This is a Project Manual for the Galesburg-Augusta Primary School Telescoping Stands project, prepared by Tower Pinkster Titus Associates for Galesburg-Augusta Community Schools in Galesburg, Michigan. The project involves the installation of electrically operated wall-attached telescoping bleacher stands with nine rows, 78 feet in length, and a capacity of 392 seats. The system includes molded plastic benches in red, plywood decking with polyethylene textured overlay, steel risers and safety rails, wheelchair-accessible seating with retractable truncated benches, and electrical components including a 1/2 horsepower motor operating at 208 V ac, three-phase, 60 hertz. The bleacher system is specified to comply with ICC 300 standards and ADA accessibility requirements, with control devices including walk-along pendant controls and wall-mounted keyed switch panels. The specifications also encompass electrical rough-in work, including common work results for electrical installation, low-voltage conductors and cables rated 600 V and less, hangers and supports for electrical systems, raceways and boxes, and identification systems for all electrical installations.

The project manual provides detailed technical specifications for products and installation requirements without indicating specific pricing terms, bid response dates, or contract award information. The electrical work requires compliance with NFPA 70, AWS welding standards, and NECA standards for workmanship. Contractors must obtain all required electrical construction permits and inspections and file electrical service requests with the utility provider. The specifications require factory-authorized service representatives to train the owner's maintenance personnel on system inspection, adjustment, operation, and maintenance. No information regarding funding sources, set-asides, contract term, or renewal options is contained in the project manual.

View the file

Other files

File Type Posted
BleacherReplacementBid.pdf PDF
14-182.15 GALESBURG AUGUSTA BLEACHER DRAWINGS.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tower Pinkster Titus Associates, Inc.

242 East Kalamazoo Avenue, Suite 200, Kalamazoo, MI 49007-5828

4 East Fulton Street, Suite 200, Grand Rapids, MI 49503

Galesburg-Augusta Primary School Telescoping Stands

PROJECT MANUAL

August 21 2019

OWNER

GALESBURG-AUGUSTA COMMUNITY SCHOOLS

1076 North 37th Street Galesburg, Michigan 49053

PROJECT NUMBER

14-182.15

SET NUMBER

PROJECT NO. 14-182.15 TABLE OF CONTENTS

GALESBURG-AUGUSTA PRIMARY SCHOOL TELESCOPING STANDS 1

GALESBURG-AUGUSTA COMMUNITY SCHOOLS 08/21/2019

© 2019 Tower Pinkster Titus Associates - All Rights Reserved

TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS (Not Applicable)

DIVISION 01 - GENERAL REQUIREMENTS (Not Applicable)

DIVISION 02 - EXISTING CONDITIONS (Not Applicable)

DIVISION 03 - CONCRETE (Not Applicable)

DIVISION 04 - MASONRY (Not Applicable)

DIVISION 05 - METALS (Not Applicable)

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES (Not Applicable)

DIVISION 07 - THERMAL AND MOISTURE PROTECTION (Not Applicable)

DIVISION 08 - OPENINGS (Not Applicable)

DIVISION 09 - FINISHES (Not Applicable)

DIVISION 10 - SPECIALTIES (Not Applicable)

DIVISION 11 - EQUIPMENT (Not Applicable)

DIVISION 12 - FURNISHINGS

12 6600 Telescoping Stands

DIVISION 13 - SPECIAL CONSTRUCTION (Not Applicable)

DIVISION 14 - CONVEYING EQUIPMENT (Not Applicable)

DIVISION 21 - FIRE SUPPRESSION (Not Applicable)

DIVISION 22 - PLUMBING (Not Applicable)

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC) (Not Applicable)

DIVISION 26 - ELECTRICAL

26 0500 Common Work Results for Electrical 26 0519 Low-Voltage Electrical Power Conductors and Cables 26 0529 Hangers and Supports for Electrical Systems 26 0533 Raceways and Boxes for Electrical Systems 26 0553 Identification for Electrical Systems

