140L0621Q0042 Page 1 of 1 Attachment 3
OMDPNM Post and Fence Replacement
Las Cruces, New Mexico
Contractor Q&A
140L0621Q0045 Amendment 1 – Attachment 4 Questions and Answers
1. Based on the estimated magnitude of this project, will a bid bond be required?
Answer: Please refer to the solicitation section 52.228-13 Alternative Payment Protections (July
2000).
2. What is the period of performance (POP)?
Answer: 45 days.
3. Can we camp onsite?
Answer: Yes but can only occupy a site for no more than 14 consecutive days.
4. Can we build the new fence a foot away from the old fence to minimize down fence?
Answer: No, fence needs to be in the same place.
5. Will possible weather delay days be added to POP if needed?
Answer: Weather delay days may be added in accordance with clauses FAR 52.236-3 Site investigations and conditions affecting the work.