About this file

This document is a Material Approval Submittal form (IA Form 3000 V2) used by contractors to submit material information, such as shop drawings, equipment data, manufacturer's literature, certificates, and samples, to the government for approval on a federal contract.

The form includes details such as the contract number, submission number, and project number. Contractors use this form to certify that the materials comply with the contract specifications. The government then reviews and approves or disapproves the materials. The instructions on the reverse side provide guidance to the contractor on how to properly complete and submit the form. This form is associated with the federal contract opportunity for the "PINE RIDGE LOG CABIN RENOVATION" project, which is being awarded by the Department of the Interior, Bureau of Indian Affairs, Bureau of Indian Education.

View the file

Other files for this federal contract opportunity

Other files attached to PINE RIDGE LOG CABIN RENOVATION, newest first.
File Type Posted
Sol_140A2324R0072.pdf PDF
SF-25_Performance_Bond_Form.pdf PDF
B08_Progress_Schedule.pdf PDF
Shannon_Cty_WD.pdf PDF
SF-25A_Payment_Bond_Form.pdf PDF
A06_PINE_RIDGE_BLDG_FLOOR_PLANS.pdf PDF
A04_Habitability_SOW_(FINAL_2024-05-13).docx DOCX document
B08_SF-24_Bid_Bond_Form.pdf PDF
B08_Questions_and_Answers_Log.xlsx XLSX spreadsheet
B08_BIA_FEDERAL_HEALTH_AND_SAFETY_CODES.pdf PDF
B08_Progress_Report.pdf PDF
B08_SF-1413_Statement_and_Acknowledgement_Form_(Subcontracting).pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IA FORM 3000 V2

PREVIOUS EDITION IS OBSOLETE.

Department of the Interior, Indian Revised on Aug 11, 2021

MATERIAL APPROVAL SUBMITTAL

(See Instructions on Reverse)

TO: (Project Engineer or Contracting Officer Representative) FROM: (Contractor) DATE

CONTRACT NUMBER SUBMISSION NUMBER SUBMITTAL

NEW RESUBMITTAL

PREVIOUS SUBMISSION NUMBER PROJECT NUMBER

TO BE COMPLETED BY CONTRACTOR FOR GOVERNMENT USE ONLY

ITEM

NO.

SPECIFICATION SECTION/

PARA NO./DRAWING NO.

DESCRIPTION OF MATERIAL

(Include Type, Model Number, Catalog Number, Mfg., etc)

AP-

PROVED

DISAP-

PROVED

SEE

REVERSE INITIAL

BY COMPLETING THIS FORM, THE UNDERSIGNED CONTRACTOR CERTIFIES THAT

THE MATERIAL COMPLIES WITH ALL SPECIFICATIONS OF SUBJECT CONTRACT.

DATE TYPE OR PRINT NAME AND TITLE SIGNATURE

FOR GOVERNMENT USE ONLY

TO: (Project Engineer or Contracting Officer Representative)

RECOMMEND APPROVAL DISAPPROVAL AS INDICATED ABOVE AND SUBJECT TO ANY APPLICABLE COMMENTS ON THE

REVERSE

DATE TYPE OR PRINT NAME AND TITLE SIGNATURE

COMMENTS

(Number to correspond with applicable Item Number on reverse)

INSTRUCTIONS TO CONTRACTORS

1.The term “material” is defined as articles, supplies, raw materials, equipment, parts, components, and end items that are to be incorporated into the work required by the contract.

2.This form is to be used by contractors for submitting Shop Drawings, Equipment Data, Manufacturer’s Literature and Certificates and samples of Materials to the Government for approval in accordance with the provisions of this contract. Unless otherwise specified, it is to be prepared in 4 copies, signed, and provided to the contracting officer with appropriate attachments.

3.Item(s) to be approved will be clearly tabbed or identified. Data pertaining to item(s) to be approved will be clearly identified or tabbed, particularly where documents are voluminous, in order to properly evaluate the materials or articles to be incorporated in the work. Each attachment will be numbered to correspond with the item number shown on the face of this form.

4.Request submitted shall be numbered consecutively, by contract, in the space entitled “Submission No.”. This number, in addition to the Contract No., will be used to identify each Material Approval Submittal. Resubmissions will be indicated in the appropriate block and the insertion of previous submission number and data in addition to a new submission number. A single submission should be used for all work of a section of the specifications, but in NO instance should the submission include work for more than one (1) contract. Submittals requiring priority handling will be submitted by separate submittal using the form and so marked across the face of the form.

5.This material Approval Submittal is not valid unless it is signed by the contracting officer. This approval is required as called for by the contracting officer under the terms of this contract.

IA FORM 3000 V2