Rachel Carson Multi-Purpose Facility – Bidder’s Questions (Questions received by OPA from Keith Davis via email.)

Response from OPA Response from Contracting Officer

1. There are door hardware items spec’d that do not fall under Buy American. Should we carry the hardware as spec’d at this point and exclude Buy American?

Response from OPA: Provide a product by one of the listed manufacturers that meets the Buy American act requirements.

Response from Contracting Officer: If the American made product exceeds the cost of foreign material by more than 20 percent, the FWS will prepare a waiver under the Buy America Act to allow the foreign made product.

2. Tags:

a. All 60-minute rated Tags vary in required material and finish. Should all of the 60-minute rated openings be receiving the Fire Frames – Timberline Series frames?

Response from OPA: Only door 102 will receive Fire Frame Timberline Series, with 120-minute fire rating for the frame and window, and 90-minute fire rating for the door. Other openings will receive fire-rated stile and rail wood doors and fire-rated wood door frames as described in specification section 081433.

b. Tag 104 is an exterior opening that is scheduled as a wood door and wood frame.

Should this door and frame be quoted as fiberglass?

Response from OPA: Exterior doors S05A, 104, and 122 should be updated to fiberglass doors (type F) and fiberglass frames.

3. Drawings AE101, AE103 & AE106 have a Section designation for Drawing A222 and AE222. I cannot find this drawing. Does it exist?

Response from OPA: A222 should read ‘AE222’ and A221 should read ‘AE221’.

4. Drawings AE701 Partial Basement Reflected Ceiling Plan North, Storage Room 008, is indicating open structure above but Keynote #1 indicates acoustical tile. Please clarify.

Response from OPA: Storage Room 008 will be open to structure above – keynote 1 should be removed from Storage Room 008.

5. There is a lot of mention about the mockup. Can you please clarify the extent required?

Response from OPA: Mockups may be constructed in place and become part of the final construction assembly once reviewed and approved by the Contracting Officer and Architect.

a. Will an onsite building be the location of the mockup?

Response from OPA: Please refer to response #5.

b. Volume #1 of the specifications on page 88 indicated that the Lab mockup to be constructed at the testing facility, please clarify where that would be or if this is needed?

Response from OPA: Laboratory mockups will not be required.

c. Exterior mockup consists of multiple products assemblies and sub-assemblies, please clarify the limits. Some of these products will be exposed to the weather.

Response from OPA: Please refer to response #5. To minimize weather exposure of assemblies, provide appropriate notification to Contracting Officer and Architect for mockup review.

d. Room mockup to include all finishes (how will weather protection be accomplished?)

Response from OPA: Please refer to response #5. Room finish mockup may be located inside.

e. Specification Section 086300 page 589 indicates that a mockup of the skylight will be required. Will a separate skylight be required just for the mockup? If we are proceeding with approved submittals for the requested skylight would any change at that point, be just part of the quality control process? Is a mockup necessary? Please clarify.

Response from OPA: Please refer to response #5. A separate skylight mockup will not be required.

6. Meeting Room 017 shown on Drawing AE102 shows 3 windows and Door 017A. Please confirm these are existing with no work required.

Response from OPA: Door 017A and windows in meeting Room 017 are existing with no work required.

7. Drawing AE620 Window Types is showing a window C8 but I have not been able to locate this window on the project. Can you clarify if this window is being used?

Response from OPA: Window types C8 and C9 are part of the C6 aluminum clad wood window system, located at the ends and rotated 90 degrees at the building corner.

8. We do not see any drawings or specifications for fire suppression. Please confirm this system does not exist and we will not be required to install as part of the scope of work.

Response from OPA: An automatic fire suppression system is not required for the project.

9. Has asbestos abatement already been done? Is all the asbestos noted in the report already removed?

Response from Contracting Officer: All asbestos has been removed from the building.

10. What contractor conducted the asbestos removal?

Response from Contracting Officer: Asbestos removal was completed on 8/10/2021 by MECX 8864 Interchange Dr., Houston, TX 77054-2512 Phone (713) 585-7000, subcontracted to Atlantic Environmental Contractors, 81 East Ave., Lewiston, ME, 04240, Phone (207) 783- 1908.

11. Underground Oil Tank: Where is the underground oil storage tank located? Is it going to be removed? How large is it? Was a permit with the fire department pulled when this tank was installed?

