This is a Statement of Work (SOW) for pavement preservation services at Tamarac National Wildlife Refuge in Rochert, Minnesota. The U.S. Fish and Wildlife Service, Midwest Region, requires the contractor to apply crack sealing, patching, slurry seal, and pavement markings to the Entrance Road and Visitor Center Parking (Route 900), totaling 4,826 square yards of surface area. The work must preserve and extend the service life of the existing asphalt pavement.

The period of performance begins upon issuance of the Notice to Proceed with a 90-day completion deadline. Work is restricted to 6:00 a.m. to 6:00 p.m., Monday through Friday, with no work permitted on federal holidays; work should ideally occur on Mondays and Tuesdays when the facility is closed to minimize traffic disruption. The contractor must develop a traffic control plan in accordance with the Manual on Uniform Traffic Control Devices, coordinate staging areas and parking lot closures with the Contracting Officer's Representative, and maintain emergency vehicle access. Required submittals include all necessary permits, a schedule of values, detailed construction schedule with major milestones, submittal schedule for material certificates and test results, a traffic control plan, and digital photographs of completed work. Construction specifications require crack sealant compatible with surface overlay and asphalt trail (installed in cracks exceeding 0.5 inches); slurry seal equivalent to SealBest 1000 with a minimum 10-year limited warranty; patching with saw-cut rectangular or trapezoidal sections extending 12 inches into adjacent sound pavement; and pavement markings using MPI #97 latex traffic-marking paint with accessibility compliance to current ADA requirements. All work must comply with state DOT standards, with performance-graded asphalt binders designated per AASHTO M 320, minimum tack coat application of 0.03 to 0.15 gallons per square yard, slurry seal mix application at manufacturer-recommended rates, and a minimum 14-day aging period before pavement marking application. The government point of contact is Alisha Haken, Deputy Project Leader at Tamarac National Wildlife Refuge (218-308-7161), with Brandon Jutz as secondary contact.

View the file

Other files

File Type Posted
Sol_140FF027Q0055.pdf PDF
B03_WD.pdf PDF
A06_Asphalt_overlay_As-Built.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

PAVEMENT PRESERVATION

TAMARAC NATIONAL WILDLIFE REFUGE

ENTRANCE ROAD AND PARKING

REVISED: 7/16/2026

U.S. FISH AND WILDLIFE SERVICE

MIDWEST REGION – REGION 3

Table of Contents Statement of Work…………………………………………………………………………… Points of Contact………………………...………………………………………………...3 Statement of Work………………………………………………………………………...3 Project Location…………………………………………………………………………...3 Project Overview………………………………………………………………………….3 Project Description………………………………………………………………………...3 Period of Performance…………………………………………………………………….4 Temporary Traffic Control………………………………………………………………...4 Staging Areas……………………………………………………………………………...4 Preconstruction Conference……………………………………………………………….4 Submittals…………………………………………………………………………………4 Final Inspection……………………………………………………………………………5 Construction Specifications…………………………………………………………………..….6 Maps and Photos……………………………………………………………………..…...…….13 Route 900………………………………………………………………………………...13

Point of Contact - The U.S. Fish and Wildlife Service Point of Contact for this requirement is:

Alisha Haken Deputy Project Leader Tamarac National Wildlife Refuge, 35704 County Highway 26, Rochert, MN 56578 218-308-7161 (office) 218-849-9867 (cell) Alisha_Haken@fws.gov

Brandon Jutz (secondary) Regional Transportation Coordinator Bloomington, MN 612-713-5407 (office) 571-305-0188 (cell) Brandon_Jutz@fws.gov

Statement of Work – This Statement of Work describes the general performance of the completed project and does not attempt to show the exact construction of the work in complete detail. Provide high-quality completed work that maintains the performance intent established by this document.

Project Location – The project location is the Entrance Road and Visitor Center Parking (Route #900) at the Tamarac National Wildlife Refuge. The Refuge address is 35704 County Highway 26, Rochert, MN 56578.

Project Overview – The U.S. Fish and Wildlife Service (FWS) needs the Contractor to apply crack sealing and slurry seal to the Entrance Road and Visitor Center Parking in order to protect and preserve the condition of the pavement and extend the service life of the pavement.

