This is a Statement of Work for roof replacement services at a U.S. Fish and Wildlife Service (USFWS) facility located at 610 Wilder Road on Big Pine Key, Florida. The pole barn structure, measuring approximately 30' by 110' and built in 2010, requires complete roof replacement to address lifecycle deterioration and prevent structural damage, water intrusion, and storm-related issues. The work order is #2026823338 with Asset #10077048, dated November 4, 2026.

The contractor must provide complete demolition and removal of the existing metal roofing system, evaluation and repair of roof framing, and installation of a new aluminum 5V crimp metal roofing system installed in 30-foot lengths without overlaps. The new roof must consist of aluminum panels at minimum 20-gauge thickness (.032 inch), comply with wind uplift resistance standards per ASCE 7 and Monroe County, Florida building codes, and be certified by Factory Mutual (FM), Underwriters Laboratories (UL), or ASTM testing procedures. All work must meet National Roofing Contractors Association (NRCA), Sheet Metal and Air Conditioning Contractors National Association (SMACNA), International Building Code, OSHA, and manufacturer specifications. The contractor shall furnish all labor, materials, equipment, temporary facilities, and flashing; obtain required permits; coordinate with facility personnel; and protect wildlife including endangered Key deer. A 5-year manufacturer warranty covering materials and workmanship is required, along with a 2-year contractor installation warranty. Deliverables include a project schedule, construction quality control plan, submittal register, and closeout documents including executed warranties and Davis-Bacon certified payrolls.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Roof Replacement for Pole Barn

Big Pine Key, Florida 4 November, 2026 Asset #: 10077048

Work Order #: 2026823338

PART 1. GENERAL

1.1. The Pole Barn is located at 610 Wilder Road on Big Pine Key, Florida. This structure is owned by the U.S. Fish and Wildlife Service and is part of the Florida Keys National Wildlife Refuge Complex. The pole barn is approximately 30’ by 110’. The pole barn was built in 2010, and the current roof has outlived its lifecycle. This work is necessary to address deficiencies in the existing roof and to provide a reliable, long-term building envelope that protects federal assets, supports continued facility use, and reduces the risk of future structural deterioration, water intrusion, and storm-related damage. The work shall include demolition, any necessary structural framing modifications - rafter, purlin, and fascia replacement , and final installation of the new roofing system in accordance with applicable building codes, and manufacturer requirements. The Roof Replacement for the Pole Barn scope of work shall include all associated work, including but not limited to:

a. This project consists of the complete removal and replacement of the existing metal panels on the subject building. The Contractor shall evaluate the complete existing roof framing following removal of the existing roofing system and shall repair, reinforce, replace, or reconstruct all deteriorated, damaged, structurally inadequate, improperly installed, or non-code-compliant structural members necessary to provide a complete, structurally sound, code-compliant roof structure capable of supporting the new roofing system and resisting applicable design loads. All such work shall be included in the base bid/quote and shall not be considered optional work. The work is intended to provide a durable, code-compliant, wind-resistant, and corrosion-resistant roof assembly suitable for long-term service in a coastal and high-exposure environment.

b. The Contractor shall furnish all labor, supervision, materials, equipment, tools, transportation, temporary protection, inspections, disposal, and incidental items necessary to complete the work. All work shall be performed in accordance with applicable federal, state, and local codes and regulations, manufacturer installation requirements, and approved construction documents.

c. The work shall include the complete removal and lawful disposal of the existing roofing system, including roofing material, flashing, trim, fasteners, and other associated roof components. Any deteriorated, damaged, or non-code-compliant roof framing, or related structural members encountered during demolition that would affect the performance or integrity of the new roof system shall be replaced as part of this project.

d. The new roof shall consist of a complete aluminum 5v crimp metal roofing system installed over the roof framing in 30’ lengths to avoid the overlap of sheets and associated issues of the existing roof. Roofing materials and attachment methods shall be suitable for the building location and exposure and shall meet applicable wind uplift, weather resistance, and corrosion resistance requirements.

e. The Contractor shall provide and install all flashing and trim required for a complete and functional roof assembly, including but not limited to drip edge, fascia trim, and all transition or termination flashing necessary to ensure the roof system is fully weatherproofed. All roof system components shall be compatible in material and finish to minimize the potential for galvanic corrosion and premature failure.

f. All work shall comply with applicable permitting and inspection requirements. The Contractor shall obtain all required permits unless otherwise directed by the USFWS and shall coordinate and pass all required inspections. Prior to installation, the Contractor shall submit applicable product data, manufacturer specifications, shop drawings or layout drawings if required, color selections, and warranty information for review and approval.

g. At the conclusion of the project, the Contractor shall remove all construction debris, unused materials, packaging, and waste from the site and leave the project area in a clean and serviceable condition, this includes removing all screws/nails on the ground of the work area and a final search of the entire area with a magnetic sweep. Final acceptance shall be contingent upon completion of all work, satisfactory inspection of the finished roof system, delivery of all required closeout documentation, and confirmation that the completed roof assembly is structurally sound, watertight, code-compliant, and fully functional.

