B12_Q_A_0001.pdf

PDF 141 KB Posted

Attached to
OK-DEEP FORK NWR-QUARTERS HVAC REPLACEM
Solicitation number
140FF027Q0025
Issued by
Not on record

About this file

This is a Questions and Answers document addressing clarifications related to an HVAC installation contract.

The project requires installation of two new 5-ton heat pump systems with factory-installed 15–20 kW electric backup heat kits, two smart thermostats (one per system), and associated ductwork modifications. For ductwork sealing, contractors must seal all identified duct leakage points and restore any damaged or missing insulation and insulation components; alternative methods such as internal aerosol duct sealing (e.g., Aeroseal) with before and after leakage testing are acceptable. The contractor is responsible for proposing a solution to eliminate the existing common return air system and enable each new unit to operate independently. An existing ductless mini-split system is excluded from the contract scope. The ten-inch uninsulated duct in the mechanical room is a cold air return, and industry standards must be followed for insulation requirements. Contractors must submit an American-manufactured substitute of equal performance to comply with Buy American requirements (FAR 52.225-9); the specified Rheem/Ruud units are not U.S. manufactured. A 5-year parts warranty is required and may be satisfied through a combination of manufacturer and third-party extended warranty coverage.

Completion is due 30 days after receipt of order, with the period of performance to be determined on the award document. Past performance information is required for both the prime contractor and proposed subcontractor. The applicable wage determination is OK20260055 (Okmulgee and Wagoner counties). Section L, Factor 1 regarding hip roof framing and standing seam metal roofing does not apply to this HVAC project.

View the file

Other files

File Type Posted
Sol_140FF027Q0025_Amd_0001.pdf PDF
A04_Statement_of_Work_(SOW)_Rev-1.pdf PDF
A04_Bid_Schedule_Rev-1.pdf PDF
Sol_140FF027Q0025.pdf PDF
B03_General_Decision.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question & Answers

• RFI 1 - Sealing Existing Wrapped Ductwork The Statement of Work requires sealing all ductwork in the attic and mechanical rooms. The existing ductwork is externally insulated with duct wrap, which conceals many joints and connections. Please clarify whether the contractor is required to remove or pull back existing insulation to expose and reseal concealed joints throughout the duct system, or whether sealing is limited to accessible connections and identified leakage locations.

Seal all identified duct leakage points and restore any damaged or missing insulation and insulation components.

• RFI 2 - Existing FSK Tape and Insulation Jacket Repairs Several areas of existing FSK facing tape were observed peeling or partially detached while the insulation remains in place. Please clarify whether all loose or deteriorated FSK tape throughout the existing duct system must be repaired or replaced, or whether repairs are limited to locations where the insulation jacket is compromised.

Seal all identified duct leakage points and restore any damaged or missing insulation and insulation components.

• RFI 3 - Existing Common Return Air System The Statement of Work requires modification of the existing return air system to eliminate the common return serving both air handlers. During the site visit, we observed that both air handlers are installed side by side on a shared return air platform. The primary return is located in the adjacent hallway and enters the common plenum beneath the equipment. Additional return connections include a 10-inch round duct routed through the attic to a lobby filter grille and a 14 x 14 grille located in the front of the platform within the mechanical room.

Due to the existing configuration, installing a partition between the air handlers would restrict one unit’s access to the primary return, potentially resulting in inadequate return airflow. The limited mechanical room space, adjacent doorway, existing piping, ductwork, and electrical components also restrict the ability to expand or relocate the platform.

Please provide direction on how the required separation of the return air systems is to be accomplished while maintaining adequate airflow to both 5-ton systems. If modifications to the existing platform, return ductwork, or building are required, please provide the intended configuration so that all bidders can accurately price the required work.

The contractor is responsible for proposing a solution that eliminates the common return and enables each new unit to operate independently.

• RFI 4 - Existing Mini-Split Equipment An existing ductless mini-split system was observed during the site visit but is not specifically identified in the Statement of Work. Please confirm that this equipment is to remain in place and that no replacement, modification, service, or other work on this system is required under this contract.

The mini-split system is excluded from the contract scope of work.

• RFI 5 - Insulation of Existing Round Return Duct An existing round snap-lock return duct was observed within the conditioned mechanical room. The duct is currently uninsulated. Please confirm whether this return duct may remain uninsulated within the conditioned space or whether insulation is required as part of this project.

The ten-inch uninsulated duct in the mechanical room is a cold air return.

Industry standard must be followed for any insulation requirements.

• Buy American: The SOW names Rheem/Ruud RD16AY60AJVCA heat pumps and RH2VY6024STACNJ air handlers "or equivalent," and the solicitation includes FAR 52.225-9. The distributor reports that the specified Rheem/Ruud units are not manufactured in the United States. Please confirm that offerors should propose a US manufactured equivalent system to comply with 52.225-9, or advise whether the Government will accept the specified models.

Contractor is to submit an American substitute of equal performance.

• Warranty: Manufacturers typically provide 1 year parts and 5 year compressor coverage on commercial installations. Will a manufacturer warranty combined with a third party extended warranty that brings parts coverage to 5 years satisfy the 5 year parts requirement?

Yes, S.O.W requires a 5-yr parts warranty, it does not specify a manufactures 5yr warranty.

• Electric heat: Are electric backup heat kits required in the new air handlers? If so, what kW?

Yes. Each heat-pump air handler must include a factory-installed 15–20 kW electric backup heat kit suitable for a 5-ton unit.

• Thermostats and CLIN 0006: Please confirm two smart thermostats (one per system) and the quantity and unit for CLIN 0006, which is blank on the bid schedule.

2- one for each new system.

• Past performance: May the offeror's past performance submission include projects completed by its proposed HVAC subcontractor?

The Contracting Officer can confirm that past performance information is required for both the prime contractor and the subcontractor.

• Duct sealing scope: The SOW requires the contractor to "seal all ductwork in the attic and mechanical room" and to "properly insulate, seal and cover all existing attic duct connections/vents." The attic trunk lines are externally wrapped with insulation.

Please confirm the intended scope is sealing all accessible joints, connections, plenums, takeoffs and boots, plus repairing damaged or missing insulation, and that removing and replacing all existing duct insulation to seal every joint is not required.

Would an internal aerosol duct sealing method (such as Aeroseal) with a before and after leakage test be acceptable as an alternative?

Any method that identifies and seals all duct leakage points and restores damaged or missing insulation and related components is acceptable.

• Completion time: Block 11 of the SF 1442 states completion within 30 calendar days, clause 52.211-10 states completion not later than 14 days after award, and the schedule shows a period of performance of 11/16/2026 to 12/14/2026. Which completion period governs?

Completion is to be 30 days after receipt of Order (ARO). Period of Performance is to be determined on the award document.

• Wage determination: Block 10 references General Decision OK20260078, while the attached wage determination is OK20260055 (Okmulgee and Wagoner counties).

Which applies?

The attached wage determination is OK20260055

• Technical factor: Section L, Factor 1 refers to "construction of framing structures for hip roofs and the installation of standing seam metal roofing." Please confirm this does not apply to this HVAC project.

This does not apply to this HVAC project.