Project Description –

Route Number Route Name Route Length (mi) Route Width

(FT)

Surface Area (SY) Specified Treatment

900
Visitor Center Pkg
--
--
4,826
Crack sealing1

Patching2 Slurry seal3 Pavement markings4

1 Reference construction specifications for Crack Sealant within SECTION 321216 – ASPHALT PAVING 2 Reference construction specifications for Patching within SECTION 321216 – ASPHALT PAVING 3 Reference construction specifications for Slurry Seal within SECTION 321216 – ASPHALT PAVING 4 Reference construction specifications for Pavement Markings within SECTION 321723 – PAVEMENT MARKINGS

Period of Performance -

Start Date: upon issuance of the Notice to Proceed Completion Date: 90 days after issuance of Notice to Proceed

Work must be performed between 6:00 a.m. and 6:00 p.m., Monday through Friday. No work is allowed on Federal holidays. Ideally, work would take place on a Monday and Tuesday, as the facility is closed to the public and would limit traffic and reduce traffic control issues.

Temporary Traffic Contral - Develop a traffic control plan to ensure contractor and public safety during construction operations.

Unless work is done on a Monday or Tuesday, a portion of the combined parking area must stay open for staff and public-use needs. Coordinate parking lot closures with the Contracting Officer’s Representative and/or with the Deputy Project Leader. Limit construction-caused delays to public and refuge traffic. Immediately open the road to emergency vehicles.

Provide barricades and warning devices as necessary to safeguard the public, workers, and government personnel. Where project work affects public roads, provide signage in accordance with the latest edition of the Manual on Uniform Traffic Control Devices (MUTCD).

Staging Areas – Coordinate the Contracting Officer’s Representative and/or with the Deputy Project Leader regarding potential staging areas.

Preconstruction Conference - prior to starting construction, schedule a virtual meeting with the Contracting Officer, the Contracting Officer’s Representative, Deputy Project Leader, Contractor’s Superintendent, and authorized representatives of major subcontractors.

Submittals –

· Permits: obtain and provide copies of all necessary local, State, and Federal permits and licenses.

· Schedule of values: provide the schedule of values prior to submitting the initial Application for Payment.

· Construction schedule: provide estimated dates and durations of major milestones and when each route will be worked on. Provide the construction schedule prior to submitting the initial Application for Payment. Provide updates to the construction schedule as changes occur.

· Submittal schedule: provide a submittal schedule of material certificates and test results from sampling and testing laboratories. Provide the submittal schedule prior to submitting the initial Application for Payment.

· Traffic control plan: submit a traffic control plan that minimizes construction-caused delays for public and hatchery traffic.

· Photographs: provide digital photos of the completed work at each road and parking area

Final Inspection - submit a written request for final inspection to the Contracting Officer at least 10 days prior to the anticipated completion date. The Contractor’s Superintendent or authorized representative responsible for the work shall be present at the final inspection and shall provide a list of unfinished work. After the final inspection, the Contracting Officer’s Representative will provide the Contractor with a punch list of items that must be completed or corrected.

Government acceptance is contingent upon all of the work described above having been completed following state and federal codes.

Copyright 2011 by The American Institute of Architects (AIA) Exclusively published and distributed by Architectural Computer Services, Inc. (ARCOM) for the AIA

SECTION 321216 - ASPHALT PAVING

Revise this Section by deleting and inserting text to meet Project-specific requirements.

Verify that Section titles referenced in this Section are correct for this Project's Specifications; Section titles may have changed.

GENERAL

SUMMARY

Section includes any work associated with asphalt work.

ACTION SUBMITTALS

Product Data: For each type of product.

QUALITY ASSURANCE

Retain "Manufacturer Qualifications" Paragraph below if required.

Temperature: Do not apply asphalt materials or place asphalt mixes when ground temperature is lower than 50 degrees F or air temperature is lower than 40 degrees F. Measure ground and air temperature in shaded areas away from heat sources or wet surfaces.

Moisture: Do not apply asphalt materials or place asphalt mixes when application surface is wet.

INFORMATIONAL SUBMITTALS

Retain "Material Certificates" Paragraph below to require submittal of material certificates from manufacturers. Retain option if permitting use of recycled materials, which is standard practice.

Material Certificates: For each paving material. Include statement that mixes containing recycled materials will perform equal to mixes produced from all new materials.

QUALITY ASSURANCE

Retain "Manufacturer Qualifications" Paragraph below if required.

Manufacturer Qualifications: Provide an asphalt mix from a production plant that is approved by the local authorities or the state DOT.

Retain "Regulatory Requirements" Paragraph below if asphalt paving work is located on public property and must comply with requirements of state or local DOT. Also retain if referencing these requirements regardless of property ownership.

Regulatory Requirements: Comply with materials, workmanship, and other applicable requirements of the state DOT for asphalt paving work.

