This is a Questions and Answers document for the Bonner House Demo Request for Information (RFI).
The Bonner House demolition project has a period of performance of 76 days following award. The scope of work includes removal of footings, foundation, and basement materials, as well as backfill and site restoration with grass establishment. Waste disposal tickets must be submitted as part of the Statement of Work requirements. Progress payments to the contractor are not permitted. The property is located on federally owned land and does not require a local county demolition permit. Utilities have been disconnected from the structure prior to contract performance.
Regarding site-specific conditions, the septic tank and well may be abandoned in place. The refuge will be responsible for removal of the dual fuel tank located exterior to the building. Asbestos abatement must be performed by a West Virginia licensed contractor in compliance with West Virginia rules and regulations; air monitoring and clearance reports are required per state regulations. Performance bonds are not required regardless of contract price. No site visit sign-in sheet is necessary, and posting to SAM is not applicable.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140FC226Q0037_Amd_0002.pdf | ||
| Sol_140FC226Q0037_Amd_0001.pdf | ||
| SOW_Wage_Rate_Clauses.pdf | ||
| A06_Bonner_Home_Abestos_report.pdf | ||
| A06_Bonner_House_Photos.pdf | ||
| Sol_140FC226Q0037.pdf | ||
| Section_B.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bonner House Demo RFI’s
Please confirm that the period of performance is only 76 days after award. – This is correct
Does the scope include removal of footings? If you are referring to the foundation and basement then yes it is included in the scope.
Is backfill and site restoration (the establishment of grass) required? Yes, this is in the scope of work.
Does the duel tank exterior to the building contain any fuel oil or other materials? The refuge will be responsible for removal of this tank.
Can progress payments be made to contractor? No
Can the site visit sign in sheet be posted to SAM? There is no sign in sheet.
Will waste disposal tickets be required to be submitted? Yes, this is included in the SOW
Have utilities been disconnected from the home? YES
Has the septic tank been located and is it required to be abandoned or remain in place? NO, can be abandon in place
Has the well been located and is it required to be abandoned? Yes, can be abandon.
Is this property on federally owned land? YES
Is a local Demolition Permit required through the County? No permit is required
Can a Virginia Asbestos Licensed Contractor perform the asbestos abatement? Appears you must be a W.V asbestos licensed contractor.
Will any air monitoring or clearance reports be required? Need to follow WV rules and regulations for asbestos removal.
Will any bonds be required regardless of price? No.