Sol_140FF027Q0033.pdf

PDF 463 KB Posted

Attached to
ID- KOOSKIA NFH-OVERHEAD DOOR REPLACE
Solicitation number
140FF027Q0033
Issued by

About this file

This is a Request for Quotation (RFQ) for construction services at the Kooskia National Fish Hatchery in Idaho. The U.S. Fish and Wildlife Service seeks qualified contractors to replace three overhead sectional garage doors and install two electric door operators. The contract is a Firm Fixed Price award set aside for small business concerns. Quotations are due by December 28, 2026, at 12:00 PM PST, with a Request for Information deadline of December 16, 2026, at 5:00 PM PST. All bidders must conduct a mandatory on-site visit on Monday, December 14, 2026, at 10:00 AM PST to verify measurements and existing conditions. The estimated contract value is less than $25,000, with an estimated 60-day performance period following Notice to Proceed. The contractor shall begin within 15 calendar days of award and complete work within 60 calendar days.

The scope includes removal and disposal of three existing roll-up doors, installation of three new sectional overhead doors (one 8'4" × 8'7" and two 10'2" × 10'1"), and installation of two electric 120vac door operators. Door specifications require ribbed steel panels with white finish, minimum 0.015" hot-dipped galvanized steel, CFC-free polyurethane foam insulation, five sections per door, bottom weather seal, galvanized hardware, 2" track with 12" radius, torsion spring system (minimum 10,000 cycles), and manual push-up operation. Additional work includes replacing side seals on existing doors and providing preventative maintenance services for up to ten additional roll-up garage doors. Payment bonds are required within 10 days of award at 100 percent of contract price. Electronic invoicing through the Invoice Processing Platform (IPP) is mandatory. Contractors must comply with Davis-Bacon wage requirements, environmental regulations, and multiple federal contract clauses. Award will be based on best value considering past experience, past performance, and price fairness and reasonableness.

View the file

Other files

File Type Posted
B06_SECTION_B_Schedule.docx DOCX document
A04_SOW_KNFH_Garage_Door_Replacement.pdf PDF
B03_Construction_WD_Idaho_County_5_18_26.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(See ).

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

SOLICITATION

1. SOLICITATION NO.

5. REQUISITION/PURCHASE REQUEST NO.

CODE

6. PROJECT NO.

8. ADDRESS OFFER TO

4. CONTRACT NO.

7. ISSUED BY

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

11. The contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and

b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than

STANDARD FORM 1442 (REV. 12/2022)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

is, is not required.

local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.

calendar days and complete it within calendar days after receiving

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

12b. CALENDAR DAYS

2. TYPE OF SOLICITATION

NEGOTIATED (RFP) REQUEST FOR PROPOSAL

3. DATE ISSUED PAGE OF

SEALED BID (IFB) INVITATION FOR BID

9. FOR

INFORMATION CALL

PAGES

140FF027Q0033

U.S. Fish & Wildlife Service, Regio 5600 American Boulevard, Suite 990 Bloomington MN 55437-1458

0044059599

F03

Cindy Salazar 5038722832

11/25/2026

12/28/2026

15 60 Statement of Work

This is for a Firm Fixed Price Contract.

See attached documents:

A04 Statement of Work (SOW)

B03 Construction WD - Idaho County - General Decision Number: ID20260024 05/18/2026

B06 Bid Schedule

Price Range: Less Than $25,000

Response End Date: 12/28/2026, 12:00 PM, (PST)

Request for Information: 12/16/2026, 5:00 PM, (PST)

Site visit: All bidders must conduct an on-site visit to verify measurements and existing conditions(see

SOW for additional information).

Site Visit Date and Time: Monday, 12/14/2026, 10:00 AM (PST)

1 29

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

OFFER (Must be fully completed by offeror)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AWARD (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

CODE FACILITY CODE

15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

21. ITEMS ACCEPTED:

22. AMOUNT

26. ADMINISTERED BY

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31c. DATE

STANDARD FORM 1442 (REV. 12/2022) BACK

31b. UNITED STATES OF AMERICA

BY

31a. NAME OF CONTRACTING OFFICER (Type or print)

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30b. SIGNATURE 30c. DATE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

23. ACCOUNTING AND APPROPRIATION DATA

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT

27. PAYMENT WILL BE MADE BY

10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )

20b. SIGNATURE 20c. OFFER DATE

Continued...

AMENDMENT

NUMBER

DATE.

