submit with Applications for Payment.

G. Daily Construction Reports: Submit at weekly intervals.

H. Material Location Reports: Submit at weekly intervals.

I. Site Condition Reports: Submit at time of discovery of differing conditions.

Bureau of Land Management 013200 - 3 Construction Progress Gila Box Bonita Creek Road GLHN #20049.01 Documentation

J. Unusual Event Reports: Submit at time of unusual event.

K. Qualification Data: For scheduling consultant.

1.5 QUALITY ASSURANCE

A. Scheduling Consultant Qualifications: An experienced specialist in CPM scheduling and reporting, with capability of producing CPM reports and diagrams within 24 hours of Government's request.

B. Prescheduling Conference: Conduct conference at Project site to comply with requirements in Section 013100 "Project Management and Coordination." Review methods and procedures related to the preliminary construction schedule and Contractor's Construction Schedule, including, but not limited to, the following:

1. Review software limitations and content and format for reports.

2. Verify availability of qualified personnel needed to develop and update schedule.

3. Discuss constraints, including work stages.

4. Review delivery dates for Government-furnished products, if any.

5. Review schedule for work of Government's separate contracts, if any.

6. Review submittal requirements and procedures.

7. Review time required for review of submittals and resubmittals.

8. Review requirements for tests and inspections by independent testing and inspecting agencies.

9. Review time required for Project closeout.

10. Review and finalize list of construction activities to be included in schedule.

11. Review procedures for updating schedule.

1.6 COORDINATION

A. Coordinate Contractor's Construction Schedule with the schedule of values, list of subcontracts, submittal schedule, progress reports, payment requests, and other required schedules and reports.

1. Secure time commitments for performing critical elements of the Work from entities involved.

2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.

1.7 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL

A. Computer Scheduling Software: Prepare schedules using current version of software:

1. Use Microsoft Project, Scheduling component of Project software, or Microsoft Excel, from Microsoft Office suite, to create and maintain the schedule.

2. Archive a dated copy of the schedule prior to each schedule change. Provide the CO with all copies upon completion.

Bureau of Land Management 013200 - 4 Construction Progress Gila Box Bonita Creek Road GLHN #20049.01 Documentation

B. Time Frame: Extend schedule from date established for the Notice to Proceed to date of final completion.

1. Contract completion date shall not be changed by submission of a schedule that shows an early completion date, unless specifically authorized by Change Order.

PART 2 - PRODUCTS (Not Used)

END OF SECTION 013200

Bureau of Land Management 013300 - 1 Submittal Gila Box Bonita Creek Road GLHN #20049.01 Procedures

SECTION 013300 - SUBMITTAL PROCEDURES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Submittal schedule requirements.

2. Administrative and procedural requirements for submittals.

B. Related Requirements:

1. Section 013100 "Project Management and Coordination" for submitting coordination drawings and subcontract list and for requirements for web-based Project software.

2. Section 013200 "Construction Progress Documentation" for submitting schedules and reports, including Contractor's construction schedule.

3. Section 014000 "Quality Assurance" for submitting test and inspection reports, and schedule of tests and inspections.

4. Section 017000 "Contract Closeout" for submitting closeout submittals and maintenance material submittals.

5. Section 017839 "Project Record Documents" for submitting record Drawings, record Specifications, and record Product Data.

1.3 DEFINITIONS

A. Action Submittals: Written and graphic information and physical samples that require Government’s responsive action. Action submittals are those submittals indicated in individual Specification Sections as "action submittals."

B. Informational Submittals: Written and graphic information and physical samples that do not require Government’s responsive action. Submittals may be rejected for not complying with requirements. Informational submittals are those submittals indicated in individual Specification Sections as "informational submittals."

1.4 SUBMITTAL SCHEDULE

A. Submittal Schedule: Submit, as an action submittal, a list of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, ordering, manufacturing, fabrication, and delivery when establishing dates. Include additional time required for making corrections or revisions to submittals noted by Government and additional time for handling and reviewing submittals required by those corrections.

1. Coordinate submittal schedule with list of subcontracts, the schedule of values, and Contractor's construction schedule.