1.2. General Requirements: Design in accordance with all applicable Federal, State and Local codes and regulations (latest edition at the time of contract award) with the following establishing the minimum requirements:

A. National Roofing Contractors Association (NRCA) B. Sheet Metal and Air Conditioning Contractors National Association (SMACNA) C. International Building Code, latest edition D. NFPA 101 Life Safety Code E. International Mechanical Code F. ASHRAE Handbook of Fundamentals G. ASHRAE/IENSA 90.1 - 2016 Energy Standard for Buildings.

H. OSHA Regulations (Federal and State) I. Consumer Product Safety Commission 16 CFR 1201 Safety Standards for Architectural

Glazing Materials J. Clean Water Act

K. Architectural Barriers Act L. Americans with Disabilities Act (ADA) Accessibility Guidelines M. U.S. Fish and Wildlife Service Prescriptive Specifications

1.3. Work is comprised of ancillary or required design, permitting, construction and other services required by the Contract Documents, including procuring and furnishing all materials, equipment, services and labor reasonably inferable from the Contract Documents.

2.1. Shell - Roof Replacement for Pole Barn

2.1.1. Provide the roofing system:

A. Provide roof systems compatible with the facility function, construction, and service conditions. Provide complete roof system design and construction services for the entire facility roof system, including all ancillary and incidental work necessary for a complete, new, roof system installation.

B. Provide a roofing system that resists wind uplift pressures calculated in accordance with American Society of Civil Engineers (ASCE) 7. Uplift resistance must be validated by applicable Factory Mutual (FM), Underwriters Laboratories (UL) or American Society for Testing and Materials (ASTM) uplift resistance test procedures.

C. Slope conversions from low slope to steep slope roofing systems must specifically address temporary waterproofing protection where new framing connections penetrate the existing low slope system.

D. Provide aluminum panels formed at the manufacturing plant and conditioned for flatness. Determine panel thickness by the requirements of NRCA, Roofing and Waterproofing Manual, but not less than 24 gauge for panels less than 16 inches wide (400 mm), and 22 gauge for panels 16 inches (400 mm) wide or greater. All panels greater than 12 inches (300 mm) wide must have performed reinforcing ribs or embossed for stiffening. The minimum gauge for aluminum panels must be 20-gauge, .032 inch thick (.8 mm thick) or greater. A single panel will run the 30’ length of the roof and under no circumstances should panels be overlapped to run the 30’ length. The overhang should extend to the end of the existing rafters.

E. The 5V Crimp Metal Roof system covered under this specification must include the entire roofing system; the aluminum roof panels, fasteners, connectors, roof securement components, and assemblies tested and approved in accordance with ASTM E 1592. In addition, the system must consist of panel finishes, slip sheet, insulation, all accessories, components, and trim and all connections with roof panels.

This includes roof penetration items such as vents, curbs, skylights; interior or exterior gutters and downspouts; eaves, ridge, hip, valley, rake, gable, wall, or other roof system flashings installed and any other components specified within this contract to provide a weathertight roof system.

a. Provide 5V Crimp roofing panels.

b. Panel Protection - Treat exposed cut edges with compatible coating comparable to the factory applied coating system for corrosion protection.

c. Sealants - Provide non-curing, non-skinning butyl based sealants and tapes for concealed locations such as within laps and under eaves. Provide polyurethane and curing butyl elastomeric sealants for exposed locations such as along top edge of surface mounted counter flashings.

d. Factory Color Finish - Provide factory applied, baked coating to the exterior and interior of metal wall panels and metal accessories, silver or galvalume in color.

F. Provide flashing and sheet metal in accordance with roof manufacturer’s printed installation instructions and in compliance with NRCA and SMACNA recommendations.

G. Provide rails or guards as required by the OSHA, the International Building Code or other applicable safety standards.

H. Lightning protection component penetrations and attachments must be sealed and flashed and anchored in a permanent manner and in a manner to avoid the degradation of the watertight integrity of the roof system. Do not cut or otherwise disturb the roof membrane. Mastic seals in the plane of the roof are unacceptable. Anchor plates set in mastic must be set on roof surface cleaned of aggregate and loose material prior to mastic application.

I. Design requirements - Wind Uplift Resistance: Determine the required wind uplift resistance based on American Society of Civil Engineers (ASCE) 7 wind loading calculations or applicable building code requirements and Monroe County, Florida Building code. When a rated system is specified, ensure the specified roof system is capable of meeting the wind uplift resistance specified. Where non-rated systems may be allowed and used, delineate calculated values in the roof specification or drawings.