FWS, CONSTRUCTION AND ACQUISITION D

5600 American Blvd West Suite 990 Bloomington MN 55437-1458

F03

Cindy Salazar

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

140FF027Q0033

Submit quotes to Contracting POC:

Cindy Salazar, Email:

cindy_salazar@ios.doi.gov

Delivery: 12/30/2026

Delivery Location Code: 0011279506

FWS KOOSKIA NATIONAL FISH HATCHERY

318 TOLL ROAD

KOOSKIA ID 83539-5190 US

Period of Performance: 12/30/2026 to

03/30/2027

00010 Replace Production Admin / Incubation Room

Period of Performance: 11/30/2026 to

12/30/2026

00020 BLDG WH EQUIP VEHICLE ADULT STORAGE BLDG

Period of Performance: 11/30/2026 to

12/30/2026

00030 BLDG WH EQUIP VEHICLE SHOP BUILDING

Period of Performance: 11/30/2026 to

12/30/2026

00040 BLDG PUMP HOUSE, O2 GENERATOR PRODUCTION

Period of Performance: 11/30/2026 to

12/30/2026

00050 BLDG MAINT SHOP, CHILLER (X2) AND GENERA

Period of Performance: 11/30/2026 to

12/30/2026

Kooskia National Fish Hatchery SOLICITATION NO. 140FF027Q0033 Replace (3) Overhead Garage Doors

4 | P a g e

Section Title

Part I—The Schedule

A Solicitation/Contract Form

B Prices

C Description/Specifications/Statement of Work

D Packaging and Marking

E Inspection and Acceptance

F Project Delivery

G Contract Administration Data

H Special Contract Requirements

Part II—Contract Clauses

I Contract Clauses

Part III—List of Documents, Exhibits, and Other Attachments

J List of Attachments

Part IV—Representations and Instructions

K Representations, Certifications, and other Statements of Offerors

L Instructions, Conditions, and Notices to Offerors

M Evaluation Factors for Award

NOTE: Be advised that the controlling law regarding certain terms and conditions of this agreement remains unsettled by the Federal judiciary at the time of award and will be enforced only to the extent permitted by law. Notice will be provided regarding the legal outcomes that impact your agreement.

52.252-2 – CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

As prescribed in 52.107(b), insert the following clause:

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): https://www.acquisition.gov/far-overhaul (FAR clauses begin with 52)

(End of Clause) https://www.acquisition.gov/far-overhaul

5 | P a g e

SECTION B – PRICES (QUOTE SCHEDULE)

Name of Firm: ________________________________________________________________________

Address: _____________________________________________________________________________

City: __________________________________ State: ___________ Zip Code: ___________________

Unique Entity ID (12 Digits assigned by SAM.gov) __________________ CAGE Code: ________________

Name and Title of Firm’s Point of Contact: __________________________________________________

Phone Number: _________________________ Email Address: __________________________

This requirement is for one (1) Firm Fixed Price Construction contract for Replacement of Three (3) Roll-up Grage Doors in Kooskia National Fish Hatchery (NFH), 318 Toll Road, Kooskia, Idaho, 83539.

(End of Section B)

Item no. Item Description Quantity Unit of

Measure Unit Price Total 00010 Replace Production

Admin/Incubation Room

1 LS $ $

00020 Building WH Equipment Vehicle Adult Storage Building

1 LS $ $

00030 Building WH Equipment Vehicle Shop Building

1 LS $ $

00040 Building Pump House O2 Generator Production

1 LS $ $

00050 Building Maintenance Shop, Chiller (X2) and General

1 LS $ $

TOTAL - Base $

GRAND TOTAL: $

6 | P a g e

SECTION C – DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

1. Scope of Work

The U.S. Fish and Wildlife Service, has a requirement for a replacement of three roll-up garage doors for Kooskia National Fish Hatchery, located at 318 Toll Road, Kooskia, Idaho, 83539.

The contractor shall provide all labor, materials, equipment, and supervision necessary to remove three existing roll-up garage doors and install three new sectional overhead doors. Work includes demolition, disposal, installation, adjustments, testing, and site cleanup.

Two additional electric door operators shall also be installed as described in Section 3.

2. Technical Requirements

2.1 Door Specifications

• Quantity: Three sectional overhead doors

• Sizes:

o One door approximately 8' 4" × 8' 7" o Two doors approximately 10' 2" × 10' 1"

• Measurement Disclaimer:

o All measurements provided are approximate.

o All vendors must perform a mandatory on-site visit and confirm all dimensions independently.

o The Kooskia National Fish Hatchery is not responsible for any measurement discrepancies or errors discovered after bidding or installation.

2.2 Door Construction Requirements

• Ribbed steel panel design, white finish

• Minimum 0.015" thick hot-dipped galvanized exterior steel

• CFC-free polyurethane foam insulated core

• Five sections per door

• Bottom weather seal required

• Galvanized steel hardware

7 | P a g e

• 2" track, 12" radius, angle-mounted

• Torsion spring system (minimum 10,000 cycles)

• Manual push-up operation

• Non-rated wind load unless otherwise specified by contractor

2.3 Additional Work

• Replace side seals on existing doors as needed

• General preventative maintenance services for up to ten additional roll up garage doors included in this solicitation

3. Electric Door Operators

3.1 Maintenance Shop – Bay #1

• Install one (1) 120vac electric door operator on the existing roll-up door in Bay #1 of the maintenance shop.

