This is Amendment 0001 to Solicitation 140FC326Q0056, issued by the Fish and Wildlife Service (FWS) Construction A/E Team 3 on September 14, 2026. The amendment is not extended and modifies the original solicitation regarding electrical work at fuel tank facilities.
The work scope requires contractors to install a hardwired electrical system to code replacing an existing solar power system at three fuel tanks. Specifically, contractors must add all new wiring, conduit, trenching, and disconnects from an existing wire source approximately 50 feet from the fuel tanks to the facilities. The fuel pumps must be replaced with models compatible with 120V AC with a pumping capacity of 20 GPM. No additional drawings or photos are available beyond the original Statement of Work. The project magnitude is under $10,000 with a period of performance from October 14, 2026 to November 13, 2026. Contractors are reminded that awards over $35,000 require a Payment Bond, and awards over $150,000 require both Payment and Performance Bonds, due within 10 calendar days of award. Offerors must acknowledge receipt of this amendment prior to the hour and date specified in the original solicitation by completing the form and returning it, acknowledging receipt on each copy of the offer submitted, or by separate letter or electronic communication referencing the solicitation and amendment numbers.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140FC326Q0056.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: is not is required copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7.ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
PAGESOF
Contractor
The hour and date specified for receipt of Offers to sign this document and return
Jessica Tines
See continuation page
FWS Constr A/E 3 FWS, Construction A/E Team 3 5275 Leesburg Pike Falls Church VA 22041
FWS, Construction A/E Team 3 FWS, Construction A/E Team 3 5275 Leesburg Pike Falls Church VA 22041
FC3
FC3
140FC326Q0056
09/14/2026
09/14/2026
1 2
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
140FC326Q0056/0001
This amendment includes responses to questions received.
1. Question: Could you please clarify whether the work is mainly internal wiring repair/connection work at the existing fuel tanks, or if the contractor will also need to install new conduit, trenching, disconnects, panels, or other electrical components?
Answer: The contractor needs to add all new wiring, conduit, trenching and disconnects to code to the fuel tanks from an existing wire source approximately 50' from the fuel tanks
2. Question: If possible, could you also provide a little more detail on exactly what needs to be repaired or installed at each of the three tanks? Any additional photos or drawings would be very helpful as well.
Answer: No additional drawings or photos are available. Per the SOW, nothing needs repaired.
The solar power system needs replaced with a hardwired system to code, therefor fuel pumps need to be replaced with ones that are compatible with 120V AC with a pumping capacity of 20 GPM
Contractors are reminded that any amount awarded over $35,000 requires submission of a
Payment Bond. Any amount over $150,000 requires both Payment and Performance bonds.
Bonds are due no later than 10 calendar days after award.
Project Magnitude: Under $10,000
Period of Performance: 10/14/2026 to
11/13/2026
| Amendment of solicitation/modification of contract |
| Contract ID code |
| Amendment/modification number |
| Effective date |
| Requisition/purchase requisition number |
| Project number |
| Issued by |
| Code |
| Administered by |
| Code |
| Name and address of contractor |
| Code |
| Facility code |
| Amendment of solicitation number |
| Dated |
| Modification of contract/order number |
| Dated |
| This item only applies to amendments of solicitations |
| Accounting and appropriation data |
| This item applies only to modifications of contracts/orders. |
| This change order is issued pursuant to: |
| The above numbered contract/order is modified to reflect the administrative changes |
| This supplemental agreement is entered into pursuant to authority of: |
| Other |
| Important: |
| Description of amendment/modification |
| Name and title of signer |
| Contractor/offeror |
| Date signed |
| Name and title of contracting officer |
| Signature of Contracting Officer |
| Date signed |
| Previous edition unusable |
| Standard form 30 (rev. 11/2016) |
| Continuation sheet |
| Reference Number |
| Name of Offeror or Contractor |
| OPTIONAL FORM 336 (4-86)) |
Sponsored by GSA FAR (48 CFR) 53.110
File details come from the government source that posted it. Updated .