Sol_140F0321R0009_Amd_0002.pdf

PDF 123 KB Posted

Attached to
US FWS Visitor Center Interpretive Design Master P Federal contract opportunity
Solicitation number
140F0321R0009
Issued by
Department of the Interior Fish and Wildlife Service

View the file

Other files for this federal contract opportunity

Other files attached to US FWS Visitor Center Interpretive Design Master P, newest first.
File Type Posted
Sol_140F0321R0009_Amd_0001.pdf PDF
Sol_140F0321R0009.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

140F0321R0009 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

F03

Bloomington MN 55437-1458 5600 American Blvd West Suite U.S. Fish & Wildlife Service, Rgn 3

06/10/20210002

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

06/10/2021

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose of this amendment is to answer questions received by the cut off date. Any new questions received may not get answered before the solicitation closes.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Anthony Kuntz

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

140F0321R0009

Questions and Answers

06/24/2021

1. Can you confirm that “no formal format is required” and that a submission with unit and total price is sufficient?

Answer: No formal format is required per the instructions in the solicitation. You will need to provide sufficient information to be evaluated using the evaluation criteria.

2. Is there a deadline for the submission of questions?

Answer: Yes, 06/23/2021 2:00 p.m. Alaska Time

3. In the Scope of Work section, the solicitation states that the deadline for completion of Phase 1 is September 1, 2022, and the deadline for completion of Phase 2 is November 1, 2022. Can you confirm that these dates should be September 1, 2021, and November 1, 2021, respectively?

Answer: Yes, Phase I is due September 1, 2021 and Phase II is due November 1, 2021, Phase III is due March 31, 2022, Phase IV is due May 31, 2022.

4. In addition to a completed form SF-1449, can you confirm that our solicitation response should address the evaluation criteria on page 4 of the solicitation?

Answer: Per the solicitation, you are not required to use the 1449, however you may choose to use it or any other format. Yes, you should address the evaluation criteria in the solicitation.

5. Does FWS require any additional information to be included with our submission in addition to the completed SI-1449 and the responses to the evaluation criteria?

Answer: Include all submission requirements within the solicitation.

6. Can FWS provide a budget range for completion of this scope of work?

Answer: The budget range is between $25,000.00 and $100,000.00 and closer to the lower end.

7. Should our Quote/ Response be directed to you via email by the due date of July 1, 2021 1700 ES? Or is a hard copy required?

Answer: Per the solicitation, proposals shall be emailed directly to anthony_kuntz@fws.gov. A hard copy shall not be mailed.

8. Will one of the interagency partners on the Interpretive Team assign a Tribal Liaison for indigenous engagement during the planning process or should we factor that into our scope of work and fee proposal?

Answer: The government will provide Tribal Liaison support and coordination.

9. Can the FWS share who will be on the Interpretive Planning Team and what their roles in the project will be?

Answer: Names of individuals will not be provided during the solicitation period.

Representatives from Tetlin NWR , Yukon Charley NP, Wrangell St. Elias NPP, Eastern Interior District BLM, USFWS Regional Office, and Tok Chamber of Commerce.

mailto:anthony_kuntz@fws.gov

10. Who will ultimately review and issue approvals of the submittals?

Answer: Names of individuals will not be provided during the solicitation period.

11. Apart from the US Fish and Wildlife Service, the National Wildlife Refuge System, the Tok Chamber of Commerce, the National Park Service and the Bureau of Land Management are there any other stakeholders to consider in the project? If so, who are they?

Answer: Names of individuals will not be provided during the solicitation period.

See question 9 for a list of stakeholders.

12. Has there been any evaluation of the current exhibit and facilities at the Visitor Center? If so, can you share it?

Answer: There has not been a formal evaluation of the current exhibits or facilities

13. Will the interpretive master plan have to accommodate the current facilities and building(s) of the visitor center or do you expect updates to the building, construction and/or any other A&E improvements?

Answer:

The master plan should keep the basic integrity of the current building but the planning team could consider some modifications to the existing structure.

End of Questions