Sol_140FF027Q0019_Amd_0001.pdf

PDF 1 MB Posted

Attached to
ID-KOOSKIA NFH-Repair Electrical Service to Mechan
Solicitation number
140FF027Q0019
Issued by
Not on record

About this file

This is Amendment 001 to Solicitation 140FF027Q0019, issued by the U.S. Fish and Wildlife Service (USFWS) Construction A/E Team 3 on November 9, 2026, for repair of electrical service to the mechanical building at Kooskia National Fish Hatchery in Idaho. The amendment is not extended and includes Questions and Answers, a Building Load Calculation Sheet, and incorporation of federal wage and leave clauses. Contractors must acknowledge receipt of this amendment prior to the offer deadline of November 17, 2026, at 10:00 AM Pacific Time by completing items 8 and 15 on the form, acknowledging receipt on each copy of the offer submitted, or submitting a separate letter or electronic communication referencing the solicitation and amendment numbers. Failure to acknowledge receipt at the designated place prior to the specified hour and date may result in rejection of the offer.

The project involves providing electrical service to a 3,870-square-foot warehouse mechanical building that requires 480-volt three-phase power. Key technical details clarified in the amendment include that the mechanical building operates at 480VAC three phase with grounds; existing underground conductors are direct burial with unknown size and no conduit; and the contractor is fully responsible for all field measurements, verification of components, coordination with Avista utility company, and ensuring all utility requirements are met. The contractor must provide all labor and material to prepare the site for transformer installation, including conduit and concrete pads. Experience requirements mandate that contractors demonstrate they have managed or served as prime on similar three-phase utility coordination projects, with past performance required from the prime contractor only, not subcontractors. The project magnitude is under $100,000 with a performance period from November 23, 2026, to January 31, 2027. Contractors awarded over $35,000 must submit a Payment Bond within 10 calendar days of award; amounts over $150,000 require both Payment and Performance Bonds. The amendment incorporates FAR clauses 52.222-55 (Minimum Wages for Contractor Workers Under Executive Order 14026) and 52.222-62 (Paid Sick Leave Under Executive Order 13706).

View the file

Other files

File Type Posted
Sol_140FF027Q0019.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: is not is required copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7.ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

PAGESOF

Contractor

The hour and date specified for receipt of Offers to sign this document and return

Jessica Tines

See continuation page

FWS, Construction A/E Team 3 5275 Leesburg Pike Falls Church VA 22041

F3C

140FF027Q0019

10/22/2026

10/22/2026

1 6

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

140FF027Q0019/0001

This amendment includes Questions and Answers, Building Load Calculation Sheet, Inclusion of clauses

Contractors are reminded that any amount awarded over $35,000 requires submission of a

Payment Bond. Any amount over $150,000 requires both Payment and Performance bonds. Bonds are due no later than 10 calendar days after award.

Project Magnitude: Under $100,000

Period of Performance: 11/23/2026 to

01/31/2027

NOTICE OF AMENDMENT TO PROPOSED PROJECT, PROPOSAL FORM

SOLICITATION NUMBER: 140FF027Q0019

AMENDMENT 001- Questions and Answers, Building Load Calculation Sheet, Inclusion of clauses

DATE: 11/09/2026

PROJECT TITLE: USFWS FWS- ID - Kooskia NFH Repair Electrical Service to Mechanical Bldg

All, This serves as an amendment to the above referenced project.

1. Question: Building Voltage:

a. Is the mechanical building operating at 480V or 208/240V?

Answer: 480vac three phase with grounds.

b. Will a step-down transformer be required?

Answer: The Contractor is fully responsible for coordinating with the utility company and ensuring all utility requirements are met.

2. Question: Service Size and Metering:

a. What is the existing service amperage?

Answer: Contractor is responsible for all field measurements and verification of components.

b. Will the new service require a 200A self-contained meter or CT metering?

Answer: The Contractor is fully responsible for coordinating with the utility company and ensuring all utility requirements are met.

c. Should the meter be installed on the building or on a pipe stand at the transformer pad?

Answer: The Contractor is fully responsible for coordinating with the utility company and ensuring all utility requirements are met.

3. Question: Transformer Distance: What is the approximate distance between the proposed transformer pad and the mechanical building?

Answer: Contractor is responsible for all field measurements and verification of components.

4. Question: Will Avista supply and install the pole riser, standoffs, and guard, or are these the contractor's responsibility?

and ensuring all utility requirements are met. The Contractor is responsible for providing all labor and material needed to prepare the site for the utility company to install the new transformer and any associated equipment. This may include but is not limited to conduit, concrete pads, etc. (Found in the SOW).

5. Question: Disconnect and Fault Current: Is a fused disconnect or main breaker preferred, and what is the available fault current from Avista?

and ensuring all utility requirements.

6. Question: Electrical Tie-In: Will the new electrical service connect directly to the existing main, or will a splice or pull box be required?

Answer: Contractor is responsible for all field measurements and verification of components.

7. Question: Existing Underground Feed: Can you provide the existing underground electrical conductor and conduit sizes?

Answer: Existing (failed) underground conductors are direct burial size unknown, no conduit.

*Please see attached Building Load Calculation Sheet submitted to Avista Power.

8. Question: Will the Government accept the required three-phase and utility-coordination project experience from our proposed licensed electrical subcontractor?

The same question applies to the past-performance projects.

Answer: No. Experience must show that the contractor has managed or was the Prime on a contract that covers similar work. The Past Performance must be for the contractor listed as the Prime.

9. Question: Please confirm the time zone for the 11/17/2026 10:00 deadline. Is it Pacific or Eastern?

Answer: The time zone for the 11/17/2026 deadline is Pacific.

The following clauses are incorporated by reference and are hereby included in the solicitation:

52.222-55 Minimum Wages for Contractor Workers Under

Executive Order 14026

JAN 2022

52.222-62 Paid Sick Leave Under Executive Order 13706 JAN 2022

Jessica Tines

Contract Specialist

Amendment of solicitation/modification of contract
Contract ID code
Amendment/modification number
Effective date
Requisition/purchase requisition number
Project number
Issued by
Code
Administered by
Code
Name and address of contractor
Code
Facility code
Amendment of solicitation number
Dated
Modification of contract/order number
Dated
This item only applies to amendments of solicitations
Accounting and appropriation data
This item applies only to modifications of contracts/orders.
This change order is issued pursuant to:
The above numbered contract/order is modified to reflect the administrative changes
This supplemental agreement is entered into pursuant to authority of:
Other
Important:
Description of amendment/modification
Name and title of signer
Contractor/offeror
Date signed
Name and title of contracting officer
Signature of Contracting Officer
Date signed
Previous edition unusable
Standard form 30 (rev. 11/2016)
Continuation sheet
Reference Number
Name of Offeror or Contractor
OPTIONAL FORM 336 (4-86))

Sponsored by GSA FAR (48 CFR) 53.110

2026-11-09T08:26:15-0500
JESSICA TINES

File details come from the government source that posted it. Updated .