Bureau of Land Management 013300 - 2 Submittal Gila Box Bonita Creek Road GLHN #20049.01 Procedures

2. Initial Submittal: Submit concurrently with startup construction schedule. Include submittals required during the first 60 calendar days of construction. List those submittals required to maintain orderly progress of the Work and those required early because of long lead time for manufacture or fabrication.

3. Final Submittal: Submit concurrently with the first complete submittal of Contractor's construction schedule.

a. Submit revised submittal schedule to reflect changes in current status and timing for submittals.

4. Format: Arrange the following information in a tabular format:

a. Scheduled date for first submittal.

b. Specification Section number and title.

c. Submittal Category: Action; informational.

d. Name of subcontractor.

e. Description of the Work covered.

f. Scheduled date for Government’s final release or approval.

g. Scheduled dates for purchasing.

h. Scheduled date of fabrication.

i. Scheduled dates for installation.

j. Activity or event number.

1.5 SUBMITTAL FORMATS

A. Submittal Information: Include the following information in each submittal:

1. Project name.

2. Date.

3. Name of Government.

4. Name of Contractor.

5. Name of firm or entity that prepared submittal.

6. Names of subcontractor, manufacturer, and supplier.

7. Unique submittal number, including revision identifier. Include Specification Section number with sequential alphanumeric identifier, and alphanumeric suffix for resubmittals.

8. Category and type of submittal.

9. Submittal purpose and description.

10. Number and title of Specification Section, with paragraph number and generic name for each of multiple items.

11. Drawing number and detail references, as appropriate.

12. Indication of full or partial submittal.

13. Location(s) where product is to be installed, as appropriate.

14. Other necessary identification.

15. Remarks.

16. Signature of transmitter.

B. Options: Identify options requiring selection by Government.

C. Deviations and Additional Information: On each submittal, clearly indicate deviations from requirements in the Contract Documents, including minor variations and limitations; include relevant additional information and revisions, other than those requested by Government on previous submittals. Indicate by highlighting on each submittal or noting on attached separate sheet.

Bureau of Land Management 013300 - 3 Submittal Gila Box Bonita Creek Road GLHN #20049.01 Procedures

D. PDF Submittals: Prepare submittals as PDF package, incorporating complete information into each PDF file. Name PDF file with submittal number.

E. Submittals for Web-Based Project Software: Prepare submittals as PDF files, or other format indicated by Project software website.

1.6 SUBMITTAL PROCEDURES

A. Prepare and submit submittals required by individual Specification Sections. Types of submittals are indicated in individual Specification Sections.

1. Email: Prepare submittals as PDF package and transmit to Government by sending via email. Include PDF transmittal form. Include information in email subject line as requested by Government.

a. Government will return annotated file. Annotate and retain one copy of file as a digital Project Record Document file.

2. Web-Based Project Software: Prepare submittals in PDF form, and upload to web- based Project software website. Enter required data in web-based software site to fully identify submittal.

3. Paper: Prepare submittals in paper form and deliver to Government.

B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.

2. Submit all submittal items required for each Specification Section concurrently unless partial submittals for portions of the Work are indicated on approved submittal schedule.

3. Submit action submittals and informational submittals required by the same Specification Section as separate packages under separate transmittals.

4. Coordinate transmittal of submittals for related parts of the Work specified in different Sections so processing will not be delayed because of need to review submittals concurrently for coordination.

a. Government reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

C. Processing Time: Allow time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Government’s receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.

1. Initial Review: Allow 14 calendar days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. Government will advise Contractor when a submittal being processed must be delayed for coordination.

2. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal.

3. Resubmittal Review: Allow 14 calendar days for review of each resubmittal.

4. Sequential Review: Where sequential review of submittals by Government’s consultants, Government, or other parties is indicated, allow 21 calendar days for initial review of each submittal.

Bureau of Land Management 013300 - 4 Submittal Gila Box Bonita Creek Road GLHN #20049.01 Procedures

D. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.

1. Note date and content of previous submittal.

2. Note date and content of revision in label or title block and clearly indicate extent of revision.

3. Resubmit submittals until they are marked with approval notation from Government’s action stamp.

E. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.

F. Use for Construction: Retain complete copies of submittals on Project site. Use only final action submittals that are marked with approval notation from Government’s action stamp.

1.7 SUBMITTAL REQUIREMENTS

A. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard published data are unsuitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable.