DIVISION 27 - COMMUNICATIONS (Not Applicable)

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY (Not Applicable)

PROJECT NO. 14-182.15 TABLE OF CONTENTS

GALESBURG-AUGUSTA PRIMARY SCHOOL TELESCOPING STANDS 2

GALESBURG-AUGUSTA COMMUNITY SCHOOLS 08/21/2019

© 2019 Tower Pinkster Titus Associates - All Rights Reserved

DIVISION 31 - EARTHWORK (Not Applicable)

DIVISION 32 - EXTERIOR IMPROVEMENTS (Not Applicable)

DIVISION 33 - UTILITIES (Not Applicable)

END OF TABLE OF CONTENTS

PROJECT NO. 14-182.15 TELESCOPING STANDS

GALESBURG-AUGUSTA PRIMARY SCHOOL TELESCOPING STANDS 12 6600 - 1

GALESBURG-AUGUSTA COMMUNITY SCHOOLS 08/21/2019

© 2019 Tower Pinkster Titus Associates - All Rights Reserved

SECTION 12 6600 - TELESCOPING STANDS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Electrically operated telescoping stands.

1.2 PREINSTALLATION MEETINGS

A. Preinstallation Conference: Conduct conference at Project site.

1.3 ACTION SUBMITTALS

A. Product Data: For each type of product.

B. Shop Drawings: For telescoping stands in both stacked and extended positions.

1. Include plans, elevations, sections, and attachment details.

2. Include diagrams for power, signal, and control wiring.

C. Samples for Initial Selection: For each type of exposed product and for each color and texture required.

1. Include Samples of accessories involving color and finish selection.

D. Samples for Verification: For the following products prepared on Samples of size indicated below:

1. Decking: 6-inch- (150-mm-) square Samples of finished material.

2. Metal Components: 6-inch- (150-mm-) square Sample of each color and finish indicated.

3. Seating Material: 6-inch- (150-mm-) square Sample of each seating material, color, and finish indicated.

1.4 INFORMATIONAL SUBMITTALS

A. Qualification Data: For Installer.

B. Welding certificates.

C. Product certificates.

1.5 CLOSEOUT SUBMITTALS

A. Operation and maintenance data.

GALESBURG-AUGUSTA PRIMARY SCHOOL TELESCOPING STANDS 12 6600 - 2

GALESBURG-AUGUSTA COMMUNITY SCHOOLS 08/21/2019

© 2019 Tower Pinkster Titus Associates - All Rights Reserved

1.6 QUALITY ASSURANCE

A. Installer Qualifications: An entity that employs installers and supervisors who are trained and approved by manufacturer.

B. Welding Qualifications: Qualify procedures and personnel according to the following:

1. AWS D1.1/D1.1M, "Structural Welding Code - Steel."

2. AWS D1.3/D1.3M, "Structural Welding Code - Sheet Steel."

1.7 FIELD CONDITIONS

A. Finished Spaces: Do not deliver or install telescoping stands until finishes in spaces to receive them are complete, including suspended ceilings, floors, and painting.

B. Field Measurements: Indicate measurements on Shop Drawings.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Structural Performance: Telescoping stands shall withstand the effects of gravity loads, operational loads, and other loads and stresses according to ICC 300 and the following:

1. Vertical live load of 100 PSF, but not less than 120 PLF on both seat boards and footboards.

2. Horizontal sway force of 24 PLF parallel to the seating and 10 PLF perpendicular to the seating.

B. Accessibility Standard: Comply with applicable provisions in the DOJ's 2010 ADA Standards for Accessible Design and ICC A117.1.

2.2 TELESCOPING STANDS

A. System Description: Operable system of multiple-tiered seating on interconnected folding platforms that close for storage, without being dismantled, into a nested stack. Telescoping-stand units permit opening and closing of adjacent, individual and multiple rows, and close with vertical faces of platforms in the same vertical plane.

1. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

2. Telescoping-Stands Standard: ICC 300.

B. Wall-Attached Telescoping Stands: Forward-folding system, in which the bleachers open in the forward direction by moving the front row away from the stack to the fully extended position and the rear of bleacher understructure permanently attaches to wall construction.

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. Hussey Seating Company.

http://www.specagent.com/Lookup?ulid=5447 http://www.specagent.com/Lookup?uid=123456977275

GALESBURG-AUGUSTA PRIMARY SCHOOL TELESCOPING STANDS 12 6600 - 3

GALESBURG-AUGUSTA COMMUNITY SCHOOLS 08/21/2019

© 2019 Tower Pinkster Titus Associates - All Rights Reserved

b. Interkal LLC.

c. Irwin Telescopic Seating Company; Irwin Seating Company.

2. Number of Rows: 9.

3. Length: 78 feet (23.8 m).

4. Capacity: 392 seats.

5. Row Spacing: 22 inches (560 mm).

6. Row Rise: 10-1/4 inches (260 mm).

7. Seat Type: Benches.

8. Operation: Electrically operated, with friction-type, integral power unit.

9. Electrical Characteristics for Each Seating Section:

a. Horsepower: 1/2.

b. Voltage: 208 V ac, three phase, 60 hertz.

10. Electrical Controls:

a. Control Devices: Walk-along pendant control system and Wall control keyed switch panel.

b. Limit Switches: Automatically stop power system when telescoping stands reach fully opened or closed positions.

c. Transformer: As required to coordinate current characteristics of motor and control station with building electrical system.

2.3 COMPONENTS

A. Benches: Seats and skirts.

1. Material: Molded plastic with contour surfaces.

a. Color: Red.

2. Bench Height: Not less than 16 inches (406 mm) or more than 18 inches (457 mm).

3. Bench Depth: 10 inches (254 mm).

B. Wheelchair-Accessible Seating: Locate retractable truncated benches to provide wheelchair-accessible seating at locations indicated on Drawings.

1. Equip tiers adjacent to wheelchair-accessible seating with front rails as required by ICC 300.

2. Equip cutouts with full-width front closure panels that match decking construction and finish and that extend from underside of tiers adjacent to cutouts to 1-1/2 inches (38 mm) from finished floor.

C. Deck: Plywood, 5/8 inch (16 mm) thick.

1. Finish: Polyethylene textured overlay bonded to substrate with exterior glue.

a. Color: As selected by Architect from manufacturer's standard colors.

D. Risers: Steel sheet with manufacturer's standard, rust-inhibiting coating or hot-dip galvanized finish.

E. Safety Rails: Steel, finished with manufacturer's standard powder coat system.

http://www.specagent.com/Lookup?uid=123456977276 http://www.specagent.com/Lookup?uid=123456977277 http://www.specagent.com/Lookup?uid=123456977295

GALESBURG-AUGUSTA PRIMARY SCHOOL TELESCOPING STANDS 12 6600 - 4

GALESBURG-AUGUSTA COMMUNITY SCHOOLS 08/21/2019

© 2019 Tower Pinkster Titus Associates - All Rights Reserved

1. Folding, "P"-shaped, mid-aisle handrails located at centerline of each aisle with seating on both sides.

2. End rails (guards) that are telescoping and self-storing.

3. Permenant rails around accessible seating cutouts and truncations.

4. Color: Black.

F. Understructure: Structural steel.

1. Finish: Manufacturer's standard rust-inhibiting finish.

2. Color: Manufacturer's standard.

G. Support Column Wheels: Nonmarring, soft, rubber-face wheel assembly under each support column.

1. Include wheels of size, number, and design required to support stands and operate smoothly without damaging the flooring surface, but no fewer than four per column or less than 3-1/2 inches (89 mm) in diameter and 1-1/2 inch (32 mm) wide.

H. Control Devices:

1. Walk-Along Pendant: Manufacturer's standard unit, which plugs into first row of each operating section. Wall mount key operation switch also provided in conjunction with pendant.