• Operator must be appropriately sized for the door’s weight and lift characteristics.

• Include wall-mounted controls and required safety features.

• Electrical wiring arrangements shall be coordinated with facility staff.

3.2 Equipment Building – East-Facing Door

• Install one (1) 120vac electric operator on the new East-facing roll-up garage door in the equipment storage building.

• Provide compatible hardware, controls, and safety systems.

• Coordinate electrical needs with facility staff.

4. Installation Requirements

• Contractor must verify all field measurements and conditions before ordering materials.

• All pad surfaces must be flush with jambs.

• Contractor is responsible for the removal and disposal of old doors and debris.

• All installation must comply with applicable codes and standards.

5. Performance Standards

• Installed doors must operate smoothly and safely.

8 | P a g e

• Doors must meet industry standards for air infiltration, deflection, and general performance.

• Electric operators must function correctly, including safety interlocks and limit adjustments.

6. Submittals & Approvals

• Contractor shall submit shop drawings, product data, and installation documentation for approval prior to procurement.

7. Vendor Site Visit Requirement

Site visit: All bidders must conduct an on-site visit to verify measurements and existing conditions.

Site Visit Date and Time:

Monday, 12/14/2026, 10:00 AM (PST)

• All site visits must be coordinated with the technical point of contact.

• Failure to complete a site visit waives any future claims related to mismeasurement or unforeseen site conditions.

8. Technical Point of Contact and Project Location

• Kurt McCorkle, Contracting Officer’s Technical Representative (COTR), Facility Operations Specialist; Email:

kurt_mccorkle@fws.gov; Phone: 208-400-0002

• Kayla Warden, Kooskia National Fish Hatchery Manager;

Email: kaylaw@nezperce.org Phone: 208-935-8798

• Location: Kooskia National Fish Hatchery 318 Toll Road, Kooskia, Idaho 83539

9. Acceptance Criteria

Work will be evaluated and accepted based on:

• Compliance with all specifications in this SOW

• Verified functionality of all three doors

• Fully operational electric door operators

• Site cleanup completed and all debris removed

10. Period of Performance

• Estimated 60 days once awarded.

(End of Section C) mailto:kaylaw@nezperce.org

9 | P a g e

SECTION D – PACKAGING AND MARKING

D.1.0 PAYMENT OF POSTAGE FEES

All postage and fees related to submitting information forms, reports, etc., to the CO or the COR shall be paid by the contractor.

D.2.0 MARKING

All information submitted to the Contracting Officer or the Contracting Officer's Representative shall clearly indicate the Contract Number of the contract for which the information is being submitted.

(End of Section D)

SECTION E – INSPECTION AND ACCEPTANCE

The following clauses are incorporated by reference:

52.246-12 Inspection of Construction AUG 1996

(End of Section E)

SECTION F – PROJECT DELIVERY

F.1.0 PERIOD OF PERFORMANCE

Estimated 60 days once Notice to Proceed is received.

F.2.0 PROGRESS PLAN

At the prework conference, the Contractor shall provide to the COR a written "work progress plan" that details its proposed work force and schedule to provide for orderly completion of the work within the contract performance time. This work schedule must be acceptable to the Government. At a minimum, the schedule must reflect a work progress rate equal to the available amount of contract performance time.

The following clauses are incorporated by reference:

52.242-14 Suspension of Work APR 1984

(End of Section F)

10 | P a g e

SECTION G – CONTRACT ADMINISTRATION DATA

ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS – INVOICE PROCESSING PLATFORM (IPP) (February 2021)

Payment requests must be submitted electronically through the U.S. Department of the Treasury’s Invoice Processing Platform System (IPP).

“Payment request” means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions – Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.

Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:

1. Invoice billed according to contract line items and rates.

2. Certified payrolls and Statement of Compliance in accordance with clause 52.222-8.

3. If the partial payment is billed and the invoice states a lump sum, the invoice shall include an itemized breakdown and narrative progress summary of the work performed during this invoice period.

4. If final payment is billed, the last invoice shall state “FINAL”.

5. Contractor’s Release of Claims shall be submitted with the final invoice.

The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of St. Louis (FRBSTL) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email IPPCustomerSupport@fiscal.treasury.gov or phone (866) 973-3131.

If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.

(End of Local Clause)

(End of Section G)

SECTION H – SPECIAL CONTRACT REQUIREMENTS

H.1.0 WORK HOURS

Unless otherwise specified in Section C, work hours under this contract shall be limited to the time between one-half hour before sunrise to one-half hour after sunset each day. Coordinate with Kurt McCorkle, COTR or Kayla Warden Kooskia National Fish Hatchery, Manager for approved work time schedule.