Utilize independently tested and rated roof systems, such as Factory Mutual (FM), Underwriters Laboratory (UL), and Single Ply Roofing Industry (SPRI). Develop and deliver a Quality Management Plan and Test Plan.

J. Furnish manufacturer's no dollar limit materials and workmanship warranty for the roofing system. The warranty period must not be less than 5 years from the date of Government acceptance of the work. The warranty must be issued directly to the Government. The warranty must provide that if within the warranty period the metal roofing system becomes non-watertight or shows evidence of corrosion, perforation, peeling paint, rupture or excess weathering due to deterioration of the roofing system resulting from defective materials or workmanship the repair or replacement of the defective materials and correction of the defective workmanship must be the responsibility of the roofing system manufacturer. Repairs that become necessary because of defective materials and workmanship while roofing is under warranty must be performed within 30 days after notification. Failure to perform repairs within the specified period of time may constitute grounds for having the repairs performed by others and reimbursement for costs may be sought by the Government. Provide a 2-year contractor installation warranty. Coating must not show a color change greater than 5 NBS color units in accordance with ASTM D2244, and not show chalking in excess of 10 in accordance with ASTM D4214. Provide a minimum five-year fungus resistance warranty in southern climate and areas susceptible to fungus growth on roofing materials.

PART 3. ANCILLARY DESIGN AND CONSTRUCTION NOTES AND DELIVERABLES

3.1. Provide a project schedule reflective of the critical path or other phase of work at the Preconstruction Meeting or issuance of notice to proceed for Government review and/or approval.

3.2. Provide a construction quality control (CQC) plan for approval that details procedures for submittal review and approval, testing, completion inspections, and QC certifications and documentation necessary to provide design, materials, equipment, workmanship, fabrication, construction and operations which comply with the requirements of this scope of work.

3.3. Develop and provide a submittal register and update this Register as submittals are logged and processed. Submittals shall be sequentially numbered. A completed submittal register shall be submitted with the Project Closeout Documents. The Contractor’s Site Superintendent shall maintain a file of approved submittals for reference purposes. This Submittal file shall be subject to inspection by the FWS without advance notice. Product samples may be required.

3.4. The surrounding area will be used and maintained by Facility personnel and volunteers.

Care should be taken to coordinate all construction activities with the Facility personnel. The contractor shall have the ultimate responsibility for safety on the project site at all times, from issuance of the Notice to Proceed until final completion and acceptance of the project by the Contracting Officer. Ensure that all onsite activates, equipment, and facilities constructed by the contractor, subcontractor, or supplier conform fully to the standards of the Department of Labor, Occupational Safety and Health Administration (OSHA) 29 CFR 1926 and 1910; and DOI and FWS policies.

3.5. The construction site and surrounding area are actively used by wildlife, including the endangered Key deer. Construction personnel shall not approach or harm wildlife. Movement of equipment and supplies should be conducted carefully. All construction materials should be secured from wildlife, and all trash must be disposed of properly.

3.6. Before work begins, the contractor shall coordinate with local utility companies to locate and protect all utilities traversing the Project.

3.7. Maintain in operating condition all active utilities servicing other facilities. Repair any damage to active utilities servicing remaining facilities. All work will be in accordance with local, state and national building codes and local regulations governing the utility concerned.

3.8. Furnish all temporary facilities and utilities as needed including heat, light, power, telephone, sanitary facilities, waste receptacles, job offices, material handling equipment, temporary construction aides, and storage enclosures; except water may be used for construction purposes at no cost if it does not adversely impact the operations of the station.

The contractor is responsible for all temporary connections and disconnections.

3.9. The contractor shall install and maintain barricades and warning devices as necessary to safeguard the public, workers, and government personnel.

3.10. Closeout Procedures

Final Inspection: Submit a request in writing to the CO requesting the Final Inspection.

Notify the COR at least 10 calendar days prior to the anticipated date of completion of all work. The COR will proceed with Final Inspection as promptly as practicable. The time required for such Final Inspection and for making any corrections as a result thereof shall be included in the contract performance time. The Contractor representative responsible for the work shall be present at the Final Inspection and shall submit a preliminary list of unfinished work prior to Final Inspection.

3.11. Closeout Documents

3.11.1. Submit fully executed manufacturer's standard material, product, and equipment warranties. All warranties must be established in the name of the facility. Warranties assigned to prime or subcontractors will not be accepted and will be returned for correction. Additionally, please submit Davis-Bacon certified payrolls and release of claims form before submission of final invoice.

END OF STATEMENT OF WORK