Response from Contracting Officer: The 1955 heating record drawing shows a 1,000-gallon oil tank near the location of existing attached garage (to be removed), before the garage was added onto the house (next to the kitchen). It is uncertain that this underground tank still exists, but some water was pumped from an adjacent old fill line. FWS has found no documentation of this tank, however when the property was purchased, the FWS Realty Department found in their Level I Environmental Assessment some evidence that an underground tank had been removed. Contractors should not include any cost for underground tank removal in their proposals. If a buried tank is found during construction, the issue will be addressed at that time.

12. Can the large garage be used for storage by the contractor(s) during the performance period?

Response from Contracting Officer: The large garage cannot be used for storage of materials or as an office. However, the general contractor can bring their own storage containers to the site.

13. Can the small garage be used for storage and/or office by the contractor(s) during the performance period?

Response from Contracting Officer: The small garage cannot be used for storage of materials or as an office. However, the general contractor can bring their own storage containers to the site.

14. Are there articles that describe the construction of the home by Elmina Sewall that can be shared with the bidders?

Response from Contracting Officer: The known original building drawings have been uploaded to SAM.gov. These drawings are FOR REFERENCE ONLY, NOT TO BE ASSUMED AS

ACCURATE AS-BUILT DRAWINGS.

15. Will the list of contractors and subcontractors who visited the site (today) be shared with all bidders?

Response from Contracting Officer: The records of attendance for the site visits on 09-22-2022 and 09-28-2022 are attached to this .pdf document.

16. Section A 52.236-1 Performance of Work by the Contractor states that “The contractor shall perform on site, with its own organization, work equivalent to at least 100% of the total amount of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performing the work, the Contractor requests a reduction, and the Contracting Officer determines that the reduction would be to the advantage of the Government”. Generally, contracts of this type stipulate the prime contractors must self-perform a minimum of 15% of the contract. Please clarify the intent of the 100% statement.

Response from Contracting Officer: The subject clause has been removed.

17. We respectfully request the schedule to be changed from 5 to 10 pages. Please Confirm.

Response from Contracting Officer: A 10-page schedule is acceptable.

18. Is there a Masonry Cleaning & Restoration Specification?

Response from OPA: A masonry cleaning & restoration specification is not included.

19. Drawing C-001 Civil Notes & Legends Civil Notes paragraph 6 - Has the "Stormwater Permit" been obtained?

Response from OPA: Yes, a copy of the Maine DEP Stormwater Permit is attached.

20. Questions regarding the photovoltaic system and the Buy American Act:

Can someone provide documentation of the specific Buy American requirements for this project? We want to make sure we're all on the same page and have the correct info.

What is the difference between component analysis and subcomponent analysis?

Which is required for this project? If you have specific documentation or descriptions of this, that would be helpful.

What does the waiver/exception application process look like?

Could you provide documentation about the specific trade agreements that impact the Buy American requirements and exceptions? In other words, are we able to procure from approved non-U.S. manufacturers due to trade agreements? And if so, which ones?

Response from Contracting Officer: If the American made product exceeds the cost of foreign material by more than 20 percent, the FWS will prepare a waiver under the Buy America Act to allow the foreign made product.

Item # Page Label Comments Response

1 General Question Can the RFI deadline be extended to 10/07/2022 to allow for all RFIs to be received from subcontractors from all the site visits? The deadline will not be extended.

2 General Question

Bid Alternates 1 & 2 - Please confirm that just the cost to furnish and install the solar panels themselves are to be included in the bid alternate, and that all electrical/sitework preparations should be included in the base bid.

Refer to Sheet CU103 for solar system site work included with the base bid and with each additive. Note base bid includes conduit from the building to a hand hole at the PV panelboard location. PV panelboard and wiring from the building is included in Additive No. 1. Refer to EP501, keynote 4 for details on electrical work. Note that Additive 1 includes one (1) 40KW PV system, Additive 2 includes a second 40KW system. Base bid includes conduit from panelboard to building exterior (refer to civil for location). Refer to Sheet ES101 Keynotes 2 and 3.

3 4/AE521

Roof flashing from flat roof to pitched roof is inappropriate for that application. Please provide updated detail. Terminate crown molding over flat roof area. At transition, provide additional membrane flashing layer with lap sealant.