Retain "Regulatory Requirements" Paragraph below if asphalt paving work is located on public property and must comply with requirements of state or local DOT. Also retain if referencing these requirements regardless of property ownership.

PRODUCTS

AGGREGATES

Materials shall be in accordance to Section 321500.1.

ASPHALT MATERIALS

Use of performance-graded asphalt binders developed by Superpave has generally replaced asphalt cement. Options in "Asphalt Binder" Paragraph below are examples only. Consult AI or state or local DOT for asphalt-binder recommendations.

Asphalt Binder: Use an Asphalt binder that would be specified for the project location by the state DOT and is designated according to AASHTO M 320.

Tack Coat: ASTM D 977 or AASHTO M 140 emulsified asphalt, or ASTM D 2397 or AASHTO M 208 cationic emulsified asphalt, slow setting, diluted in water, of suitable grade and consistency for application.

Retain "Tack Coat" Paragraph below if required. Tack coat is usually diluted in equal amounts of water and emulsified asphalt. It is usually applied to vertical surfaces of curbs, gutters, cold pavement joints, and structures in the pavement that will be in contact with hot-mix asphalt. Tack coat is also applied to existing pavement surfaces to bond new hot-mix asphalt overlays.

AUXILIARY MATERIALS

Generally retain "Recycled Materials for Hot-Mix Asphalt Mixes" Paragraph below for recycled-materials content, which is standard practice, and for use of recycled materials for LEED Credit MR 4; revise to suit Project.

Recycled Materials for Hot-Mix Asphalt Mixes: Reclaimed asphalt pavement; reclaimed, unbound-aggregate base material; and recycled tires, asphalt shingles, or glass from sources and gradations that have performed satisfactorily in previous installations, equal to performance of required hot-mix asphalt paving produced from all new materials.

Retain "Herbicide" Paragraph below for weed control if required.

Herbicide is not allowed.

MIXES

Retain "Recycled Content of Hot-Mix Asphalt" Paragraph below to specify recycled content if applying for LEED Credit MR 4. Consult authorities having jurisdiction and local hot-mix plants on recycled content of base and surface courses. An alternative method of dealing with these credit requirements is to retain requirement in SECTION 018113.13 "Sustainable Design Requirements - LEED for New Construction and Major Renovations," Section 018113.19 "Sustainable Design Requirements - LEED for Core and Shell Development," or Section 018113.23 "Sustainable Design Requirements - LEED for Schools" that gives Contractor the option and responsibility to determine how these credit requirements will be met.

Recycled Content of Hot-Mix Asphalt: Postconsumer recycled content plus one-half of preconsumer recycled content not less than 10 percent or more than 25 percent by weight.

Surface Course Limit: Recycled content no more than 10 percent by weight.

Retain first option in "Hot-Mix Asphalt" Paragraph below if specifying state or local DOT standard paving mixes or for approval of mixes by state or local DOT if approval of mixes for private work is the practice of authorities having jurisdiction. DOT standard paving mixes will usually be required for public roads. Same paving mixes may also be used for private work. Generally, retain second option below for private work, with or without first option, and for state or local DOT if that is the practice of authorities having jurisdiction.

CRACK SEALANT

Install in cracks or abnormalities that exceed 0.5 inches Use product that is compatible with surface overlay and asphalt trail

SLURRY SEAL

Equivalent to SealBest 1000 Minimum of 10-year limited warranty Durability to withstand light vehicle traffic Mix thickness shall be based on construction techniques recommended by the state DOT or other approved method Retain "Base Course" and "Surface Course" subparagraphs below to identify state or local DOT specifications for each course. Insert binder course in list if required.

EXECUTION

SURFACE PREPARATION

General: Immediately before placing asphalt materials, remove loose and deleterious material, including organic material, from substrate surfaces. Ensure that prepared subgrade is ready to receive paving, if required.

Retain first paragraph below for full-depth asphalt pavement.

Proof-roll subgrade below pavements with heavy pneumatic-tired equipment to identify soft pockets and areas of excess yielding. Do not proof-roll wet or saturated subgrades.

Tack Coat: Apply uniformly to contact surfaces of pavements, curbs, gutters, manholes, and other fixtures according to Section 321216.3.7 Retain "Herbicide Treatment" Paragraph below if weed control is required.

Retain "Tack Coat" Paragraph below if tack coating an existing hot-mix asphalt pavement before placing a hot-mix asphalt overlay.

INSTALLATION TOLERANCES

Meet minimum thicknesses outlined in the drawings. Additional asphalt or base may need to be installed to meet finish surface grades and minimum thickness.