No work will be performed on Saturday, Sunday, or Federal holidays unless authorized by the COR.

https://www.ipp.gov/ mailto:IPPCustomerSupport@fiscal.treasury.gov

11 | P a g e

H.2.0 ENVIRONMENTAL INTERRUPTION OF WORK

H.2.1 Environmental - The Contracting Officer, by issuance of a suspend work order, may direct the Contractor to shut down any work that may be subject to damage due to weather conditions, fire danger, or because it is impracticable to work during the winter season. The Contractor will be given a resume work order which will document the date the work suspension ends. The Contractor will not be entitled to additional monetary compensation for such suspensions regardless of duration. An allowance has been included in the contract time for environmental delays. The count of contract time will therefore continue during all periods of suspension due to normal weather conditions, including fire danger. The Contractor will not be entitled to additional contract time for any suspensions except to the extent that they are due to unusually severe weather conditions.

H.2.2 Endangered Species - The Government may direct the Contractor to discontinue all operations in the event that listed or proposed threatened or endangered plants or animals protected under the Endangered Species Act of 1973, as amended, are discovered to be present in or adjacent to the project area.

H.3.0 DRAWINGS

H.3.1 Reduced Size Drawings. Drawings appearing in this package may be photographically reduced in size.

Accordingly, measurements and dimensions should not be taken or be based on any numerical scales shown.

The Contractor may request full-size drawings from the COR.

H.4.0 PRESERVATION OF HISTORICAL AND ARCHEOLOGICAL DATA

H.4.1 Public Law 93-291, May 24, 1974, provides for the preservation of scientific, prehistorical, and archeological data (including relics and specimens) which might otherwise be lost due to alteration of the terrain as a result of any Federal construction project.

H.4.2 The Contractor agrees that should any contractor employee, in the performance of this contract, discover evidence of possible scientific, prehistorical, historical, or archeological data the contractor will notify the Contracting Officer immediately in writing giving the location and nature of the findings.

H.4.3 Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance and/or changes in the work. If such delays and/or changes are ordered, the time of performance and contract price shall be adjusted in accordance with the applicable clauses in Section I of this contract.

H.4.4 The Contractor agrees to insert this requirement in all subcontracts which involve the performance of work on the terrain of the site.

H.5.0 SUBSTITUTION – PROCESSION OF WORK

Any proposed key personnel, minimum qualifications for incoming or replacement key personnel, subcontractors, processes, procedures or materials included in the quotation are hereby incorporated into the contract. Performance shall be limited to the personnel, qualifications, firms, procedures, and materials that were specifically identified in the RFQ response. The Contractor shall obtain the Contracting Officer’s written consent before making any substitutions or changes. All substitutions or replacements shall comply with the terms and conditions of the contract.

12 | P a g e

H.6.0 ENVIRONMENTAL IMPACT

All waste materials generated by any work under the contract performed on a Government installation shall at all times be handled, transported, stored, and disposed of by the contractor and by subcontractors in accordance with all applicable Federal, state, and local laws, ordinances, regulations, court orders, and other types of rulings having the effect of the law, including, but not limited to Executive Order 12088, 13 October 1978, Federal Compliance with Pollution Control Standards; the Federal Water Pollution Control Act, as amended (33 U.S.C. 1251 ET SEQ); the Clean Air Act as amended (42 U.S.C. Sec 7401 ET SEQ); the Endangered Species Act, as amended (16 U.S.C. Sec 1531, ET SEQ); the Toxic Substances Control Act, as amended (15 U.S.C.

Sec 2601, ET SEQ); the National Historic Preservation Act, as amended (16 U.S.C. Sec 470, ET SEQ); the Solid Waste Disposal Act, as amended (42 U.S.C. 6901 ET SEQ); and the Archaeological and Historic Preservation Act, as amended (16 U.S.C. Sec 469, ET SEQ). Should the United States Government be held liable for any neglect or improper actions by the contractor or any subcontractor regarding removal or disposal of any hazardous waste, the contractor shall reimburse the Government for all such liability.

H.7.0 HAZARDOUS MATERIALS

Any material suspected of being hazardous that is unexpectedly encountered during performance of a project shall immediately be brought to the attention of the Contracting Officer, at which time a determination will be made as to whether hazardous material testing shall be performed. If the Contracting Officer directs the contractor to perform tests, and/or the material is found to be of a hazardous nature requiring additional protective measures, a contract modification may be required, subject to equitable adjustment under the terms of the contract. The contractor is advised that friable and/or non-friable asbestos-containing material may be encountered in project areas. Friable asbestos-containing material is any material that contains more than one percent asbestos by weight, and that hand pressure can crumble, pulverize or reduce to powder when dry. Non-friable asbestos containing materials are materials in which asbestos fibers are bound by a matrix material, saturation, impregnation or coating.

Non-friable asbestos-containing materials do not normally release airborne asbestos fiber during routine handling and end-use. However, excessive fiber concentrations may be produced during uncontrolled abrading, sanding, drilling, cutting, machining, removal, demolition, or other similar activities. 29 CFR 1910.1001 shall be referenced in the event asbestos-containing materials are encountered. Friable asbestos-containing materials are not authorized for use in new construction or maintenance projects.