4 6/AE520

Framing detail: No flashing shown, and no backing shown to attach to the elevator shaft. Also, the trim is called out to be Wood, but this should be PVC. Provide aluminum flashing at wall-to-roof connection. Crown molding, trim, and soffit panel to be PVC.

5 3/AE521

Flat roof to existing roof: No blocking shown at roof intersection, please provide detail which shows how this should be securely attached

Keep existing exterior sheathing up to top plate- first flat truss will be inboard. Attachement not required between new flat truss and existing but new end truss can be nailed to exterior sheathing for stability in construction. Blocking not shown at existing building roof but expected to be present (VIF). Flat roof trusses to have engineered panel blocking at bearing walls (See Sketch SK- S1 attached).

6 3/AE520

EPDM roofing is called out, but it calls for heat-welding at all seams, but this is not appropriate for this system. Please clarify appropriate method for seaming. Provide manufacturer's standard seaming materials and installation methods, refer to spec section 075323

7 1/AE623

Blocking is not shown between 8/12 roof and LVL connection, please update detail to show how this should be securely attached Refer to detail 4/SF504 for hanger on LVL. No blocking required.

8 2/SF106

It is unclear how many locations this detail occurs. Please provide an allowance all bidders should carry for this unknown quantity. Condition only directly observed at one location.

9 1/SF101

Note 13: It is unclear if the rotted sill condition is limited to the one area shown on the drawings, or if it exists elsewhere. Please provide an allowance all bidders should carry for this unknown quantity. Unit price and base bid quantities section of spec section 01.2200: Unit Prices

10 1/AD120

Note calls to remove and store chimney. Are we removing and storing the entire chimney, or just from the roof up (aka granite section)? Also, if the chimney is being stored, what is its future use? We do not see anywhere it calls for re-use Remove and salvage stone veneer from chimney. Return material to government.

11 Allowance request

Plaster ceiling repairs: A majority of the plaster ceilings are called as existing to remain, but will likely need to be repaired from other minor work occurring in the area. Please provide an allowance all bidders should carry for plaster repairs. Include a $6,000 allowance for miscellaneous plaster repairs.

12 General Question

Please confirm the requirements for appropriately abandoning the well. Should this be filled with concrete, abandoned in place, dug and remove, etc? Are there any state or Federal environmental requirements which need to be met for this? Requirements for abandoning the well are included in Specification Section 33113, Potable Water Supply Wells, Paragraph 3.3.

13 General Question

At existing wood windows, is it acceptable to replace existing weight and pulley mechanism with spring mechanisms? This will affect the pricing of if the window needs to be rebuilt entirely, or if a spring mechanism is acceptable, leaving windows in place and installing spring mechanisms without removing Replacing existing weight and pulley mechanisms with spring mechanisms is acceptable at existing wood windows.

14 89_AE102 PARTIAL BASEMENT PLAN SOUTH

Please provide sections, details and enlarged plan for the Concrete Ramp 014, including railing installation details

Ramp 014 will be wood construction, built over existing concrete step. Provide 1-1/2" diameter, painted handrail on each side.

Install ramp and handrails to comply with ABA standards.

104_AE420 STAIRS/ELEVATOR TOWER PLANS

AND SECTIONS

Please provide enlarged plans and sections at the elevator shaft to confirm light fixture locations, dimensions, etc. Enlarged plans with dimensions provided on AE420. Refer to structural and electrical drawings for additional information.

16 CS101-SITE PLAN-PARKING

TRANSFORMER AND PAD, PEDESTAL ELECTRICAL PANELS AND COMMUNICATIONS HANDHOLE :IT IS NOT NOTED ON THIS SHEET AND SHOWN ON SHEET CU101. Please confirm if this is included in the scope of work.

The transformers and pads, pedestal mounted panels, communication hand hole, and other site utility features indicated on Sheet CU101 are included in the project. Also refer to the Utility Service Notes on Sheet C-001 for additional information.

17 CS101-SITE PLAN-PARKING

KEY NOTE #17 CHARGING STATION AND POST. IS THERE PLAN DETAIL TO SHOW INSTALLATION

DIMENSIONS?

Refer to installation instructions for EV Charger indicated on Sheet ES101 (Leviton Evergreen 4000 with two ports) for installation dimensions.

18 CS101 SITE PLAN-PARKING

RELOCATED COTTAGE: PLEASE CONFIRM IF THERE IS ANY SCOPE OF WORK RELATED TO THIS RELOCATED COTTAGE, OR IF THIS IS NIC.( ALSO ON CL101-SITE LAYOUT PLAN) The cottage has been removed by FWS and is NOT in the scope of work.

