Attachment_4_Updated_Statement_of_Work_7FEB22_0004.pdf

PDF 250 KB Posted

Attached to
CO-ROCKY MTN ARSNL NWR-BLDG PAINTING
Solicitation number
140F0122R0028
Issued by

View the file

Other files

File Type Posted
Attachment_5_Additional_Questions_and_Answers_0004.pdf PDF
Sol_140F0122R0028_Amd_0004.pdf PDF
Sol_140F0122R0028_Amd_0003.pdf PDF
Sol_140F0122R0028_Amd_0002.pdf PDF
Attachment_3_IMG_0072_0002.JPG JPG image
Attachment_3_IMG_0070_0002.JPG JPG image
Attachment_3_IMG_0073_0002.JPG JPG image
Attachment_3_IMG_0078_0002.JPG JPG image
Attachment_2_Questions_and_Answers_0002.pdf PDF
Attachment_3_IMG_0071_0002.JPG JPG image
Attachment_3_IMG_0074_0002.JPG JPG image
Sol_140F0122R0028_Amd_0001.pdf PDF
Sol_140F0122R0028.pdf PDF
Attachment_1_Wage_Determination.pdf PDF
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION C - DESCRIPTION/SPECIFICATION/STATEMENT OF WORK (7 February 2022)

Statement of Work for Exterior Painting of Prefabricated Metal Buildings at the Rocky Mountain Arsenal National Wildlife Refuge

1) Description: BLD 120 and BLD 124 at Rocky Mountain Arsenal National Wildlife Refuge require the exterior painted.

2) Scope of Work: The contractor is responsible for preparing and painting the exterior of two prefabricated metal buildings located in the maintenance area of the Rocky Mountain Arsenal National Wildlife Refuge (Commerce City, Colorado). Work includes

(1) cleaning and proper preparation of exterior of buildings; (2) repairing and application of rust-inhibiting primer; and (3) painting the exterior of the buildings to include garage overhead doors, all doors, door frames, window trims, and louvers, gutters, downspouts, replaced OH door, vertical beams, unit on top of building 120. Contractors should bid on painting the exterior of each of the two prefabricated metal buildings: (1) MAINTENANCE BUILDING which is approximately 8,225 square feet of paintable surfaces; and (2) FIRE BUILDING which is approximately 5,635 square feet of paintable surfaces.

3) Period of Performance: 90 days after Notice to Proceed.

4) Special Requirements: The following minimum standards apply:

Color Selection:

• Exterior color shall be DUNES SAND or appropriate alternative.

• Doors and trim color shall be CEDAR or appropriate alternative.

• USFWS will approve final color selection.

Paint Requirement:

• Paint will meet the minimum standards of being acrylic-latex paint designed specifically for exterior use on metal.

General conditions:

• Contractor shall provide information on warranty of all products.

• Contractor is responsible for safety of the worksite.

7) COR Suggestion: COR will be provided at time of award.

File details come from the government source that posted it. Updated .