H.8.0 GREEN PROCUREMENT REQUIREMENTS

In the performance of this construction contract, the Contractor shall make maximum use of products identified on the mandatory environmental purchasing list at the following links, as applicable:

• U.S. EPA Comprehensive Procurement Guidelines published at www.epa.gov/cpg/products.htm.

• USDA Biobased product listings published at www.biopreferred.gov.

• Energy Star® product listings published at www.energystar.gov/products.

• FEMP Low Standby Power product listings published at http://energy.gov/eere/femp/covered-product-categories

Contractor shall comply with all reporting requirements of the following clauses/provisions when applicable (See Clause and Provision sections):

http://www.epa.gov/cpg/products.htm http://www.bioprefferd.gov/ http://www.energystar.gov/products http://energy.gov/eere/femp/covered-product-categories http://energy.gov/eere/femp/covered-product-categories

13 | P a g e

• 52.223-1 Biobased Product Certification

• 52.223-2 Affirmative Procurement of Biobased Products under Service and Construction Contracts

• 52.223-4 Recovered Material Certification

• 52.223-9 Estimate of Percentage of Recovered Material Content for EPA Designated Items

H.9.0 UNAUTHORIZED PERSONNEL

The contractor shall inform all personnel working under their jurisdiction (including subcontractor and visiting supplier personnel) that access to restricted areas outside of the immediate work area; excluding direct haul and access routes, contracting and Civil Engineering offices and points of supply and storage; is prohibited.

Circulation of said personnel will be limited to official business only. Persons in violation of the above will be apprehended and appropriately disciplined.

H.10.0 DAVIS-BACON WAGE RATES APPLICABLE TO TRUCK DRIVERS

29 CFR 5.2(j) limits coverage of construction contractor or subcontractor employees performing as truck drivers under the Davis-Bacon Act (FAR 52.222-6) to only their time spent directly upon the "site of the work" or when hauling between the site of the work and a facility which is dedicated to and located in the proximity of the actual construction location. Other transportation of materials or supplies to or from the site of work by employees of the construction contractor or subcontractor is not “construction” at the site of work and accordingly is not subject to the Davis-Bacon Act.

H.11.0 FIRE DANGER SEASON

If the COR allows the Contractor to continue work during periods of declared fire danger or season, the Contractor shall comply with all applicable state laws relating to fire prevention and with all special conditions of work as directed by the COR.

(End of Section H)

SECTION I – CONTRACT CLAUSES

The following clauses are incorporated by reference:

Clause Title Date 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements

JAN 2017

52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards

JUN 2020 (DEVIATION MAR 2026)

52.204-13 System for Award Management Maintenance OCT 2018 52.204-14 Service Contract Reporting Requirements OCT 2016 (DEVIATION MAR 2026) 52.204-16 Commercial and Government Entity Code Reporting AUG 2020 (DEVIATION MAR 2026) 52.204-19 Incorporation By Reference of Representations and Certifications DEC 2014 52.204-23 Prohibition on Contracting for Hardware, Software, and Services

Developed or Provided by Kaspersky Lab Covered Entities

DEC 2023

14 | P a g e

52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Servies or Equipment

NOV 2021

52.209-6 Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded

JAN 2025 (DEVIATION MAY 2026)

52.209-10 Prohibition on Contracting with Inverted Domestic Corporations NOV 2015 52.211-10 Commencement, Prosecution and Completion of Work APR 1984 52.213-4 Terms & Conditions-Simplified Acquisitions (Other Than Commercial

Products and Commercial Services)

MAR 2026 (DEVIATION MAR 2026)

52.215-8 Order of Precedence-Uniform Contract Format OCT 1997 (DEVIATION OCT 2026) 52.215-11 Price Reduction for Defective Certified Cost or Pricing Data-

Modifications

JUN 2020 (DEVIATION OCT 2026)

52.215-9 Notification of Ownership Changes OCT 1997 (DEVIATION OCT 2026) 52.215-21 Requirements for Certified Cost or Pricing Data and Data Other Than

Certified Cost or Pricing Data-Modifications – (Alternate I-

DEVIATION (OCT 2026)

NOV 2021 (DEVIATION OCT 2026)

52.219-6 Notice of Total Small Business Set-Aside NOV 2020 (DEVIATION JAN 2026) 52.219-28 Postaward Small Business Program Representation JAN 2025 (DEVIATION JAN 2026) 52.219-33 Nonmanufacturer Rule SEP 2021 (DEVIATION JAN 2026) 52.222-3 Convict Labor JUN 2003

52.222.6 Construction Wage Rates AUG 2018 (DEVIATION JAN 2026) 52.222-7 Withholding of Funds MAY 2014 52.222-8 Payrolls and Basic Records JUL 2021 52.222-9 Apprentices and Trainees JUL 2005 52.222-10 Compliance with Copeland Act Requirements FEB 1988 52.222-11 Subcontracts (Labor Standard) MAY 2014 (DEVIATION MAY 2026) 52.222-12 Contract Termination – Debarment MAY 2014 52.222-13 Compliance with Construction Wage Rate Requirements and Related

