This is a Questions and Answers document (Amendment 1) for solicitation #140FGA26R0044, White Horse Hill National Game Preserve Water Main Extension, issued by the Department of Interior. The document addresses three items: a period of performance modification, pipe material specifications, and site visit clarification.
The period of performance has been revised from January 4, 2027 to April 4, 2027 to May 15, 2027 to August 15, 2027 to accommodate North Dakota ground conditions, where frost penetrates up to 6 feet below the surface and prevents excavation during winter months. Regarding pipe materials, the response clarifies that horizontal drilling is minimum and additional drilling may be used. The project specifies three required drilling areas and one optional area: SDR9 250 PSI HDPE under the lake (1,375 linear feet), SDR 17 250 PSI under a gate (250 linear feet), SDR 17 250 PSI optional drilling (400 linear feet), and SDR 17 250 PSI 3-inch pipe within steel casing (50 linear feet). The response indicates that if 4-inch HDPE is substituted for 3-inch HDPE under the lake, a water pressure model may be required to verify requirements. All other 3-inch PVC pipe installation will occur via open trench or horizontal drill. The contracting officer notes that a site visit occurred on November 12, 2026 at 11:00 AM local time, with an invitation for interested parties who were unsuccessful in attending to contact Samantha_LaGue@ios.doi.gov to schedule an alternative visit.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140FGA26R0044_Amd_0001.pdf | ||
| Drawings.pdf | ||
| Notice_to_Offerors.pdf | ||
| DOL_Wage_Determination.pdf | ||
| SOW.pdf | ||
| Price_Schedule.pdf | ||
| Sol_140FGA26R0044.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions & Answers - Amendment 1
White Horse Hill National Game Preserve Water Main Extension
Solicitation # 140FGA26R0044 Questions and Answers
1. Period of Performance: 1/4/2027 – 4/4/2027 – This is not the time in North Dakota when outside utility work gets completed. The ground freezes in this area and doesn’t allow for excavation to take place easily due to the frost going in the ground up to 6 ft below the surface. I would recommend that the period of performance be changed to May 15, 2027, to August 15, 2027. The frost will not be out of the ground at the earliest by May 15 in this part of the country and that will be essential to dig holes and backfill.
Response: The period of performance for this project has been changed to May 15, 2027, to August 15, 2027.
2. The size of HDPE pipe to be used for the bore is 3” HDPE pipe. So boring and pipe experts state that 800-1000 ft. is the maximum bore length that should be used for small diameter HDPE. They recommend either a larger diameter pipe or using a fusible PVC in place of the HDPE. The 3” HDPE when used in longer bores has been known to stretch and break due to the strength of the pipe.
a) Would 4” HDPE be acceptable in place of the 3” HDPE?
b) Would 4” FPVC be acceptable in place of the 3” HDPE?
Response:
a) See construction note 7 on sheet 3 of 8. The horizontal drilling is minimum, and additional drilling can be used. Does the 800-1,000 linear ft pertain to both the SDR 17 PVC 250 and the
SDR9 250 PSI HDPE?
There are 3 areas that are listed as required drilling and 1 that is optional.
• SDR9 250 PSI HDPE that is under the lake at 1,375 LF
• SDR 17 250 PSI that is under the gate at 250 LF.
• SDR 17 250 PSI that is optional shown on the site plan at 400 LF. (optional)
• SDR 17 250 PSI 3-inch pipe within the steel casing at 50 LF.
All other 3-inch PVC pipe is via open trench or horizontal drill.
If we need to increase HDPE diameter pipe to 4-inch under lake, we may have to run a quick water model to verify pressure requirements.
b) Same response to a)
3. This was not a question that was submitted, but clarification from the Contracting Officer of this project. There was a site visit held on November 12, 2026, at 11:00 AM local time for this project. Initially, there was some confusion about where and who to
Questions & Answers - Amendment 1 meet, but the site visit did end up taking place shortly after its original 11:00 AM start time. If you RSVP’d for the November 12, 2026, site visit but were unsuccessful in taking place with the one that did happen that day and would like to schedule another one, please reach out to me via email at Samantha_LaGue@ios.doi.gov