This document outlines the scope of work for a federal contract to replace a rice trunk on the Combahee Fields Unit of the Ernest F. Hollings ACE Basin National Wildlife Refuge. The project will require removing the existing bulkhead walls and rice trunk, and replacing them with new materials according to the provided plans. The old rice trunk and walls will be fully removed, and the new trunk and walls will be installed per specifications within 12 months.

The related federal contract opportunity is solicitation number 140FC124R0031 from the U.S. Fish and Wildlife Service to replace the rice trunk on the Combahee Fields Unit of the Ernest F. Hollings ACE Basin National Wildlife Refuge. The solicitation is for the scope of work described in the document and will be awarded by the Department of the Interior Fish and Wildlife Service.

View the file

Other files for this federal contract opportunity

Other files attached to Rice Trunk Replacement on Combahee Fields Unit (Er, newest first.
File Type Posted
B03_DOL_Wage_Determination_SC20240004_01_05_2024.pdf PDF
Past_Experience_Questionnaire.pdf PDF
Sol_140FC124R0031.pdf PDF
B03_DOL_Wage_Determination_SC20240041_01_05_2024.pdf PDF
A06_Rice_Trunk_Plan_Specifications.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project: Ernest F. Hollings ACE Basin NWR rice trunk replacement on Combahee Fields Unit Scope of work:

Project will require the removal of an existing old rice trunk and replacement of a new rice trunk.

Removal of the old will consist of removal of bulkhead walls the width of the existing rice trunk to remove the existing trunk, the wall will be replace with like material and backfilled will soil material.

Installation of the new trunk will be consistent with the provided plans.

Work must be completed in 12 months