Regulations

MAY 2014

52.222-14 Disputes Concerning Labor Standards FEB 1988 52.222-15 Certification of Eligibility MAY 2014

52.222.20 Contracts for Materials, Supplies, Articles, and Equipment JUN 2020 (DEVIATION MAY 2026) 52.222-32 Construction Wage Rate Requirements - - Price Adjustment (Actual

Method)

AUG 2018

52.222-50 Combating Trafficking in Persons OCT 2025 (DEVIATION MAY 2026) 52.222-55 Minimum Wages for Contractor Workers Under Executive Order

14026

JAN 2022

52.222-62 Paid Sick Leave Under Executive Order 13706 JAN 2022 52.223-5 Pollution Prevention and Right-to-Know Information MAY 2024 52.223-2 Reporting of Biobased Products Under Service and Construction MAY 2024 (DEVIATION MAY 2026) 52.225-9 Buy American-Construction Materials OCT 2022 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While

Driving

MAY 2024

52.227-4 Patent Indemnity-Construction Contracts DEC 2007 52.228-11 Individual Surety – Pledges of Assets FEB 2021

15 | P a g e

52.228-12 Prospective Subcontractor Requests for Bonds DEC 2022 52.232-5 Payments Under Fixed-Price Construction Contracts MAY 2014 52.232-16 Progress Payments NOV 2021 (DEVIATION OCT 2026) 52.232-24 Prohibition of Assignment of Claims MAY 2014 52.232-27 Prompt Payment for Construction Contracts JAN 2017 52.232-33 Payment by Electronic Funds Transfer—System for Award

Management

OCT 2018

52.232-39 Clause for unenforceability of unauthorized obligations JUN 2013 52.232-40 Providing Accelerated Payments to Small Business Subcontractors MAR 2023 52.232-1 Disputes MAY 2014 (DEVIATION OCT 2026) 52.233-3 Protest after Award AUG 1996 (DEVIATION OCT 2026) 52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 (DEVIATION OCT 2026) 52.236-3 Site Investigation and Conditions Affecting the Work APR 1984 (DEVIATION JAN 2026) 52.236-2 Differing Site Conditions APR 1984 (DEVIATION JAN 2026) 52.236-5 Material and Workmanship APR 1984 (DEVIATION JAN 2026) 52.236-6 Superintendent by the Contractor APR 1984 (DEVIATION JAN 2026) 52.236-7 Permits and Responsibilities NOV 1991 (DEVIATION JAN 2026) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements

APR 1984 (DEVIATION JAN 2026)

52.236-14 Availability and Use of Utility Services APR 1984 (DEVIATION JAN 2026) 52.242-5 Payments to Small Business Subcontractors JAN 2017 52.243-5 Changes and Changed Conditions APR 1984 (DEVIATION OCT 2025) 52.244-6 Subcontracts for Commercial Products and Commercial Services OCT 2025 (DEVIATION MAY 2026) 52.246-21 Warranty of Construction MAR 1994 52.249-10 Default (Fixed-Price Construction) APR 1984

The following clauses are provided in full text:

52.228-13 – ALTERNATIVE PAYMENT PROTECTIONS (JUL 2000)

(a) The Contractor shall submit one of the following payment protections:

Payment bond Irrevocable letter of credit (ILC)

(b) The amount of the payment protection shall be 100 percent of the contract price.

(c) The submission of the payment protection is required within 10 days of contract award.

(d) The payment protection shall provide protection for the full contract performance period plus a one-year period.

(e) Except for escrow agreements and payment bonds, which provide their own protection procedures, the Contracting Officer is authorized to access funds under the payment protection when it has been alleged in writing by a supplier of labor or material that a nonpayment has occurred, and to withhold such funds pending resolution by administrative or judicial proceedings or mutual agreement of the parties.

16 | P a g e

(f) When a tripartite escrow agreement is used, the Contractor shall utilize only suppliers of labor and material that signed the escrow agreement.

(End of Clause)

52.236-12 Cleaning Up (APR 1984) (DEVIATION JAN 2026)

As prescribed in 36.101-7(a), insert the clause:

(a) The Contractor shall keep the work area, including storage areas, in a clean, neat, orderly condition, and free from accumulations of waste materials.

(b) Before completing the work, the Contractor shall remove from the site any rubbish, tools, scaffolding, equipment, and materials that are not the property of the Government.

End of clause)

52.236-13 Accident Prevention (NOV 1991) (DEVIATION JAN 2026)

As prescribed in 36.101-7(e), insert the clause:

(a) The Contractor shall provide and maintain work environments and procedures that—

(1) Safeguard the public and Government personnel, property, materials, supplies, and equipment exposed to

Contractor operations and activities;

(2) Avoid interruptions of Government operations and delays in project completion dates; and

(3) Control costs in the performance of this contract.

