B08_Scope_of_Work-Walkin_Cooler_Repair.pdf

PDF 144 KB Posted

Attached to
Walk-in Cooler Repair, Jemez Day School
Solicitation number
140A2324Q0212
Issued by

About this file

This document is a Statement of Work (SOW) for the repair of a walk-in cooler at the Jemez Day School in Jemez Pueblo, New Mexico. The contractor shall remove and dispose of the existing non-working condensing unit and indoor coil, install a new condensing unit on the roof, install a new indoor coil, connect the refrigeration lines and condensate drain, and start up and check the operation of the walk-in cooler. The contractor shall provide all parts, materials, equipment, and labor to complete the repair. The work shall be completed within 30 calendar days from the Notice to Proceed, with the exception of potential interruptions due to tribal traditional activities. The contractor shall adhere to all applicable safety regulations, provide a background investigation for personnel, and coordinate access with the BIE Facility Management personnel. The contractor shall provide a written warranty on the materials and workmanship.

The related federal contract opportunity is for the Walk-in Cooler Repair at the Jemez Day School, solicitation number 140A2324Q0212, issued by the Department of the Interior, Bureau of Indian Affairs, Bureau of Indian Education.

View the file

Other files

File Type Posted
Sol_140A2324Q0212.pdf PDF
B08_Wage_Determination_2015-5443.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Jemez Day School

Walk-In Cooler Repair

1. SCOPE OF WORK:

The contractor shall repair walk-in cooler in School Kitchen at Jemez Day School. Contractor will provide all parts, materials, equipment, and labor to make repair. Contractor will remove non-working parts and materials and dispose of them. After repair and installation of new parts and materials, contractor will run test to make sure walk-in cooler is back in operating condition.

2. PROJECT LOCATION:

Jemez Day School 243 Day School Road Jemez Pueblo, New Mexico 87024 Phone: (505) 834-7304

3. PURPOSE:

The purpose of the project is to repair Walk-In Cooler so the Kitchen staff can store food at the correct temperature and prepare nutritional food for students.

4. SPECIFIC REQUIREMENTS:

A. SCHOOL SITE VISIT:

Not required.

B. SERVICES:

The contractor shall perform the following:

• Remove and dispose of existing non-working condensing unit and indoor coil in Walk-In Cooler, Make – Bally; Model No. 3478-1; Serial No. J3103-2.

• Walk-in cooler is a 10 x 20 which takes up the area in the kitchen from the kitchen floor to the roof of the building.

• Install new condensing unit on the roof.

• Install new indoor (evaporative) coil and connect with power supply from existing electrical location.

• Connect existing refrigeration lines to new equipment.

• Connect existing condensate drain line to the new equipment.

• Start up and check operation.

C. GENERAL REQUIREMENTS:

a. QUOTE/PROPOSAL:

Quotes/Proposal shall be itemized by material, supplies, equipment, labor costs, and NM State Taxes.

b. WORK HOURS:

Work hours for this project shall be schedule with school maintenance worker. With safety in mind, contractor prefer to spray before or after school with minimal staff in the building.

c. SAFETY:

The contractor shall adhere to all BIA/BIE adopted codes and the contractor shall abide by all OSHA regulations while on school grounds, and shall review all applicable safety regulations before beginning the project. The contractor shall provide signs, barriers, and or caution tape as a safety precaution around the work site. The contractor shall have a fall protection plan if workers are to be performing duties above six (6) feet from the ground or finished floor. The contractor shall bear sole responsibility of taking all appropriate actions necessary to prevent accidents, injuries to individuals and damage to property in and around the work area.

d. BACKGROUND INVESTIGATION:

The awarded contractor shall provide a designated individual(s) from their company who will be subject to a BIA Security Background Investigations in accordance with Section 231 of the Crime Control Act of 1990, Public Law 101-647. Background Investigation forms will be provided at the pre-construction meeting.

e. ACCESS:

BIE Facility Management personnel shall provide access to Jemez Day School at all times. The contractor shall minimize disruption of classroom instructions and normal school activities expected in such areas.

f. DAMAGES:

Where existing surfaces are damaged the contractor shall repair and finish with matching existing structure. The contractor shall be responsible for replacement of any items (interior or exterior) damaged during the performance of this project.

g. CLEANING:

The Contractor shall keep the work area reasonably clean at all times. Contractor shall accomplish a complete cleanup at the end of the project. The Contractor shall properly dispose of all debris at an approved dumping site.

h. PERFORMANCE:

Performance time for this project is 30 Calendar Days from Notice to Proceed.

(Exception: Work days maybe interrupted with closures of the Pueblo due to Tribal Traditional Activities). All work shall be completed in a professional manner and without delay once the on-site work is started.

i. SALVAGE:

All salvageable materials and equipment shall be the property of the contractor unless otherwise noted in the Statement of Work and/or drawings. The Contractor is responsible for the removal of all salvageable materials and equipment from the installation.

5. PRODUCTS:

A. WARRANTY:

The Contractor shall provide a written warranty on the material and workmanship from date of acceptance by the Government.

B. MATERIALS:

The Contractor shall provide a written statement noting all material being utilized are asbestos free.

End of Statement of Work