Attachment_5-_Questions_and_Answers_0001.pdf
PDF 80 KB Posted
- Attached to
- ELECTRICAL CABLE & OUTLET INSTALLATION Federal contract opportunity
- Solicitation number
- 140G0324Q0089
About this file
This document includes an attachment of questions and answers related to a federal contract solicitation for electrical cable and outlet installation work. The solicitation is for installing new electrical circuits and outlets at a US Geological Survey facility, with a preference for using existing raceways and conduits where possible and allowing surface mounting. Some wall penetrations may be necessary for transitions between rooms and existing electrical panels. The attachment clarifies that only electrical work is included in the scope and that a new countertop being installed by the government is not part of the contract.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140G0324Q0089_Amd_0001.pdf | ||
| Attchment_2__Circuit_Location_Sketch.pdf | ||
| Attachment_3__Floor_Plan_and_Electrical_Drawings.pdf | ||
| Attachment_1__Wage_Determination.pdf | ||
| Sol_140G0324Q0089.pdf | ||
| Attachment_4__Equipment_List_by_Room.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 5: Questions and Answers
1. Is there other CSI categories other than electrical involved?
A: Refer to SOW Section 3 Technical Requirements and Section 4 Deliverables.
2. The technical representative mentioned about new casework in rm. D101A. Please confirm offer to include this item.
A: A new countertop that is provided and installed by the government was referenced in location of the placement for the new electrical circuits. The inclusion of the countertop is not offered in this contract. Refer to SOW Section 3 Technical Requirements and Section 4 Deliverables.
3. The scope work indicates no penetration of walls during the work. Please confirm all wiring to surface-mounted?
A: Refer to SOW Section 3 Technical Requirements and Section 4 Deliverables. It is preferred to use existing raceways and conduit paths where possible. Surface mounting is acceptable. Some wall penetrations may be necessary to transition from rooms, hallways, existing panels, etc.
File details come from the government source that posted it. Updated .