3. Include the following information, as applicable:

a. Manufacturer's catalog cuts.

b. Manufacturer's product specifications.

c. Standard color charts.

d. Statement of compliance with specified referenced standards.

e. Testing by recognized testing agency.

f. Application of testing agency labels and seals.

g. Notation of coordination requirements.

h. Availability and delivery time information.

4. For equipment, include the following in addition to the above, as applicable:

a. Wiring diagrams that show factory-installed wiring.

b. Printed performance curves.

c. Operational range diagrams.

d. Clearances required to other construction, if not indicated on accompanying Shop

Drawings.

5. Submit Product Data before Shop Drawings, and before or concurrent with Samples.

B. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.

1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:

a. Identification of products.

b. Schedules.

c. Compliance with specified standards.

Bureau of Land Management 013300 - 5 Submittal Gila Box Bonita Creek Road GLHN #20049.01 Procedures

d. Notation of coordination requirements.

e. Notation of dimensions established by field measurement.

f. Relationship and attachment to adjoining construction clearly indicated.

g. Seal and signature of professional government if specified.

2. Paper Sheet Size: Except for templates, patterns, and similar full-size Drawings, submit Shop Drawings on sheets at least 8-1/2 by 11 inches, but no larger than 11 by 17 inches.

a. Two opaque (bond) copies of each submittal. Government will return one copy.

b. Three opaque copies of each submittal. Government will retain two copies;

remainder will be returned.

C. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other materials.

1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package.

2. Identification: Permanently attach label on unexposed side of Samples that includes the following:

a. Project name and submittal number.

b. Generic description of Sample.

c. Product name and name of manufacturer.

d. Sample source.

e. Number and title of applicable Specification Section.

f. Specification paragraph number and generic name of each item.

3. Email Transmittal: Provide PDF transmittal. Include digital image file illustrating Sample characteristics, and identification information for record.

4. Web-Based Project Software: Prepare submittals in PDF form, and upload to web- based Project software website. Enter required data in web-based software site to fully identify submittal.

5. Paper Transmittal: Include paper transmittal including complete submittal information indicated.

6. Disposition: Maintain sets of approved Samples at Project site, available for quality-control comparisons throughout the course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set.

a. Samples that may be incorporated into the Work are indicated in individual Specification Sections. Such Samples must be in an undamaged condition at time of use.

b. Samples not incorporated into the Work, or otherwise designated as Government's property, are the property of Contractor.

7. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.

a. Number of Samples: Submit one full set of available choices where color, pattern, texture, or similar characteristics are required to be selected from manufacturer's product line. Government will return submittal with options selected.

Bureau of Land Management 013300 - 6 Submittal Gila Box Bonita Creek Road GLHN #20049.01 Procedures

8. Samples for Verification: Submit full-size units or Samples of size indicated, prepared from same material to be used for the Work, cured and finished in manner specified, and physically identical with material or product proposed for use, and that show full range of color and texture variations expected. Samples include, but are not limited to, the following: partial sections of manufactured or fabricated components; small cuts or containers of materials; complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets; and components used for independent testing and inspection.

D. Product Schedule: As required in individual Specification Sections, prepare a written summary indicating types of products required for the Work and their intended location. Include the following information in tabular form:

1. Type of product. Include unique identifier for each product indicated in the Contract Documents or assigned by Contractor if none is indicated.

2. Manufacturer and product name, and model number if applicable.

3. Number and name of room or space.

4. Location within room or space.

E. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, contact information of governments, and other information specified.

F. Design Data: Prepare and submit written and graphic information indicating compliance with indicated performance and design criteria in individual Specification Sections. Include list of assumptions and summary of loads. Include load diagrams if applicable. Provide name and version of software, if any, used for calculations. Number each page of submittal.

G. Certificates:

1. Certificates and Certifications Submittals: Submit a statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.

Provide a notarized signature where indicated.

2. Installer Certificates: Submit written statements on manufacturer's letterhead certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.

3. Manufacturer Certificates: Submit written statements on manufacturer's letterhead certifying that manufacturer complies with requirements in the Contract Documents.

Include evidence of manufacturing experience where required.

4. Material Certificates: Submit written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents.

5. Product Certificates: Submit written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents.

6. Welding Certificates: Prepare written certification that welding procedures and personnel comply with requirements in the Contract Documents. Submit record of Welding Procedure Specification and Procedure Qualification Record on AWS forms. Include names of firms and personnel certified.