19 CU101-SITE UTILITY PLAN-WEST

KEY NOTE #19 FUTURE ELECTRIC CAR CHARING STATIONS: PLEASE CONFIRM THE SCOPE OF WORK TO

PREPARE FOR FUTURE

Keynote 15 on CU101 indicates hand holes at (3) future EV charging locations. The scope of work includes the hand holes with underground conduit extended from the EV Charger.

SD101- PARTIAL FOUNDATION REMOVALS PLAN

NORTH

KEY NOTE #11 IS SHOWN ON THE PLAN AND NOT LISTED IN THE KEY NOTES. PLEASE CONFIRM THIS KEY NOTE. Consider as Keynote 4 and remove existing foundation wall and wall footing under entrance.

21 SB101- PARTIAL FOUNDATION PLAN NORTH 1 KEY NOTE #20- PLEASE CONFIRM THE DETAIL TO REFERENCE: THERE IS NOT A SHEET 6/SF5603. See detail 6 on sheet SF503

22 SB101- PARTIAL FOUNDATION PLAN NORTH 1

KEY NOTE #19 CONCRETE HOUSEKEEPING PAD- Please confirm the correct area for bidding purposes.

SB101 and P-101 show approximately 28 SF area, but M-401 shows approx 50 SF area. Use largest area as required by all disciplines.

AD103 -PARTIAL FIRST FLOOR REMOVALS PLAN

NORTH PLEASE CONFIRM KEY NOTE #7 LOCATION ON THE PLAN. Keynote #7 is not used and should be deleted.

AD104- PARTIAL FIRST FLOOR REMOVALS PLAN

SOUTH

KEY NOTE #18 IS NOT USED, IT IS CALLED OUT IN THE BATH 117 PLEASE CONFIRM THIS KEY NOTE SCOPE OF WORK Keynote #18 is not used and should be deleted.

25 AD201 -REMOVALS EXTERIOR ELEVATIONS 1 KEY NOTE #16- PLEASE CONFIRM DETAIL X/AEXXX. Refer to detail 3/AE621 and Window Schedule General Notes on sheet AE620.

AE701- PARTIAL BASEMENT REFLECTED CEILING

PLAN NORTH

ROOM 008- HAS KEY NOTE #1 THAT REFERENCES ACOUSTICAL CEILING TILE, BUT WRITTEN NOTE INDICATES EXPOSED STRUCTURE ABOVE. PLEASE CONFIRM CEILING TYPE IN THIS ROOM. Storage Room 008 will be open to structure above – keynote 1 should be removed from Storage Room 008.

27 AE001- REFERENCE PLANS

SECTION DETAIL CALL OUT 1/AE222- PLEASE CONFIRM SHEET AE222 AND DETAIL. THERE IS NOT A SHEET AE222 PROVIDED Section callout 4/AE220 should be deleted. Section callout 1/AE222 should read '1/AE420'.

28 AE002- WALL TYPES AND DETAILS 3/AE002- HAS A REFERENCES SHEET AE222- PLEASE PROVIDE THIS SHEET AE222 IS NOT IN THE SET. Sheet AE222 does not exist - reference AE222 should read 'AE220'.

29 AE002- WALL TYPES AND DETAILS

PARTITION TYPES GENERAL NOTES #1: PLEASE CONFIRM THE FIRE STOPPING DETAILS REFERENCED ON AE001, THERE ARE NO FIRE STOPPING DETAILS LOCATED ON SHEET AE001. Reference AE001 should read 'AE003'.

30 AE002- WALL TYPES AND DETAILS PLEASE CONFIRM IF WALL TYPE "1A" IS BEING USED AND LOCATION ON THE PLANS. Wall type 1A will be used at perimeter of Elevator Machine Room 005B. One sheet AE101, wall tag at Room 005B should read '1A'.

31 AE101 -PARTIAL BASEMENT PLAN NORTH PLEASE CONFIRM THE DETAIL CALL OUT 1/A222- THERE IS NOT A SHEET A222 PROVIDED. A222 should read ‘AE222’.

