This document is a set of Questions and Answers related to Solicitation 140FC224Q0059 for Interior Refinish/Painting at the Waubay National Wildlife Refuge Visitor Center in South Dakota.

The key details are:

  • The solicitation requires painting the interior walls and ceilings of the Visitor Center, including areas around windows, doors, and permanent exhibits. Measurements for the wall and ceiling areas are provided.
  • The government will remove exhibits from the walls, but the contractor is responsible for protecting floors and other permanent fixtures during the work.
  • A small amount of mold was found in the entryway that needs to be addressed. The government will provide a dumpster for disposal of project waste, with hazardous materials disposed of properly.
  • The work can only be performed during normal business hours, Monday through Friday, and the Visitor Center will be closed to the public during the project. Onsite storage can be arranged but the government will not be responsible for contractor materials or equipment.
  • No specific paint brand or type is required, but the selection should consider the public use and long-term needs of the space.

View the file

Other files

File Type Posted
Sol_140FC224Q0059_Amd_0001.pdf PDF
Provisions_and_Clauses.doc DOC document
Wage_Determination_SD20240021.pdf PDF
SOW.docx DOCX document
Sol_140FC224Q0059.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation 140FC224Q0059 Questions & Answers

1. Could you please provide the exact square footage area which needs to be repainted?

A: Contractors are responsible for taking their own measurements, estimates are provided.

North wall is 27 feet wide x 14 feet high, east and west walls are 15 feet wide x 14 feet high sloping down to 10 feet high, south wall is 27 feet wide x 10’ high. Windows, doors, and permanent exhibits is included in these measurements.

2. Will we be required to remove items hanging from the wall such as picture frames etc..

A: Refuge staff will remove exhibits from walls.

3. Will we be required to remove and replace any drywall? I see there is a picture where the area that looks like moisture was present in the ceiling.

A: This is not from moisture, it is dirt from a heating vent located below the ceiling location.

No replacement of drywall is anticipated.

4. Surface Condition: Are there any existing issues with the walls or ceilings beyond the mentioned cracks and glue residue that could impact the work, such as water damage or mold?

A: A small amount of mold was found in the entryway, from a previously known water leak.

No large areas of water damage or mold.

5. Paint Specifications: Are there any specific brand or type of paint that must be used? Should the paint be low-VOC or have other environmental certifications?

A: Area to painted is a public use area and the rest of the building contains permanent office space. Need to consider daily, long term use in paint selection.

6. Wallpaper Type: What type of wallpaper is currently on the walls? Is it standard, or does it have additional layers like vinyl that might require special removal techniques?

A: Standard wallpaper. Much of is already beginning to peel. Expect it will be fairly easy to remove as glue is dry and brittle.

7. Site Access: Will the Contractor have access to the site during work hours? Are there any areas that will remain off-limits or any specific site access protocols?

A: Contractor will have access to site from 8:00 to 4:30 Monday – Friday, except Federal holidays.

8. Storage: Is there an on-site storage area available for materials and equipment during the project?

A: Storage can be arranged for materials and equipment; however, the Government will not assume responsibility for these items.

9. Site Preparation: Who is responsible for site preparation, such as moving furniture or displays, covering floors, and protecting adjacent areas from dust or paint splatters?

A: Refuge staff will remove exhibits from walls. Two large permanent wall mounted exhibits will need to be protected from paint/dust. Two large portable exhibits will be moved to center of room and will need to be protected from paint/dust. Room is carpeted so floor will need to be protected.

10. Waste Disposal: Are there specific disposal procedures to follow?

A: Dumpster is available to accommodate disposal of trash. Hazardous waste, like paint and chemicals, shall be disposed of in accordance with South Dakota regulations.

11. Concurrent Activities: Will other contractors or government staff be working on-site simultaneously, potentially impacting scheduling or requiring coordination?

A: No other contractors will be working in the Visitor Center. Refuge staff will be present in offices located in building. Visitor Center area will be closed to the public during painting project.