This is Amendment 0001 to Solicitation 140FC326Q0015, issued by the U.S. Fish and Wildlife Service (FWS), Construction A/E Team 3, with an effective date of February 26, 2026. The solicitation seeks replacement of a sewage pump vault at Merced National Wildlife Refuge in California. The project involves abandonment of an existing unsafe in-ground sewage pump vault and installation of a new above-grade sewage pump vault and pumping system to improve safety and operational reliability. The work is a brand-new project with a project magnitude less than $25,000. The period of performance is April 6, 2026 to August 15, 2026. The contracting officer is Shannon Barnhill (shannon_barnhill@fws.gov). A mandatory site visit was scheduled for March 12, 2026 at 9:00 AM PST, with a questions deadline of March 16, 2026 by 4:00 PM MDT and proposals due March 30, 2026 by 4:00 PM MDT.

The amendment provides responses to twelve contractor inquiries and includes photographs of the existing deteriorated vault conditions. Key specifications and requirements clarified include: the vault should be designed for wastewater applications with approximately 500-gallon capacity; a single ½ horsepower pump system mounted directly on the vault base; a high-level audible and visible alarm system (no telemetry or remote notification required); approximately 18-28 inch invert depth from the house; approximately 35-50 feet distance to septic leach field with 2-3 feet elevation change; 200-amp electrical panel; contractor responsibility for field verification and total dynamic head calculations; use of existing electrical infrastructure with code-compliant connections; and provision of temporary bypass pumping if service maintenance is necessary during construction. The site visit sign-in sheet shows one contractor (Living Water Initiatives LLC, contact: Tanner Terrell) attended the mandatory site visit.

View the file

Other files for this federal contract opportunity

Other files attached to CA-MERCED NWR-QTRS SEPTIC SYSTEM, newest first.
File Type Posted
Sol_140FC326Q0015.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: is not is required copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7.ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

PAGESOF

Contractor

The hour and date specified for receipt of Offers to sign this document and return

Shannon Barnhill

See continuation page

FWS Constr A/E 3 FWS, Construction A/E Team 3 5275 Leesburg Pike Falls Church VA 22041

FC3

140FC326Q0015

02/26/2026

02/26/2026

1 12

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

140FC326Q0015/0001

Replacement of Sewage Pump Vault in accordance with the attached Statement of Work.

Project Magnitude: less than $25,000.00.

Please refer to 52.236-27 - Site Visit for the

Site Visit details. Contractors are required to

RSVP to the Contracting Officer.

The purpose of this amendment is to provide the following:

1) Responses to questions received.

2) The site visit sign in sheet.

All other terms and conditions remain unchanged.

Period of Performance: 04/06/2026 to

08/15/2026

Points of Contact:

Contractor:

TBD

Contracting Officer Representative (COR):

TBD

Contracting Officer:

Shannon Barnhill shannon_barnhill@fws.gov

Questions and Responses Question1: Is there any incumbent/recompete or is this a brand-new project? If yes, could you please provide us with their award number or even if the customer bought similar services in the past.

Response: This project is considered a brand-new project. The work involves the abandonment of an existing unsafe sewage pump vault and the installation of a new above-grade sewage pump vault and pumping system at Merced National Wildlife Refuge to improve safety and operational reliability.

Question 2: Are there any existing photos of the site and vault that you can share?

Visual reference would help us better assess access, layout, and overall conditions.

Response:

Question 3: Additionally, could you provide the specifications for the following:

1) Vault

Response: Currently presume cast iron or different type of metal made. Dilapidated and in need of replacement

2) Pump

Response: ½ horsepower pump

3) Alarm system

Response: Currently there are no alarm systems for the current vault pump

4) Electrical panel

Response: 200 Amp panel

Question 4: Regarding the pump installation, can you confirm whether the pump is mounted on guide rails, suspended, or set directly on the base of the vault?

Response: It is set directly on the base of the vault

Question 5: Do we know the invert depth of the pipe entering the vault from the house?

Response: Approximately 18 to 28 inches.

Question 6: Is there going to be an emergency bypass line in case the house loses power and the vault fills up? If so, how will that be designed?

Response: It only requires installation of a pump, float system, and high-level audible/visible alarm.

In the event of power loss, the system relies on storage capacity within the vault and the high-level alarm to alert personnel.

Question 7: Do we know the elevation change and distance from the pump vault to the septic leach field? This information is needed to calculate the total dynamic head

(TDH).

Response: The Contractor is responsible for field verification and determining TDH as part of their installation and equipment selection. The distance to the septic leach is approximately 35 -50 feet and elevation change is approximately 2-3 feet.

Question 8: Do we know the storage requirement for the pump vault in gallons?

Response: The Contractor is expected to furnish a vault “designed for wastewater applications” and compliant with safety and operational needs, the current pump vault capacity site at 500 gallons.

Question 9: Do we know if we are going with a duplex pump station or single pump station?

Response: This is single pump system, Question 10: Are we trenching new power and conduit back to the main house panel?

Response: The contractor may use existing electrical infrastructure. The Contractor should assume responsibility for providing a complete and code-compliant electrical connection.

Question 11: Will the contractor be responsible for bypass pumping during construction while the existing vault is abandoned? It appears that the existing pump station is already not functioning.

Response: If maintaining service will be necessary, the Contractor will provide temporary bypass pumping

Question 12: Are there any requirements for telemetry, autodialer, or remote alarm notification for the pump station?

Response: Only requires:

• Audible alarm

• Visible alarm

Amendment of solicitation/modification of contract
Contract ID code
Amendment/modification number
Effective date
Requisition/purchase requisition number
Project number
Issued by
Code
Administered by
Code
Name and address of contractor
Code
Facility code
Amendment of solicitation number
Dated
Modification of contract/order number
Dated
This item only applies to amendments of solicitations
Accounting and appropriation data
This item applies only to modifications of contracts/orders.
This change order is issued pursuant to:
The above numbered contract/order is modified to reflect the administrative changes
This supplemental agreement is entered into pursuant to authority of:
Other
Important:
Description of amendment/modification
Name and title of signer
Contractor/offeror
Date signed
Name and title of contracting officer
Signature of Contracting Officer
Date signed
Previous edition unusable
Standard form 30 (rev. 11/2016)
Continuation sheet
Reference Number
Name of Offeror or Contractor
OPTIONAL FORM 336 (4-86))

Sponsored by GSA FAR (48 CFR) 53.110

B09 Amendment 0001 Questions and Responses
B12 Site Visit Sign In Sheet

File details come from the government source that posted it. Updated .