PATCHING

Retain this article if patching existing pavement. Retain "Asphalt Pavement" Paragraph below if existing pavement is asphalt.

Asphalt Pavement: Saw cut perimeter of patch and excavate existing pavement section to sound base. Excavate rectangular or trapezoidal patches, extending 12 inches into perimeter of adjacent sound pavement, unless otherwise indicated. Cut excavation faces vertically. Remove excavated material. Recompact existing unbound-aggregate base course to form new subgrade.

Tack Coat: Before placing patch material, apply tack coat uniformly to vertical asphalt surfaces abutting the patch. Apply according to Section 321216.3.7.

Retain "Portland Cement Concrete Pavement" Paragraph below if existing pavement is portland cement concrete.

Retain "Placing Patch Material" Paragraph below for asphalt or concrete pavement. A single asphalt course is preferred by AI.

Placing Patch Material: Fill excavated pavement areas with hot-mix asphalt base mix for full thickness of patch and, while still hot, compact flush with adjacent surface.

Install in accordance to the drawings.

TACK COAT

Surface Preparation: Clean the existing surface of loose material, dirt, or other deleterious material by approved methods. When the surface is concrete, remove excess joint and crack filler.

Weather Limitations: Apply asphalt tack only when the following apply:

Surface is dry and unfrozen;

Ambient air temperature is above 35 °F (2 °C) and rising; and Weather is not foggy or rain is forecasted before the tack coat will be covered by the work.

ASPHALT APPLICATION

When using slow-setting emulsified asphalt, dilute by adding an equal quantity of water to the emulsified asphalt.

Apply the asphalt tack coat at a rate of 0.03 to 0.15 gallons per square yard (0.15 to 0.70 liters per square meter).

Avoid smearing or staining adjoining surfaces, appurtenances, and surroundings. Spread building paper on the pavement surface at the beginning and end of each asphalt application so distributor flow is started and stopped on the paper to avoid spraying on adjoining surfaces and appurtenances. Remove spillages and clean affected surfaces.

Apply asphalt uniformly at the specified application rate. Do not apply more asphalt than can immediately be covered by work. Correct skipped areas or deficiencies.

Apply the asphalt tack coat uniformly and completely by fogging with a hand spray attachment or by another approved method when application with a distributor spray bar is not practical.

Squeegee the excess asphalt from the surface. Allow the tacked surfaces to completely cure before placing the covering course. Place the covering course within 4 hours of placing the asphalt tack coat.

CRACK SEALANT

Install per the manufacturer’s recommendations.

Cleaning: Prevent debris from entering waterways, areas open to public, or areas designated not to be disturbed. Remove dirt, dust, and other deleterious material from the crack walls and cavity using a stream of air or other approved methods. Blow or brush dry material off the pavement surface.

Sealing and Filling: Dry the crack surfaces with the hot air lance before sealing or filling. Do not seal or fill cracks when the pavement surface temperature is below 35 °F (2 °C) and weather conditions are rainy or foggy.

Submit a copy of and adhere to the manufacturer’s recommendations for heating and applying the hot applied crack material. Heat the material to pouring temperature in a heating kettle and continuously agitate the material.

Warm and dry the crack surfaces using a hot-compressed air lance if the pavement temperature is lower than 50 °F (10 °C) or moisture is present. Keep the lance moving to prevent burning the pavement surface. Place and finish the material within 5 minutes after heating the pavement surface with the lance.

Use an application wand to place material in each crack from the bottom up. Use a squeegee or screed to strike off the material. Crack sealant shall be flush with existing surface.

Any installation of crack sealant shall be installed along the entire crack or abnormalities to create a smooth flush appearance Reseal cracks exhibiting adhesion failure, damage, incomplete filling, foreign objects in the sealant, or otherwise rejected by the CO.

SLURRY SEAL

Install per the manufacturer’s recommendations.

Surface Preparation:

Perform any necessary crack sealing and pavement patching in the existing paved surface prior to applying the slurry seal.

Clean the existing surface of loose material, dirt, or other deleterious material by approved methods.

Avoid smearing or staining adjoining surfaces, appurtenances, and surroundings. Promptly remove spillages and clean affected surfaces.

Lightly dampen the existing surface with water immediately before applying the slurry seal so the mixture doesn’t dry out too quickly.

Weather limitations: Apply slurry seal only when the following apply:

Surface is dry and unfrozen;

Ambient air temperature is above 45° F (7° C);

Surface temperature is above 45° F (7° C);

Weather is not foggy or rain is not forecasted within 24 hours; and Application

Mixing: Blend the aggregate, asphalt emulsion, water, and mineral additives until the mixture reaches a thick, creamy consistency.