I. Fasteners: Vibration proof, in manufacturer's standard size and material.

2.4 ACCESSORIES

A. Steps:

1. Slip-resistant, abrasive tread surfaces at aisles.

2. Intermediate aisle steps, fully enclosed, at each aisle.

3. Removable front steps, fully enclosed, at each aisle, that engage with front row to prevent accidental separation or movement and are equipped with a minimum of four skid-resistant feet.

B. Closure Panels and Void Fillers:

1. Aisle closures at foot level that produce flush vertical face at aisles when system is stored.

2. End panels covering exposed ends of stands in the stored position.

3. Vinyl End Curtains: Manufacturers’ standard vinyl end curtains to close off under the bleacher units in the extended position. Curtain color as selected from manufacturer’s standard range.

4. Panels at cutouts and truncations for accessible seating.

5. Rear fillers including supports for closing openings between top row and rear wall of adjoining construction.

C. Signage:

1. Row letters at each row end.

2. Accessibility signs at each accessible space.

3. Custom graphics as indicated on Drawings on whole seating array.

GALESBURG-AUGUSTA PRIMARY SCHOOL TELESCOPING STANDS 12 6600 - 5

GALESBURG-AUGUSTA COMMUNITY SCHOOLS 08/21/2019

© 2019 Tower Pinkster Titus Associates - All Rights Reserved

2.5 MATERIALS

A. Lumber: Kiln dried, surfaced four sides; southern pine complying with SPIB's "Standard Grading Rules for Southern Pine Lumber" for C & Btr finish (C and better) grade-of-finish requirements.

B. Plywood: PS 1 as standard with manufacturer.

C. Molded Plastic: High-density polyethylene; blow or injection molded, color-pigmented, textured, impact-resistant, with integral reinforcing ribs for attachment and anchoring points. Provide with UV inhibitors to retard fading.

2.6 FABRICATION

A. Fabricate telescoping stands to operate easily without special tools or separate fasteners unless otherwise indicated.

B. Round corners and edges of components and exposed fasteners to reduce snagging and pinching hazards.

C. Form exposed work with flat, flush surfaces, level and true in line.

D. Supports: Fabricate supports to withstand, without damage to components, the forces imposed by use of stands without failure or other conditions that might impair their usefulness.

1. Cantilever bench seat supports to produce toe space uninterrupted by vertical bracing.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Examination: Examine substrates, areas, and conditions, with Installer present, for compliance with requirements for installation tolerances and other conditions affecting performance of the Work.

1. Proceed with installation only after unsatisfactory conditions have been corrected.

B. Install telescoping stands according to ICC 300 and manufacturer's written instructions.

3.2 ADJUSTING

A. Adjust backrests so that they are at proper angles and aligned with each other in uniform rows.

B. Adjust hardware and moving parts to function smoothly, and lubricate, test, and adjust each telescoping stand unit to operate according to manufacturer's written instructions.

GALESBURG-AUGUSTA PRIMARY SCHOOL TELESCOPING STANDS 12 6600 - 6

GALESBURG-AUGUSTA COMMUNITY SCHOOLS 08/21/2019

© 2019 Tower Pinkster Titus Associates - All Rights Reserved

3.3 DEMONSTRATION

A. Engage a factory-authorized service representative to train Owner's maintenance personnel to inspect, adjust, operate, and maintain telescoping stands.

END OF SECTION 12 6600

PROJECT NO. 14-182.15 COMMON WORK RESULTS FOR ELECTRICAL

GALESBURG-AUGUSTA PRIMARY SCHOOL TELESCOPING STANDS 26 0500 - 1

GALESBURG-AUGUSTA COMMUNITY SCHOOLS 08/21/2019

© 2019 Tower Pinkster Titus Associates - All Rights Reserved

SECTION 26 0500 - COMMON WORK RESULTS FOR ELECTRICAL

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Electrical Scope of work

2. Electrical equipment coordination and installation.

3. Rough-in

4. Electrical Demolition

5. Common electrical installation requirements.

1.2 SCOPE OF WORK

A. The scope of work is to include but not be limited to the following:

1. Obtain all required electrical construction permits and inspections.

2. File electrical service request with the Electric Utility for a new (upgraded, primary, secondary) electrical service.

