Attachment 9 – Question and Answers
Solicitation Number: 140L0623R0012
PROJECT DESCRIPTION: GAOA Grand Junction Air Center Tanker Base Repair Design/Build
1. Will there be a second site visit for contractor that make it to phase two?
Response: Yes, we will offer another site tour for all contractor that make it to phase two
2. Will other forms of past performance be acceptable? CPARS? USACE? NAVFAC?
Response: Yes, we will review CPARS. If you would like any other past performance to be reviewed, please follow the process outlined in the solicitation.
3. Will the concrete be removed after the tank farm is relocated?
Response: No, the tank farm concrete will be left and the contractor will pave over it to make a parking lot
4. Will there be a new sidewalk installed from the air tanker base to the tank farm parking lot?
Response: Yes, the contractor will put in a new sidewalk that connects the new tanker base to the tank farm parking lot.