H. Test and Research Reports:

1. Compatibility Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion.

Bureau of Land Management 013300 - 7 Submittal Gila Box Bonita Creek Road GLHN #20049.01 Procedures

2. Field Test Reports: Submit written reports indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract Documents.

3. Material Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents.

4. Preconstruction Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of tests performed before installation of product, for compliance with performance requirements in the Contract Documents.

5. Product Test Reports: Submit written reports indicating that current product produced by manufacturer complies with requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.

6. Research Reports: Submit written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project. Include the following information:

a. Name of evaluation organization.

b. Date of evaluation.

c. Time period when report is in effect.

d. Product and manufacturers' names.

e. Description of product.

f. Test procedures and results.

g. Limitations of use.

1.8 CONTRACTOR'S REVIEW

A. Action Submittals and Informational Submittals: Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents.

Note corrections and field dimensions. Mark with approval stamp before submitting to Government.

B. Contractor's Approval: Indicate Contractor's approval for each submittal. Include name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.

1. Government will not review submittals received from Contractor that do not have Contractor's review and approval.

1.9 GOVERNMENT’S REVIEW

A. Action Submittals: Government will review each submittal, indicate corrections or revisions required, and return it.

1. PDF Submittals: Government will indicate, via markup on each submittal, the appropriate action.

2. Paper Submittals: Government will stamp each submittal with an action stamp and will mark stamp appropriately to indicate action.

B. Informational Submittals: Government will review each submittal and will not return it or will return it if it does not comply with requirements. Government will forward each submittal to appropriate party.

Bureau of Land Management 013300 - 8 Submittal Gila Box Bonita Creek Road GLHN #20049.01 Procedures

C. Partial submittals prepared for a portion of the Work will be reviewed when use of partial submittals has received prior approval from Government.

D. Incomplete submittals are unacceptable, will be considered nonresponsive, and will be returned for resubmittal without review.

E. Government will return without review submittals received from sources other than Contractor.

F. Submittals not required by the Contract Documents will be returned by Government without action.

PART 2 - PRODUCTS (Not Used)

END OF SECTION 013300

Bureau of Land Management 014000 - 1 Quality Gila Box Bonita Creek Road GLHN #20049.01 Assurance

SECTION 014000 – QUALITY CONTROL/QUALITY ASSURANCE

PART 1 - GENERAL

1.1 DEFINITIONS

A. Quality Control - planned and specific actions or operations necessary to produce a product that complies with the contract documents. Quality control consists of actions, inspections, sampling and testing necessary to ensure the work is in compliance with the contract documents and to control production and construction processes. Quality control is key to the construction sequence to quickly determine when the work is out of compliance with the contract documents and to respond to correct the situation and bring the work into compliance. Quality control is the responsibility of the CONTRACTOR.

B. Quality Assurance – planned and systematic observations, testing and actions to verify the work complies with the contract documents. Quality assurance includes oversight of the CONTRACTOR’s quality control, verifying the results of the CONTRACTOR’s testing and additional assurance sampling and testing. The Government will provide quality assurance at a level determined necessary by the Contracting Officer.

C. Verification/Compliance Testing – sampling and testing which is carried out independent of the CONTRACTOR’s quality control testing to confirm/verify the work complies with the contract documents. The frequency of verification/compliance testing will be determined by the Contracting Officer. Verification/compliance testing will not be used to determine construction procedures or operations (i.e. rolling patterns, lift thickness, etc.). Verification/compliance testing, if required, will be provided by the Contracting Officer.

1.2 SUBMITTALS

A. Contractor shall conduct testing and prepare submittals according to the SUBMITTALS SCHEDULE.

B. All sampling and testing shall be performed by the Contractor or by a qualified third-party testing agency as defined in the contract documents, at CONTRACTOR expense.

C. Submit records of all CONTRACTOR tests to the Contracting Officer within 24 hours of the testing.

The Quality Control laboratory is to notify the CONTRACTOR and Contracting Officer promptly of irregularities or deficiencies observed in the Work during performance of the Quality Control Testing.

PART 2 - PRODUCTS (Not Used)

PART 3 -…