3. Provide complete electrical installation including all components, i.e. light fixtures, lamps, receptacles, conduit, wire, etc.

4. Provide selective demolition of electrical systems and equipment as indicated on the drawings.

5. Submit documentation such as shop drawings, record documents, maintenance manuals, infrared scan results, systems test results, fire alarm system certification, etc. as specified.

1.3 COORDINATION

A. Coordinate arrangement, mounting, and support of electrical equipment:

1. To allow maximum possible headroom unless specific mounting heights that reduce headroom are indicated.

2. To provide for ease of disconnecting the equipment with minimum interference to other installations.

3. To allow right of way for piping and conduit installed at required slope.

4. So connecting raceways, cables, wireways, cable trays, and busways will be clear of obstructions and of the working and access space of other equipment.

B. Coordinate electrical systems, equipment and materials installation with other building components.

C. Coordinate installation of electrical panelboard tubs, backboxes and concealed conduit and tubing with masonry/concrete work.

D. Coordinate connection of electrical systems with exterior underground and overhead utilities and services.

Comply with requirements of governing regulations, franchised service companies and controlling agencies. Provide required connection for each service.

GALESBURG-AUGUSTA PRIMARY SCHOOL TELESCOPING STANDS 26 0500 - 2

GALESBURG-AUGUSTA COMMUNITY SCHOOLS 08/21/2019

© 2019 Tower Pinkster Titus Associates - All Rights Reserved

E. Coordinate installation of required supporting devices and set sleeves in cast-in-place concrete, masonry walls, and other structural components as they are constructed.

F. Coordinate location of access panels and doors for electrical items that are behind finished surfaces or otherwise concealed. Access doors and panels are specified in Division 08 Section "Access Doors and Frames."

G. Coordinate sleeve selection and application with selection and application of firestopping specified in Division 07 Section "Penetration Firestopping."

1.4 INTERPRETATIONS

A. It is the intent of these Drawings and Specifications to result in a complete electrical installation in complete accordance with applicable code and ordinances.

B. Drawings are diagrammatic in character and do not necessarily indicate every required junction box, pull box, ell, etc. Items not specifically mentioned in the specification or noted on the Drawings, but which are necessary to make a complete working installation, shall be included.

C. Drawings and Specifications are complementary. Whatever is called for in either is binding as though called for in both. The more stringent requirement shall govern.

PART 2 - PRODUCTS

PART 3 - EXECUTION

3.1 ELECTRICAL DEMOLITION

A. Disconnect, demolish, and remove electrical system equipment and components indicated to be removed.

B. Accessible Work: Remove exposed electrical equipment and installations, indicated to be demolished, in their entirety.

C. Inaccessible Work: Cut and remove buried raceway and wiring, indicated to be demolished, 2 inches below the surface of adjacent construction. Cap raceways and patch surface to match existing finish.

D. All existing fixtures, equipment, etc., that are removed and not indicated to be relocated, or reused, shall first be offered to the Owner, after Owner has approved, the remaining removed items shall become property of the Contractor and shall be removed from the building site.

E. Remove, store, clean, reinstall, reconnect, and make operational components indicated for relocation.

F. Protect existing electrical equipment and installations not indicated to be removed. If damaged or disturbed in the course of the Work, remove damaged portions and install new products of equal capacity, quality, and functionality.

G. Contractor shall examine the Drawings and Specifications, and existing conditions. All costs relating to maintaining existing services or relocating existing circuits and/or equipment shall be included in the bid.