(b) In addition, for contracts for construction or dismantling, demolition, or removal of improvements, the Contractor shall—

(1) Provide appropriate safety barricades, signs, and signal lights;

(2) Comply with the standards issued by the Secretary of Labor at 29 CFR part 1926 and 29 CFR part 1910 ; and

(3) Ensure that any additional measures the Contracting Officer determines to be reasonably necessary for the purposes are taken.

17 | P a g e

(c) If this contract is for construction or dismantling, demolition or removal of improvements with any Department of

Defense agency or component, the Contractor shall comply with all pertinent provisions of the latest version of U.S.

Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1, in effect on the date of the solicitation.

(d) (1) If the Contracting Officer becomes aware of any noncompliance with these requirements or any condition that poses a serious or imminent danger to the health or safety of the public or Government personnel, the Contracting

Officer will notify the Contractor orally, with written confirmation, and request immediate initiation of corrective action.

(2) This notice, when delivered to the Contractor or the Contractor's representative at the work site, shall be deemed sufficient notice of the noncompliance and that corrective action is required.

(3) After receiving the notice, the Contractor shall immediately take corrective action.

(4) If the Contractor fails or refuses to promptly take corrective action, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken.

(5) The Contractor shall not be entitled to any equitable adjustment of the contract price or extension of the performance schedule on any stop-work order issued under this clause.

(e) The Contractor shall insert the substance of this clause, including this paragraph (e), in subcontracts.

(End of clause)

Alternate I ( Nov 1991). If the contract will involve (a) work of a long duration or hazardous nature, or (b) performance on a Government facility that on the advice of technical representatives involves hazardous materials or operations that might endanger the safety of the public and/or Government personnel or property, add the following paragraph (f) to the basic clause:

(f) Before commencing the work, the Contractor shall-

(1) Submit a written proposed plan for implementing this clause. The plan shall include an analysis of the significant hazards to life, limb, and property inherent in contract work performance and a plan for controlling these hazards; and

(2) Meet with representatives of the Contracting Officer to discuss and develop a mutual understanding relative to administration of the overall safety program.

52.236-14 Availability and Use of Utility Services (APR 1984) (DEVIATION JAN 2026)

As prescribed in 36.101-7(f), insert the clause:

18 | P a g e

(a) The Government will make all reasonably required utilities available to the Contractor from existing outlets and supplies, as specified in the contract.

(b) Unless otherwise provided in the contract, the Contractor shall pay for all utility costs.

(c) The Contractor, at its expense and in a workmanlike manner, shall install and maintain all necessary temporary connections, distribution lines, and all meters required to measure the amount of each utility used for the purpose of determining charges.

(d) Before final acceptance by the Government, the Contractor shall remove the temporary connections, distribution lines, meters, and associated paraphernalia.

(End of clause)

Alternate I (APR 1984). If it is determined at a level above that of the Contracting Officer that it is impracticable for

Government personnel to perform the original and final surveys, and the Government wishes the Contractor to perform these surveys, substitute the following paragraph (b) for paragraph (b) of the basic clause:

(b) The Contractor shall conduct the original and final surveys and surveys for any periods for which progress payments are requested. All these surveys shall be conducted under the direction of a representative of the Contracting

Officer, unless the Contracting Officer waives this requirement in a specific instance. The Government shall make such computations as are necessary to determine the quantities of work performed or finally in place. The Contractor shall make the computations based on the surveys for any periods for which progress payments are requested.

52.236-17 Layout of Work (APR 1984) (DEVIATION JAN 2026)

As prescribed in 36.101-7(i), insert the clause:

(a) The Contractor shall lay out its work from Government-established base lines and benchmarks provided on the drawings.

(b) The Contractor shall be responsible for all measurements in connection with the layout.

(c) The Contractor shall furnish, at its own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required for the layout.

(d) The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the Contracting Officer.

(e)

19 | P a g e

(1) The Contractor shall be responsible for maintaining and preserving all stakes and other marks established by the

Contracting Officer until authorized to remove them.

(2) If such marks are destroyed by the Contractor, the Contracting Officer may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.

(End of clause)

52.245-2 – GOVERNMENT PROPERTY INSTALLATION OPERATION SERVICES (APR 2012)

(a) This Government Property listed in paragraph (e) of this clause is furnished to the Contractor in an “as-is, where is” condition. The Government makes no warranty regarding the suitability for use of the Government property specified in this contract. The Contractor shall be afforded the opportunity to inspect the Government property as specified in the solicitation.

(b) The Government bears no responsibility for repair or replacement of any lost Government property. If any or all of the Government property is lost or becomes no longer usable, the Contractor shall be responsible for replacement of the property at Contractor expense. The Contractor shall have title to all replacement property and shall continue to be responsible for contract performance.

