Revised_SOW_2022_for_RFQ_0002.docx
DOCX document 17 KB Posted
- Attached to
- MARINE SHOP SERVICES BLANKET PURCHASE AGREEMENT
- Solicitation number
- 140G0122Q0218
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140G0122Q0218_Amd_0002.pdf | ||
| Sol_140G0122Q0218_Amd_0001.pdf | ||
| Revised_SOW_2022_Changes_in_POP_HN_modified_to_compete_0001.docx | DOCX document | |
| Sol_140G0122Q0218.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE-BASED WORK STATEMENT
I. GENERAL INFORMATION
A. Introduction USGS requires the use of marine shop equipment services to carry out the mission of the USGS St. Petersburg Coastal and Marine Science Center.
B. Background This is to request for quotes from all technically qualified marine shop equipment services The review determined marine shop use required a separate procurement method and this request only covers those services.
C. Scope Provide marine shop service and equipment on an as needed basis to include but not limited to depth testing and simulation, welding, cutting, bending, woodworking, and on-site fabrication, or repair of components used by USGS for research.
D. Annual information Machine shop vendor shall maintain an annual log for the work performed. Annual funding is not expected to exceed $30,000; $150,000 for the life of the contract.
II. WORK REQUIREMENTS
A. Technical Requirements
1. Marine shop work requirements include, but not limited to design, fabrication, and modification or repair of USGS components used for field research.
2. Vendor will provide the personnel and equipment for:
1. expert welding including TIG, MIG, electric arc, and spot welding
2. woodworking including routers, sanders, and crafting tools
3. cutting, bending, or punching metal
3. USGS will bring components to the vendor location for review, analysis, and discussion on any modifications.
4. Criteria for acceptance of Product or Service.
The product will be accepted when USGS design specifications are met based on each requirement.
B. Deliverables
1. Delivery dates for work/product to be completed and point of delivery based on requirement provided. To be determined with each requirement or call order.
III. SUPPORTING INFORMATION
A. Place of Performance shall be the vendor facilities.
B. Period of Performance Award date -8/5/27.
BASE YEAR: August 6, 2020, Through August 19 2023 OPTION YEAR 1: August 20, 2023, Through August 19, 2024 OPTION YEAR 2: August 20, 2024, Through August 19, 2025 OPTION YEAR 3: August 20, 2025, Through August 19, 2026 OPTION YEAR 4: August 20, 2026, Through August 19, 2027
Call orders / work to be completed on or before date determined with each requirement.
C. Government Furnished Property (GFP): No GOV property required.
D. Special Considerations. Key personnel qualifications.
1. Contractor must provide all equipment, labor, and tools to perform the work.
2. Data Rights, Safety, Environment – USGS retains all rights to data, specifications of parts, and intellectual property.
3. Security/Privacy issues FISMA and 508 do not apply. No access to USGS IT systems will be required. Should contractor assist with installation, it will be via electronic means or contractor / vendor will be escorted on site and monitored by USGS personnel.