UPDATED 8/17/2022
Table 2
Task Time Duration from Award*
Initial meeting and discussion between consultant and U.S. Fish and Wildlife cultural resource staff
(USFWS)
1 week
Consultant submits a draft of report and forms to USFWS Zone Archaeologist
~ late August 2023
USFWS Zone Archaeologist provides comments back to the consultant
~ early September 2023
Consultant submits revised report and forms to USFWS Zone Archaeologist
~ mid-September 2023
USFWS Zone Archaeologist submits forms and reports to SHPO for their review
~ mid-September 2023
USFWS Zone Archaeologist provides SHPO comments to consultant for final revisions of forms and report
~ mid-September 2023
Consultant submits final forms, report, and photographs
~ late November 2023
* Actual calendar dates will be established at the start of the project.