This file is an Amendment 2 Questions and Answers document addressing clarifications for the MN Fergus Falls WMD Parking Rehab design contract solicitation (140FF027R0006).

The Q&A addresses three primary scope clarifications for the Architect-Engineer (A-E) firm: (1) Topographic and Site Boundary Surveys—offerors should reference the Phase 2-3 Statement of Work (SOW) Section V.A.3 for guidance on whether to utilize existing survey datasets or perform new, complete topographic and boundary surveys for each site area across CLINs 00010-00050; (2) Geotechnical Engineering and Testing Services—the Government will not contract geotechnical investigations separately, requiring the A-E contractor to solicit, subcontract, and manage all necessary geotechnical field investigations (soil borings, pavement core sampling, percolation testing, and subgrade evaluations) within the A-E design contract, as detailed in Section V.A.4 of the SOW; and (3) Project Footprint and Stormwater Management—the final design limits will be determined by the Engineer of Record (EOR), and if stormwater retention/detention is required by Authorities with Jurisdiction or permitting agencies, the EOR must perform such work as part of the contract scope, with reference to Section I.A of the SOW for general project objectives. These clarifications establish that the A-E firm bears responsibility for comprehensive site investigations, design determinations, and all associated civil engineering and environmental compliance work related to the parking area rehabilitation project.

View the file

Other files

File Type Posted
Sol_140FF027R0006_Amd_0002.pdf PDF
Sol_140FF027R0006_Amd_0001.pdf PDF
Sol_140FF027R0006.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Topographic & Site Boundary Surveys Question: The RFP documentation includes existing conditions survey information. Is it the Government’s intent for the A-E firm to utilize these existing survey datasets as the base for design, or should offerors include a task scope and cost structure for performing new, complete topographic and boundary surveys for each site area (CLINs 00010–00050)?

Answer – Please reference 'Phase 2-3 SOW_REV SEPT2026.pdf' specially Parts V.A.3.

2. Geotechnical Engineering & Testing Services Question: Our preliminary technical approach includes geotechnical oversight and coordination. If award is made, will geotechnical investigation services (e.g., soil borings, pavement core sampling, percolation testing, and subgrade evaluations) be contracted directly by the Government/Owner, or is the A-E contractor expected to solicit, sub-contract, and manage all necessary geotechnical field investigations within this A-E design contract?

Answer - The Government does not plan to directly contract geotechnical investigations outside this Contract. Reference 'Phase 2-3 SOW_REV SEPT2026.pdf' specially Parts V.A.4.

3. Project Footprint, Impervious Surface & Stormwater Management Question: Are the final design limits intended to match the existing spatial footprint of the current parking lot, overflow areas, driveways, and laydown areas? If the proposed design expands the impervious surface footprint beyond existing boundaries, will additional stormwater retention/detention and civil site drainage modeling be required as part of this scope?

Answer - The Final Design limits will be determined by the EOR and if stormwater retention/detention is required per the Authorities with Jurisdiction/Permitting Agencies and/or EOR, EOR should perform such work as part of this Contract. Reference 'Phase 2-3 SOW_REV SEPT2026.pdf' specially Parts I.A for general project objectives.