140G0120Q0160-0001_0001.pdf
PDF 225 KB Posted
- Attached to
- PENTHOUSE WALL REPAIR Federal contract opportunity
- Solicitation number
- 140G0120Q0160
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140G0120Q0160_Amd_0001.pdf | ||
| Solicitation Attachments.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140G0120Q0160 x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
GNB
Reston VA 20192 12201 Sunrise Valley Drive 205 National Center USGS OAG National Acq. Branch
GNB
RESTON VA 20192
12201 SUNRISE VALLEY DRIVE
205 NATIONAL CENTER
USGS NATIONAL ACQUISITION BRANCH
07/01/20200001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
06/09/2020
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Amendment 0001 is issued to provide answers to offeror questions. See attached document, QandA_140G0120Q0160_v1.
For questions regarding this solicitation, please contact:
Vicky Williams, Contract Specialist vwilliams@usgs.gov
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Karen Phillips
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Questions and Answers v1 Solicitation Number 140G0120Q0160
Q1. What is the make/model of the siding installed last year on the other Penthouse walls?
A1. We do not have the make/model of the siding installed last year.
Q2. What is the wall panel thickness and material? What is the substrate?
A2. Current walls are insulated metal walls; believe .26g with foam.
Q3. Is the exterior coating smooth or aggregate?
A3. Smooth
Q4. If sections of a wall are compromised due to decay, can like and kind material be put in its place rather than trying to find an exact match from 24 years ago?
A4. Yes
Q5. Does rust inhibitor need to be applied over the entire body of existing walls since all walls have been exposed to oxygen and water?
A5. No, only on portions where rust is evident.
Q6. How old is the roof? Is it a TPO, EPDM, Torch down, or PVC?
A6. Roof is 2013. It is rubber membrane.
Q7. Can the roof to wall flashing remain with new being applied over the existing?
A7: If talking about parapet, yes
Q8. Are there leaks occurring now near the roof to wall flashings?
A8. There have been leaks. Unaware of where located.
Q9. Will removing and replacing the coping cap cause roof damage to upper penthouse roofing material?
A9. Parapet cap does not need to be removed – If contractor deems necessary, please see SOW pertaining to lightning protection.
Q10. What manufacturer produces the desired .26 gauge steel ribbed siding to match last year’s siding?
A10. We do not have the manufacturer of the siding installed last year.
Q11. Can the roof structure sustain a staging area with siding materials, or does the staging need to be grounded?
A11. Staging of materials can be done on roof – no electric/motorized lifts.
Q12. If materials are grounded, what area is allowable for a telescopic handler?
A12. Near the N2 door.