32 88_AE101 PARTIAL BASEMENT PLAN NORTH

PLEASE CONFIRM THE DETAIL SECTION SHOWN AT STAIR #5 AND UTILITY 003-1/A221-THERE IS NOT A SHEET A221 A221 should read ‘AE221’.

33 88_AE101 PARTIAL BASEMENT PLAN NORTH DETAIL CALL OUT NEXT TO STAIR #2 - PLEASE CONFIRM THE DETAIL TAG INFORMATION, IT IS MISSING Detail callout should be deleted.

34 88_AE101 PARTIAL BASEMENT PLAN NORTH

ELEVATOR MACH. ROOM 005B: THE DOOR 005B IS 60 MIN RATED. PLEASE CONFIRM THE PARTITIONS FOR THE ROOM ARE NOT RATED AS SHOWN. Partitions are rated as shown on sheet G-102. Refer to response #30 above.

35 89_AE102 PARTIAL BASEMENT PLAN SOUTH

TEAM ROOM 012- KEY NOTE #2 CONCRETE STOOP TO BE IN STALLED IN IN THE INTERIOR? THIS IS A COUNTER (2/AE740) PLEASE CONFIRM SCOPE OF WORK AT THIS AREA. Keynote #2 should be removed in Team Room 012.

36 89_AE102 PARTIAL BASEMENT PLAN SOUTH OPEN OFFICE 016- PLEASE CONFIRM THE PARTITION TYPE AT THE 1'-1" x 11". Provide wall type NE.

37 89_AE102 PARTIAL BASEMENT PLAN SOUTH KEY NOTE #10 PLEASE CONFIRM THE GYP. BOARD SIZE Provide 5/8" thick gypsum board.

38 90_AE103 PARTIAL FIRST FLOOR PLAN NORTH 1 PLEASE CONFIRM THE DETAIL CALL OUT 1/AE222- THERE IS NOT A SHEET A222 A222 should read ‘AE222’.

39 90_AE103 PARTIAL FIRST FLOOR PLAN NORTH 1

PLEASE CONFIRM THE DETAIL SECTION SHOWN AT THE LOBBY 101 -1/A221-THERE IS NOT A SHEET A221.

IS THIS AE221 A221 should read ‘AE221’.

40 90_AE103 PARTIAL FIRST FLOOR PLAN NORTH 1

DETAIL 10/AE501 IS THIS TYPICAL AT ALL THE WINDOWS IN VEST. 100 TO HAVE ALL SIDES FINISHED IN

WOOD OAK TRIM?

Provide painted, 5/8" gypsum board window returns, typical in Vest. 100. Provide white oak trim at northeast and northwest corners.

41 90_AE103 PARTIAL FIRST FLOOR PLAN NORTH 1

LOBBY 101: NO ELEVATIONS CALLED TOWARDS DOOR 100A AND DOOR 104. CAN ELEVATIONS BE PROVIDED TO CONFIRM FINISHES/TRANSITIONS/CROWN MOLDING REQUIREMENTS? See detail 7/AE741 for south elevation of Lobby 101 and detail 10/AE501 for trim/finish information.

42 90_AE103 PARTIAL FIRST FLOOR PLAN NORTH 1

STAIR #5 S05 WINDOW TYPE "A" DOUBLE HUNG WINDOW SAFETY GLAZING AT TRANSOM ABOVE THE WINDOW. SHOULD THIS BE RATED OR THE INSULATED GLASS . Provide insulated glass at transom.

43 AE103 -PARTIAL FIRST FLOOR PLAN NORTH 1

STAIR KEY NOTE #2-REFERENCES WOOD RAILING SYSTEM 4/AE420. PLEASE CONFIRM THE DETAIL THAT IS REFERENCED SHOULD BE DETAIL 5/AE420. Concur - keynote #2 should reference detail 5/AE420.

44 AE106 -PARTIAL FIRST FLOOR PLAN SOUTH

SECTION 1/AE222 AT ELEV 007 PLEASE CONFIRM THE SECTION AND SHEET LOCATION. THERE IS NOT A SHEET AE222. Sheet AE22 does not exist. Please refer to detail 4/AE220 for similar building section.

45 AE106- PARTIAL FIRST FLOOR PLAN SOUTH

S04- DOOR AT STORAGE 205. THIS DOOR IS NOT LISTED ON THE DOOR SCHEDULE PLEASE CONFIRM SCOPE OF WORK FOR THIS DOOR Door S04 to remain in place and receive paint.

