About this file
Bid Schedule
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 140A1119Q0043_Without_SF-1449.pdf | ||
| Sol_140A1119Q0043_Amd_0003.pdf | ||
| Sol_140A1119Q0043_Amd_0002.pdf | ||
| Sol_140A1119Q0043_Amd_0001.pdf | ||
| 140A1119Q0043_Without_SF-1449.pdf | ||
| Sol_140A1119Q0043.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS
PROPOSAL SCHEDULE
BASE YEAR
Main Building Generator
Annual/Quarterly Preventative Maintenance
San Carlos Irrigation Project, Coolidge, AZ
7/1/2019 through 6/30/2020
ITEM
ITEM DESCRIPTION QUANTITY
lJNIT OF lJNIT
TOTAL PRICE
NO. MEASURE PRICE
BASE PRICE
Annual Inspection and
EA
Maintenance/Service Package
Quarterly Inspection and
3 EA
Maintenance/Service Package
Annual Load Bank Test (level I, two
3 hour)(to be completed as part of EA inspection)
Additional Services, Routine: Hourly
Rate for Technician with Service Truck.
4 HR
Subject to 4 hour minimum including travel time. Allowance item.
Additional Services, Emergency
(Weekdays): Hourly Rate for Technician
5 with Service Truck. Subject to 4 hour 4 HR minimum including travel time.
Allowance item.
Additional Services, Emergency
(Weekend/Holidays): Hourly Rate for
6 Technician with Service Truck. Subject 4 HR to 4 hour minimum including travel time.
Allowance item.
Allowance for extra Parts/Materials per
Year (not part of CLINS 1-3 above).
7 Allowance Item. To be billed at actual LS cost plus 15% contractor markup plus applicable sales tax.
TOTAL PRICE (Items 1 through 7)
OPTION YEAR ONE
Main Building Generator
Annual/Quarterly Preventative Maintenance
San Carlos Irrigation Project, Coolidge, AZ
7/1/2020 through 6/30/2021
ITEM
ITEM DESCRIPTION QUANTITY
UNIT OF UNIT
TOTAL PRICE
NO. MEASURE PRICE
BASE PRICE
Annual Inspection and
EA
Maintenance/Service Package
Quarterly Inspection and
3 EA
Maintenance/Service Package
Annual Load Bank Test (level I, two
3 hour)(to be completed as part of EA inspection)
Additional Services, Routine: Hourly
Rate for Technician with Service Truck.
4 HR
Subject to 4 hour minimum including travel time. Allowance item.
Additional Services, Emergency
(Weekdays): Hourly Rate for Technician
5 with Service Truck. Subject to 4 hour 4 HR minimum including travel time.
Allowance item.
Additional Services, Emergency
(Weekend/Holidays): Hourly Rate for
6 Technician with Service Truck. Subject 4 HR to 4 hour minimum including travel time.
Allowance item.
Allowance for extra Parts/Materials per
Year (not part of CLINS 1-3 above).
7 Allowance Item. To be billed at actual LS cost plus 15% contractor markup plus
OPTION YEAR TWO
Main Building Generator
Annual/Quarterly Preventative Maintenance
San Carlos Irrigation Project, Coolidge, AZ
7/1/2021 through 6/30/2022
ITEM
ITEM DESCRIPTION QUANTITY
UNIT OF UNIT
TOTAL PRICE
NO. MEASURE PRICE
BASE PRICE
Annual Inspection and
EA
Maintenance/Service Package
Quarterly Inspection and
3 EA
Maintenance/Service Package
Annual Load Bank Test (level 1, two
3 hour)(to be completed as part of EA inspection)
Additional Services, Routine: Hourly
Rate for Technician with Service Truck.
4 HR
Subject to 4 hour minimum including travel time. Allowance item.
Additional Services, Emergency
(Weekdays): Hourly Rate for Technician
5 with Service Truck. Subject to 4 hour 4 HR minimum including travel time.
Allowance item.
Additional Services, Emergency
(Weekend/Holidays): Hourly Rate for
6 Technician with Service Truck. Subject 4 HR to 4 hour minimum including travel time.
Allowance item.
Allowance for extra Parts/Materials per
Year (not part of CUNS 1-3 above).
7 Allowance Item. To be billed at actual LS cost plus 15% contractor markup plus
PROPOSAL SCHEDULF:
OPTLON YEAR THREE
Main Building Generator
Annual/Quarterly Preventative Maintenance
San Carlos Irrigation Project, Coolidge, AZ
7/1/2022 through 6/30/2023
ITEM
ITEM DESCRIPTION QUANTITY
UNIT OF lJNIT
TOTAL PRICE
NO. MEASlJRE PRICE
BASE PRICE
Annual Inspection and
EA
Maintenance/Service Package
Quarterly Inspection and
3 EA
Maintenance/Service Package
Annual Load Bank Test (level 1, two
3 hour)(to be completed as part of EA inspection)
Additional Services, Routine: Hourly
Rate for Technician with Service Truck.
4 HR
Subject to 4 hour minimum including travel time. Allowance item.
Additional Services, Emergency
(Weekdays): Hourly Rate for Technician
5 with Service Truck. Subject to 4 hour 4 HR minimum including travel time.
Allowance item.
Additional Services, Emergency
(Weekend/Holidays): Hourly Rate for
6 Technician with Service Truck. Subject 4 HR to 4 hour minimum including travel time.
Allowance item.
Allowance for extra Parts/Materials per
Year (not part of CUNS 1-3 above).
7 Allowance Item. To be billed at actual LS cost plus 15% contractor markup plus
PROPOSAL SCHEDllLE
OPTION YEAR FOUR
Main Building Generator
Annual/Quarterly Preventative Maintenance
San Carlos Irrigation Project, Coolidge, AZ
7/1/2023 through 6/30/2024
ITEM
ITEM DESCRIPTION QUANTITY
UNIT OF UNIT
TOTAL PRICE
NO. MEASURE PRICE
BASE PRICE
Annual Inspection and
EA
Maintenance/Service Package
Quarterly Inspection and
3 EA
Maintenance/Service Package
Annual Load Bank Test (level I, two
3 hour)(to be completed as part of EA inspection)
Additional Services, Routine: Hourly
Rate for Technician with Service Truck.
4 HR
Subject to 4 hour minimum including travel time. Allowance item.
Additional Services, Emergency
(Weekdays): Hourly Rate for Technician
5 with Service Truck. Subject to 4 hour 4 HR minimum including travel time.
Allowance item.
Additional Services, Emergency
(Weekend/Holidays): Hourly Rate for
6 Technician with Service Truck. Subject 4 HR to 4 hour minimum including travel time.
Allowance item.
Allowance for extra Parts/Materials per
Year (not part of CLINS 1-3 above).
7 Allowance Item. To be billed at actual LS cost plus 15% contractor markup plus