(c) Unless the Contracting Officer determines otherwise, the Government abandons all rights and title to unserviceable and scrap property resulting from contract performance. Upon notification to the Contracting Officer, the Contractor shall remove such property from the Government premises and dispose of it at Contractor expense.

(d) Except as provided in this clause, Government property furnished under this contract shall be governed by the Government Property clause of this contract.

(e) Government property provided under this clause:

____No Government property or equipment is provided.

(End of clause)

52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (NOV 2020)

As prescribed in 52.107(f), insert the following clause in solicitations and contracts that include any FAR or supplemental clause with an authorized deviation.

20 | P a g e

(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the clause.

(b) The use in this solicitation or contract of any DIAR] (48 CFR 1401) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.

(End of clause)

52.253-1 Computer Generated Forms (JAN 1991) (DEVIATION MAY 2026)

As prescribed in FAR 53.111, insert the clause:

(a) Any data required to be submitted on a Standard or Optional Form prescribed by the Federal Acquisition Regulation

(FAR) may be submitted on a computer-generated version of the form, provided there is no change to the name, content, or sequence of the data elements on the form, and provided the form carries the Standard or Optional Form number and edition date.

(b) Unless prohibited by agency regulations, any data required to be submitted on an agency unique form prescribed by an agency supplement to the FAR may be submitted on a computer generated version of the form provided there is no change to the name, content, or sequence of the data elements on the form and provided the form carries the agency form number and edition date.

(c) If the Contractor submits a computer-generated version of a form that is different than the required form, then the rights and obligations of the parties will be determined based on the content of the required form.

(End of clause)

1452.201-70 AUTHORITIES AND DELEGATIONS (SEP 2011)

(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.

(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.

(c) The COR is not authorized to perform, formally or informally, any of the following actions:

(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;

21 | P a g e

(2) Waive or agree to modification of the delivery schedule;

(3) Make any final decision on any contract matter subject to the Disputes Clause;

(4) Terminate, for any reason, the Contractor's right to proceed;

(5) Obligate in any way, the payment of money by the Government.

(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.

(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause.

A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.

(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.

(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.

(End of clause)

1452.203-70 Restrictions on Endorsements. Restriction on Endorsements - Department of the interior (JUL 1996)

The Contractor shall not refer to contracts awarded by the Department of the Interior in commercial advertising, as defined in FAR 31.205-1, in a manner which states or implies that the product or service provided is approved or endorsed by the Government, or is considered by the Government to be superior to other products or services. This restriction is intended to avoid the appearance of preference by the Government toward any product or service. The Contractor may request the Contracting Officer to make a determination as to the propriety of promotional material.

(End of clause)

1452.201-70 AUTHORITIES AND DELEGATIONS (SEP 2011)

(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.

22 | P a g e

(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.

(c) The COR is not authorized to perform, formally or informally, any of the following actions:

(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;

(2) Waive or agree to modification of the delivery schedule;

(3) Make any final decision on any contract matter subject to the Disputes Clause;

(4) Terminate, for any reason, the Contractor's right to proceed;

(5) Obligate in any way, the payment of money by the Government.

(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.

(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause.

A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.

(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.

(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.

(End of clause)

1452.203-70 Restrictions on Endorsements. Restriction on Endorsements - Department of the interior (JUL 1996)

The Contractor shall not refer to contracts awarded by the Department of the Interior in commercial advertising, as defined in FAR 31.205-1, in a manner which states or implies that the product or service provided is approved or endorsed by the Government, or is considered by the Government to be superior to other products or services. This restriction is intended to avoid the appearance of preference by the Government toward any product or service. The Contractor may request the Contracting Officer to make a determination as to the propriety of promotional material.

23 | P a g e

(End of clause)

1452.215-70 Examination of Records by the Department of the Interior. Examination of Records by the Department of the Interior (APR 1984)

For purposes of the Examination of Records by the Comptroller General clause of this contract (FAR 52.215-1), the Secretary of the Interior, the Inspector General, and their duly authorized representative(s) from the Department of the Interior shall have the same access and examination rights as the Comptroller General of the United States.

(End of clause)

(End of Section I)

SECTION J – LIST OF ATTACHMENTS

A04 Statement of Work 2006 B03 Construction Wage Determination 2006 B06 Bid Schedule (Quote) 2026

(End of Section J)

SECTION K – REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS OF OFFERORS

The following clauses are incorporated by reference:

52.203-18 Prohibition on Contracting with Entities that Require Certain Internal

Confidentiality Agreements or Statements-Representation

JAN 2017

52.223-4 Recovered Material Certification MAY 2008

NOTE for SAM Representations: System updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in agency.

Contracting officers will not consider representations when making award decisions or enforce requirements. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.

*NOTE: The following provisions are provided in full text:

(End of provision)

24 | P a g e

52.209-11…

This is the start of the file's text. The full file is on GovTribe.