103AE402 ENLARGED TOILET PLANS AND

ELEVATIONS

13/AE402 THE ELEVATION HAS "B" WHICH IS A TOILET TISSUE DISPENSER. PLEASE CONFIRM THIS IS THE ELECTRIC HAND DRYER "O" PER PLAN The 'B' designation in 13/AE402 should be an 'O' to reference an electric hand dryer.

104_AE420 STAIRS/ELEVATOR TOWER PLANS

AND SECTIONS

5/AE420 PLEASE CONFIRM PLAN THIS DETAIL IS REFERENCED FROM. ALSO THE NOTE IS CLIPPED OFF, PLEASE PROVIDE PNT (

Detail 5/AE420 is referenced from detail 2/AE420 and keynote 2 on sheet AE103 (refer to response #41 above). The clipped off note should read '…PNT (TYP)'.

48 105_AE421 STAIR DETAILS

3/AE421- PLEASE CONFIRM THIS IS THE CORRECT RETURN FOR THIS RAIL AND LANDING FOR ADA AS IT IS SHOWN. Note at bottom of handrail should be modified to read 'return to wall'.

49 AE601- DOOR SCHEDULE, TYPES AND DETAILS

DOOR S05- SHOULD THE GLAZING BE RATED SINCE THE DOOR IS RATED. WILL ALL TYPE "D" THAT ARE RATED HAVE RATED GLAZING? SEE NOTE #5 All rated doors will receive rated glazing.

50 AE601- DOOR SCHEDULE, TYPES AND DETAILS SHOULD THE DOORS IN THE LOBBY AND STAIR ALL BE RATED WITH RATED GLAZING? Refer to door schedule for rated door locations. Refer to response #49 above.

51 AE601- DOOR SCHEDULE, TYPES AND DETAILS PLEASE CONFIRM IF DOOR TYPE "F' IS USED. Doors S05A, 104, and 122 should be door type 'F'

52 AE601- DOOR SCHEDULE, TYPES AND DETAILS

PLEASE CLARIFY THE DIFFERENCE BETWEEN 'DOOR SCHEDULE GENERAL NOTES' AND 'DOOR SCHEDULE NOTES'? ARE THE NUMBERS CALLED OUT IN THE 'NOTES' COLUMN IN REFERENCE TO 'DOOR SCHEDULE NOTES'? Refer to attached updated drawing for clarification.

53 AE620- WIDOW TYPES

WINDOW SCHEDULE: THE WINDOW TYPE DETAILS (2/AE620) SHOW DIFFERENT DETAILS THAN ON THE WINDOW SCHEDULE. EXAMPLE: WINDOW A- HEAD DETAIL IS - 1E/A622 IS CALLED OUT ON THE ELEVATION TYPE AND 1A/AE622 (SIM) ON THE SCHEDULE? Refer to attached updated drawing for clarification.

AE703- PARTIAL FIRST FLOOR REFLECTED

CEILING PLAN NORTH 1 IN THE STAIR S05 AND LOBBY 117 DOES THIS CLG REQUIRE TO BE RATED Ceilings in Stair S05 and Lobby 117 will not be rated.

AE704- PARTIAL FIRST FLOOR REFLECTED

CEILING PLAN NORTH 2 KEY NOTE #3 REFERS TO SHEET AE540 PLEASE CONFIRM THE DETAIL TO REFERENCE ON THIS SHEET. Keynote #3 refers to gypsum board soffit over cabinets shown in details 2 and 3 on AE540.

56 128_AE740 INTERIOR ELEVATIONS 1

17/AE740 PLEASE CONFIRM THE TV IS FURNISHED BY OWNER AND INSTALLED BY G.C. WITH THE REQUIRED POWER AND BLOCKING LOCATION FOR INSTALLATION TV will be provided and installed by the contractor - please refer to spec section 274116.

P-102 -PARTIAL BASEMENT PLUMBING PLAN

SOUTH

(HB) HOSE BIB - PLEASE CONFIRM IF A NEW LOCATION IS TO BE INSTALLED. ONLY HB(E) IS SHOWN ON THE

PLAN, IS THE HOSE BIBB EXISTING TO REMAIN OR REPLACED WITH NEW?

Sheet P-102 has a total of four hose bibbs/non-freeze wall hydrants. Three of them are new NFWH at locations close to existing hose bibbs to be removed. The hose bibb in the lower left corner of the plan is located in the stone façade, so to minimize disturbance of this material is existing to remain with a new water connection as indicated.

