SECTION B – Supplies or Services and Prices/Costs (19 April 2022)
BID SCHEDULE
FLINT HILLS NATIONAL WILDLIFE REFUGE HARTFORD, KANSAS
QTY Unit Unit
Cost Total Price
1 Mobilization/Demobilization, Bonding, Overhead, & Profit
1 LS
2 Site preparation 1 LS 3 WCS and all work associated with project completion
1 LS
Total of All Division
Project Description: Construct WCS at Pin Tail Marsh at Flint Hills NWR.
Furnish all labor, materials, and equipment to complete the following work in accordance with the attached specifications.