Sol_140FC324R0011_Amd_0002.pdf
PDF 88 KB Posted
- Attached to
- WA-TOPPENISH NWR-DESIGN/BUILD WELL
- Solicitation number
- 140FC324R0011
About this file
This document is an amendment to a solicitation for a design-build well project at the Toppenish National Wildlife Refuge in Washington. The amendment provides additional details, including a Google map showing the project location and coordinate values, and reminds contractors that payment and performance bonds are required for awards over $35,000 and $150,000, respectively. The project magnitude is between $500,000 and $1,000,000, and a site visit is scheduled for July 30, 2024. All Phase 1 questions must be submitted via email to the Contracting Officer by August 5, 2024. The period of performance is September 23, 2024 to January 22, 2026.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140FC324R0011_Amd_0003.pdf | ||
| A06_MAP_0002.pdf | ||
| Sol_140FC324R0011_Amd_0001.pdf | ||
| Sol_140FC324R0011.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140FC324R0011
x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
FC3
Falls Church VA 22041 5275 Leesburg Pike FWS, Construction A/E Team 3 FWS, Construction A/E Team 3
FC3
Falls Church VA 22041 5275 Leesburg Pike FWS, Construction A/E Team 3 FWS Constr A/E 3
07/22/20240002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
07/22/2024
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
This amendment includes a Google map showing the project address and coordinate values to the existing well.
Contractors are reminded that any amount awarded over $35,000 requires submission of a
Payment Bond. Any amount over $150,000 requires both payment and performance bonds. Bonds are due no later than 10 calendar days after award.
Project Magnitude- Between $500,000 and $1,000,000.
A site visit will be held on 07/30/24 at 12:00 am PDT at 21 Pump House Road. Toppenish, WA
98948
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Jessica Tines
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 2
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140FC324R0011/0002
All Phase 1 questions should be submitted via email to jessica_tines@fws.gov NLT 08/05/2024 at
10:00 am PDT. Questions received in any other manner will not be entertained.
Period of Performance: 09/23/2024 to 01/22/2026
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
File details come from the government source that posted it. Updated .