Sol_140F0S26Q0004_Amd_0001.pdf
PDF 209 KB Posted
- Attached to
- NV-STILLWATER NWRC-HUNTER RD GRAVEL PROJ
- Solicitation number
- 140F0S26Q0004
About this file
This is Amendment 001 to a federal solicitation for the Stillwater Hunter Road Gravel Project issued by the U.S. Fish and Wildlife Service (FWS) Over SAT G/S, effective February 13, 2026. The solicitation number is 140F0S26Q0004, with a period of performance from March 1, 2026 through June 30, 2026. The amendment addresses a Request for Information (RFI) regarding truck delivery spacing and scheduling requirements for gravel material delivery to the project site.
The amendment clarifies that the refuge has flexibility on truck spacing and delivery scheduling, contrary to the original 15-minute minimum interval requirement. Contractors may now coordinate consecutive dumping with refuge staff, and the 15-minute interval is not mandatory throughout the shift but can vary based on site coordination with the project manager. Alternative staging and sequencing methods are acceptable provided safety and site control are maintained. Historical delivery data indicates approximately 800-1,000 tons of gravel per shift using belly dump trucks, with delivery averaging 800-1,000 tons per day across similar past projects. The contractor remains responsible for final delivery coordination with the on-site project manager and ensuring gravel reaches its final location on the designated delivery route. Offerors must acknowledge receipt of this amendment by February 13, 2026.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140F0S26Q0004_Amd_0002.pdf | ||
| Sol_140F0S26Q0004.pdf | ||
| B08_-_Solic_140F0S26Q0004_Fallon_NV_Gravel.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: is not is required copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7.ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
PAGESOF
Contractor
The hour and date specified for receipt of Offers to sign this document and return
Robert Sung
See continuation page
FWS Over SAT G/S FWS, Over SAT G/S 5275 Leesburg Pike Falls Church VA 22041
F0S
140F0S26Q0004
02/13/2026
02/13/2026
1 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
140F0S26Q0004/0001
Stillwater Hunter Road Gravel Project
This amendment is hereby issued to respond to a
RFI Q&A:
Q1: After reviewing this requirement with our subcontractor, we received the following clarification from them:
"If the trucks ran consecutively, they could all dump in sequence, allowing the refuge staff time to work the material before the trucks returned for their second and third trips. The total daily tonnage can be adjusted to suit your needs by increasing or decreasing the number of trucks. We anticipate approximately
800 - 1,000 tons per shift. The material would be delivered using belly dump trains, leaving a window for the refuge staff to spread.
We would revise the proposal to include minimum truck spacing. However, doing so would limit roughly half the trucks to only two loads per day, increasing the cost per ton. Based on this scenario and eight trucks per day, spacing would be approximately 15-30 minutes between loads, followed by about 1.25 hours of downtime between the last truck in the first rotation and the first truck returning for the second rotation. This would result in approximately
800 tons per shift."
Based on this, strict adherence to the minimum
15-minute spacing requirement would materially affect operational efficiency and increase the cost per ton.
We would respectfully like to inquire whether there is any flexibility in the delivery spacing requirement. Specifically:
A. Would consecutive dumping be acceptable if coordinated safely and efficiently with the grading contractor?
B. Is the 15-minute minimum interval mandatory throughout the entire shift, or could it be adjusted during certain delivery windows?
C. Would alternative staging or sequencing methods be considered, provided safety and site control are maintained?
A1: The refuge does have some flexibility on
Continued...
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
140F0S26Q0004/0001 the spacing of the trucks and could be coordinated at that time with the project coordinator. During the work day - we will have a refuge staff member who is stationed to take the tickets from drivers and direct them when it is safe to unload. However, we have completed similar projects at least three times in the past 5 years with various contractors.
A 15-minute interval between trucks was generally what they averaged between trucks just based on how long it took the for each load to be filled between the first and the next truck at the gravel pit. Across the projects, delivery has averaged between 800-1k tons per day.
For the specific questions:
A. Yes, consecutive dumping can be coordinated with the refuge staff who will be completing the gravel grading.
B. The 15 minute interval would not be mandatory and could vary throughout the shift, but would need to be coordinated with staff on site.
C. Alternative staging or sequencing methods could be considered, provided safety and site control are maintained. The contractor would be responsible for coordinating with the project manager on site and ultimately would be responsible for ensuring the gravel is delivered to its final location on the delivery route.
Period of Performance: 03/01/2026 to
06/30/2026
| Amendment of solicitation/modification of contract |
| Contract ID code |
| Amendment/modification number |
| Effective date |
| Requisition/purchase requisition number |
| Project number |
| Issued by |
| Code |
| Administered by |
| Code |
| Name and address of contractor |
| Code |
| Facility code |
| Amendment of solicitation number |
| Dated |
| Modification of contract/order number |
| Dated |
| This item only applies to amendments of solicitations |
| Accounting and appropriation data |
| This item applies only to modifications of contracts/orders. |
| This change order is issued pursuant to: |
| The above numbered contract/order is modified to reflect the administrative changes |
| This supplemental agreement is entered into pursuant to authority of: |
| Other |
| Important: |
| Description of amendment/modification |
| Name and title of signer |
| Contractor/offeror |
| Date signed |
| Name and title of contracting officer |
| Signature of Contracting Officer |
| Date signed |
| Previous edition unusable |
| Standard form 30 (rev. 11/2016) |
| Continuation sheet |
| Reference Number |
| Name of Offeror or Contractor |
| OPTIONAL FORM 336 (4-86)) |
Sponsored by GSA FAR (48 CFR) 53.110
File details come from the government source that posted it. Updated .