GALESBURG-AUGUSTA PRIMARY SCHOOL TELESCOPING STANDS 26 0500 - 3

GALESBURG-AUGUSTA COMMUNITY SCHOOLS 08/21/2019

© 2019 Tower Pinkster Titus Associates - All Rights Reserved

Contractor is required to complete all work necessary to meet these requirements without additional expense to the Owner or his Representative.

H. Equipment Replacement: Contractor shall verify all circuit breakers and fuse sizes against the existing wire size prior to replacing switchboards, panelboards and disconnect switches. Notify the Architect of any discrepancies prior replacing equipment.

3.2 ROUGH-IN

A. Verify final locations for rough-ins with field measurements and with the requirements of the actual equipment to be connected.

B. Refer to equipment specifications in Divisions 02 through 49 for rough-in requirements.

3.3 COMMON REQUIREMENTS FOR ELECTRICAL INSTALLATION

A. Comply with NECA 1, Standard Practices for Good Workmanship in Electrical Construction.

B. Arrange for chases, slots and openings in other building components during progress of construction, to allow for electrical installations.

C. Sequence, coordinate and integrate installations of electrical materials and equipment for efficient flow of the Work. Give particular attention to large equipment requiring positioning prior to closing in the building.

D. Install systems, materials and equipment level and plumb, parallel and perpendicular to other building systems and components, where installed exposed in finished spaces.

E. Measure indicated mounting heights to bottom of unit for suspended items and to center of unit for wall-mounting items.

F. Headroom Maintenance: If mounting heights or other location criteria are not indicated, arrange and install components and equipment to provide maximum possible headroom consistent with these requirements.

G. Equipment: Install to facilitate service, maintenance, and repair or replacement of components of both electrical equipment and other nearby installations. Connect in such a way as to facilitate future disconnecting with minimum interference with other items in the vicinity.

H. Right of Way: Give to piping systems installed at a required slope.

3.4 FIRESTOPPING

A. Apply firestopping to penetrations of fire-rated floor and wall assemblies for electrical installations to restore original fire-resistance rating of assembly. Firestopping materials and installation requirements are specified in Division 07 Section "Penetration Firestopping."

END OF SECTION 26 0500

PROJECT NO. 14-182.15 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES

GALESBURG-AUGUSTA PRIMARY SCHOOL TELESCOPING STANDS 26 0519 - 1

GALESBURG-AUGUSTA COMMUNITY SCHOOLS 08/21/2019

© 2019 Tower Pinkster Titus Associates - All Rights Reserved

SECTION 26 0519 - LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Building wires and cables rated 600 V and less.

2. Connectors, splices, and terminations rated 600 V and less.

1.2 INFORMATIONAL SUBMITTALS

A. Field quality-control test reports.

PART 2 - PRODUCTS

2.1 CONDUCTORS AND CABLES

A. Conductor Material: Copper complying with NEMA WC 70/ICEA S-95-658.

B. Conductor Insulation Types: Type THHN-2-THWN-2, Type XHHW-2 and Type SO

2.2 CONNECTORS AND SPLICES

A. Description: Factory-fabricated connectors and splices of size, ampacity rating, material, type, and class for application and service indicated.

2.3 SYSTEM DESCRIPTION

A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

B. Comply with NFPA 70.

PART 3 - EXECUTION

3.1 CONDUCTOR AND INSULATION APPLICATIONS

A. Minimum conductor size for power wiring #12 AWG.

B. Exposed Feeders: Type THHN-2-THWN-2, single conductors in raceway.

GALESBURG-AUGUSTA PRIMARY SCHOOL TELESCOPING STANDS 26 0519 - 2

GALESBURG-AUGUSTA COMMUNITY SCHOOLS 08/21/2019

© 2019 Tower Pinkster Titus Associates - All Rights Reserved

C. Feeders Concealed in Ceilings, Walls, and Partitions: Type THHN-2-THWN-2, single conductors in raceway.

D. Feeders Concealed in Concrete, below Slabs-on-Grade, and in Crawlspaces: Type THHN-2-THWN-2, single conductors in raceway.