Applying: Dispense the material using a truck-mounted slurry paver or pull-box, laying a single stone thickness mat evenly across the paved surface. Use a rubber squeegee to do edges and corners.

Rolling: Roll the surface using a pneumatic roller and make at least 2 full passes under 5 mph (8 km/h).

Curing: Keep all traffic off the paved surface for 2 to 4 hours or until it is fully cured.

Install over entire paved surface, excluding any concrete sections, unless otherwise noted.

WASTE HANDLING

Retain this article if repairs, patching, or cold milling of existing pavement is required.

General: Handle asphalt-paving waste according to Section 017419 "Construction Waste Management and Disposal."

Dispose of all excess or discarded asphalt concrete mix according to state and local regulations.

Retain "Crowned Surfaces" Subparagraph below if required.

END OF SECTION 321216

SECTION 321723 - PAVEMENT MARKINGS

1. GENERAL

SUMMARY

Section includes painted markings applied to asphalt pavement.

PREINSTALLATION MEETINGS

Preinstallation Conference: Conduct conference at the project site with the Contracting Officer’s Representative and/or with the Deputy Project Leader.

ACTION SUBMITTALS

Product Data: For each type of product.

LEED Submittals:

"Product Data for Credit IEQ 4.2" Subparagraph below applies to LEED-NC and LEED-CS. Coordinate with requirements for paints and coatings.

Product Data for Credit IEQ 4.2: For interior, field-applied, pavement-marking paints, documentation including printed statement of VOC content.

Samples: For each exposed product and for each color and texture specified.

PRODUCTS

See Editing Instruction No. 1 in the Evaluations for cautions about named manufacturers and products. For an explanation of options and Contractor's product selection procedures, see Section 016000 "Product Requirements."

PAVEMENT-MARKING PAINT

Retain one of two "Pavement-Marking Paint" paragraphs below. Verify availability with marking-paint manufacturers.

Pavement-Marking Paint: MPI #32, alkyd traffic-marking paint is not allowed on this project.

Retain required color(s) in "Color" Subparagraph below. If more than one color is required, indicate locations of each on Drawings or by inserts.

Pavement-Marking Paint: use only MPI #97, latex traffic-marking paint or similar.

Retain required color(s) in "Color" Subparagraph below. If more than one color is required, indicate locations of each on Drawings or by inserts.

Retain "Glass Beads" Paragraph below if reflectorized pavement markings are required. Retain option if required.

Glass Beads: AASHTO M 247, Type 1, made of 100 percent recycled glass.

Retain "VOC Content" Paragraph below if required for LEED-NC or LEED-CS Credit IEQ 4.2 and product is used inside the weatherproofing system such as for underground parking. VOC content limit is that for traffic- or zone-marking coatings. Coordinate product selection to ensure that products comply.

VOC Content: Pavement markings used on building interior shall have a VOC content of 150 g/L or less.

EXECUTION

PAVEMENT MARKING

Do not apply pavement-marking paint until layout, colors, and placement have been verified with the Contracting Officer’s Representative and/or with the Deputy Project Leader.

The proposed pavement marking layout shall replicate the existing pavement marking layout unless otherwise directed by the Contracting Officer’s Representative or by the Deputy Project Leader. Accessible parking spaces and accessible pavement markings shall comply with the current ADA requirements.

Marking-paint manufacturers caution that paint will bleed or tear surface of new asphalt unless asphalt is aged before painting. This aging period may vary from 30 to 90 days. If pavement marking must proceed immediately, consider revising text to a phased application of a thin first coat followed by a thicker second coat once asphalt has aged. Verify that two-coat application is recommended by marking-paint manufacturer.

Allow paving to age for a minimum of 14 days before starting pavement marking.

Sweep and clean surface to eliminate loose material and dust.

Apply paint with mechanical equipment to produce pavement markings, of dimensions indicated, with uniform, straight edges. Apply at manufacturer's recommended rates to provide a minimum wet film thickness of 15 mils (0.4 mm).

Retain first subparagraph below if graphic symbols or lettering is required.

Apply graphic symbols and lettering with paint-resistant, die-cut stencils. Apply paint so that it cannot run beneath the stencil.

Retain subparagraph below if glass beads are required for reflectivity.

Broadcast glass beads uniformly into wet markings at a rate of 6 lb/gal. (0.72 kg/L).

END OF SECTION 321723