58 C-508- SITE DETAILS 6

3-C-508-RAILING DETAIL: SHOULD THIS HAND RAIL RETURN LEVEL TO GRADE AT THE LAST STEP ? TYPICAL FOR ALL DETAILS No, handrails are correct as detailed.

M-106- SECOND FLOOR AND PARTIAL ATTIC

MECHANICAL PLAN PLEASE CONFIRM LOCATION OF KEY NOTE #3 ON THE PLAN. Keynote 3 is missing, and should be located on the flat roof section, to the plan right of Storage 205.

M-108- SECOND FLOOR ATTIC MECHANICAL

PLAN PLEASE CONFIRM LOCATION OF KEY NOTE #7 ON THE PLAN.

Keynote 7 is missing and should be located at the fire damper and access door for the exhaust air duct located above the landing of the existing interior staircase.

61 ES101 ELECTRICAL SITE PLAN

FUTURE COMFORT STATION N.I.C ON SHEET C0101 PLEASE CONFIRM ELECTRICAL SIZE SHOWN ON CU101 IS THE REQUIRED SIZE. IS THERE A CONCRETE SLAB TO BE INSTALLED? No concrete slab. Provide electric handhole (key note 17 on CU101) and 2" conduit (keynote 22 on CU101).

62 ES101 ELECTRICAL SITE PLAN

KEY NOTE #1 PLEASE CONFIRM WHO FURNISHES THE F&W FLEET ELECTRIC VEHICLE CHARGING STATION.

IS GC RESPONSIBLE FOR FURNISHING AND INSTALLING, OR JUST PROVIDED ELECTRICAL AS NEEDED TO

STATIONS?

Keynote 1 is duplex receptacles for EV charging. The contractor is responsible for providing charging station per Keynote 4, and infrastructure for charging at the three locations per keynote 5.

EP101- BASEMENT POWER PARTIAL PLAN

NORTH ELEVATOR: PLEASE CONFIRM WHAT "SP -1" REFERENCES FOR EQUIPMENT. SP-1 is the sump pump, which is no longer required.

EP103 -FIRST FLOOR POWER PARTIAL PLAN

NORTH 1 LOBBY 101 PLEASE CONFIRM TELEVISION LOCATION AND POWER AND DATA REQUIRED/MOUNTING

Three locations for television mounting shown with keynote 1. The height of the receptacle is to be coordinated with tv mounting.

Wireless access point on the ceiling for smart tv, if required.

65 EP601 -PANELBOARD SCHEDULES 1

PLEASE CONFIRM GARAGE FEED AND FUTURE COTTAGE FEED SIZES AND CONDUIT REQUIRE ON THE PLANS. There are no feeds to the garage and cottage. The breakers are to be provided for future use.

66 EP601- PANELBOARD SCHEDULES 1

PLEASE CONFIRM ELECTRICAL REQUIREMENTS ARE REQUIRED FOR BASE BID FOR FUTURE CHARGING

STATIONS. CONDUIT AND WITH PULL STRINGS, CONDUIT WITH FEEDERS, ETC?

Base bid: The duplex receptacles and wiring for MDP-2, MDP-4, MDP-6, MDP-8, AND MDP-10 (ES101 keynote 1). The electric charging station, wiring, conduit and connections connected to MDP-1,3 (ES-101 keynote 4). Infrastructure including conduit, pull string, handhole, breakers for future charging stations, MDP-5,7, MDP-9,11, AND MDP-13,15 (ES-101 KEYNOTE 5).

EL101-BASEMENT LIGHTING PARTIAL PLAN

NORTH

STAIR #5: LIGHT FIXTURE C1 IS NOTED WALL MOUNT/EGRESS LIGHT, BUT IT APPEARS TO BE SHOWN ON THE CLG. PLEASE CONFIRM LOCATIONS ALL LIGHTING IN THE ELEVATOR SHAFT ON ALL LEVELS . The intention is that the C1 fixtures be mounted on the ceiling surface in stair S05.

67 LS102 - BIKE RACK SHOULD EACH BIKE RACK HAVE A CUSTOM LOGO OR JUST THE RACKS ON EACH END OF THE SETS OF 5? Provide a total of two (2) custom logos. Locate one (1) at each end of the line of bike racks.