B09_RFI_Paint_Attachment_3_TORFP_Questions_and_Answers_Log_0001.xlsx
XLSX spreadsheet 22 KB Posted
- Attached to
- PAINTING - NENAHNEZAD COMMUNITY SCHOOL
- Solicitation number
- 140A2324R0061
About this file
This document is a Questions and Answers Log related to Task Order Request for Proposal (TORFP) #140A2324R0061 for a painting project at the Nenahnezad Community School. The contractor, Zohnnie Construction Industries, Inc., submitted several questions regarding the scope of work, including clarification on the number of doors to be painted, whether the gym and maintenance building had already been painted, and if light fixtures and windows also needed painting. The government responses provided additional details and clarification on the expected work. There is no bid bond or performance/payment bond requirement for this project if the bid is under $35,000, but there are alternative bond options if the bid exceeds that amount but is below $150,000. The summary indicates this is a small painting project with a focus on preparation, priming, and touch-up work on select building components.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140A2324R0061_Amd_0001.pdf | ||
| Attachment_4_SF1413_Statement_and_Acknowledgement.pdf | ||
| Attachment_2_Wage_Determination.pdf | ||
| Attachment_1_SOW.pdf | ||
| Attachment_3_TORFP_Questions_and_Answers_Log.xlsx | XLSX spreadsheet | |
| Sol_140A2324R0061.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1 Questions and Answers Log for Task Order Request for Proposal # 140A2324R0061 Paint
| Number | Date Received | Contractor | Question | Date Sent to COR | Answer | Date Answered |
| 1 | 5/10/24 | Zohnnie Construction Industries, Inc | On the Jobwalk yesterday, I was shown 54 Doors to paint. On the SOW it states paint 42 doors. DO we paint what was pointed out to us yesterday or do we increase the door count to 52? | 5/10/24 | paint the doors on the SOW. The initial walk around included doors that needed painting . | 5/10/24 |
| 2 | 5/10/24 | Zohnnie Construction Industries, Inc | On the SOW, Introduction 1b the SOW calls for painting an dcleaning the Exterior of the School Gym/Cafeteria Blding 455 and 456. However, Mr Sabaque and Mr Smith said this was Already painted? | 5/10/24 | The gym was painted. The areas needing paint are expected to be prepped and primed properly. Again show up and call first before arriving and make and appointment with me so we can pinpoint these items from the horses mouth | 5/10/24 |
| 3 | 5/10/24 | Zohnnie Construction Industries, Inc | on site visit it appears that Building 456 the Shop/Maint. Office has been painted as well as the doors? Do you still want ZCI to paint the doors on this Building too? | 5/10/24 | NO doors painted at the maintenance. | 5/10/24 |
| 4 | 5/10/24 | Zohnnie Construction Industries, Inc | Do light fixtures get painted? It does not say on SOW on introductiona nd was not discussed at the stie visit but it appears on the contractors responsibility on page 4? | 5/10/24 | NO light fixtures painted. | 5/10/24 |
| 5 | 5/10/24 | Zohnnie Construction Industries, Inc | It appears some windows were painted maroon? But it does not appear on the SOW on introduction? However it appears on the Contractor responsibity on page 4. There are quite a few windows not painted at the school. Do you want all windows painted | 5/10/24 | Frames that are peeling around the downspout caulked primed and painted and the creacked areas brushed off primed and painted bldg. 401. | 5/10/24 |
| 6 | 5/10/24 | Zohnnie Construction Industries, Inc | At what buildling do we paint drain down spouts? | 5/10/24 | Per our conversation on the phone 5.13.24 bldg 401 wooden spouts | 5/10/24 |
| 7 | 5/10/24 | Zohnnie Construction Industries, Inc | On page 2 task lists Demolition? I was wondering where the demolition is required for this SOW? | 5/10/24 | No demolition, but haul off of debris and prep and paint surfaces. | 5/10/24 |
| 8 | 5/10/24 | Zohnnie Construction Industries, Inc | Just to clarify again, there is no bid bond or performance / payment bond o this bid correct? | 5/10/24 | There is no bid, performance, or payment bond on this bid if it is under $35k. However, if the bid exceeds this amount and is below $150k then two of the following is required: a payment bond; irrevocable letter of credi (ILC); tripartite escrow agreement; certificates of deposit; or a deposit of types of security. Please see FAR 28.102-1 for more information. | 5/10/24 |
| 9 | 5/10/24 | Zohnnie Construction Industries, Inc | SO can you please clarify if we paint the gym again or not? Or is it just the doors? | 5/10/24 | Per our conversation on the phone 5.13.24 touch ups as needed in the front inner foyer and maroon colored to cover green areas in the foyer of the gym. | 5.13.24 |
| 10 |