E. Exposed Branch Circuits, including in Crawlspaces: Type THHN-2-THWN-2, single conductors in raceway.

F. Branch Circuits Concealed in Ceilings, Walls, and Partitions: Type THHN-2-THWN-2, single conductors in raceway.

G. Fixture Whips: Type MC cable may be used for light fixture whips only, with a maximum length of 6 feet.

H. Branch Circuits Concealed in Concrete and below Slabs-on-Grade: Type THHN-2-THWN-2, single conductors in raceway.

I. Underground Feeders and Branch Circuits: Type THHN-2-THWN-2, single conductors in raceway.

J. Cord Drops and Portable Appliance Connections: Type SO, hard service cord with stainless-steel, wire-mesh, strain relief device at terminations to suit application.

K. Class 1 Control Circuits: Type THHN-2-THWN-2, in raceway.

L. Class 2 Control Circuits: Type THHN-2-THWN-2, in raceway or Power-limited cable, concealed in building finishes where raceway is not specified.

3.2 INSTALLATION OF CONDUCTORS AND CABLES

A. Where 120 volt, 20 amp, branch circuit wiring from panelboard to first outlet exceeds 100 feet in length, increase home-run wire size to #10 AWG.

B. Where 277 volt, 20 amp, branch circuit wiring from panelboard to first light fixture exceeds 150 feet in length, increase home-run wire size to #10 AWG.

C. Common neutral conductors shall not be used for convenience outlet or lighting branch circuits.

D. Neutral conductors shall be clearly labeled at the panelboard with the circuit number of associated phase conductors.

E. Conceal cables in finished walls, ceilings, and floors, unless otherwise indicated.

F. Use manufacturer-approved pulling compound or lubricant where necessary; compound used must not deteriorate conductor or insulation. Do not exceed manufacturer's recommended maximum pulling tensions and sidewall pressure values.

G. Use pulling means, including fish tape, cable, rope, and basket-weave wire/cable grips, that will not damage cables or raceway.

H. Install exposed cables parallel and perpendicular to surfaces of exposed structural members, and follow surface contours where possible.

GALESBURG-AUGUSTA PRIMARY SCHOOL TELESCOPING STANDS 26 0519 - 3

GALESBURG-AUGUSTA COMMUNITY SCHOOLS 08/21/2019

© 2019 Tower Pinkster Titus Associates - All Rights Reserved

I. Seal around cables penetrating fire-rated elements according to Division 07 Section "Penetration Firestopping."

3.3 IDENTIFICATION

A. Identify and color-code conductors and cables according to Section 26 0553 "Identification for Electrical Systems."

B. Identify each spare conductor at each end with identity number and location of other end of conductor, and identify as spare conductor.

3.4 CONNECTIONS

A. Tighten electrical connectors and terminals according to manufacturer’s published torque-tightening values. If manufacturer’s torque values are not indicated, use those specified in UL 486A and UL 486B.

B. Make splices and taps that are compatible with conductor material and that possess equivalent or better mechanical strength and insulation ratings than unspliced conductors.

C. Wiring at Outlets: Install conductor at each outlet, with at least 12 inches(300 mm) of slack.

3.5 SLEEVE AND SLEEVE-SEAL INSTALLATION FOR ELECTRICAL PENETRATIONS

A. Install sleeves and sleeve seals at penetrations of exterior floor and wall assemblies. Comply with requirements in Division 26 Section "Sleeves and Sleeve Seals for Electrical Raceways and Cabling."

3.6 FIRESTOPPING

A. Apply firestopping to electrical penetrations of fire-rated floor and wall assemblies to restore original fire-resistance rating of assembly according to Division 07 Section "Penetration Firestopping."

3.7 FIELD QUALITY CONTROL

A. Perform tests and inspections and prepare test reports.

B. Tests and Inspections:

1. After installing conductors and cables and before electrical circuitry has been energized, test for compliance with requirements.

2. Infrared Scanning: After Substantial Completion, but not more than 60 days after Final Acceptance, perform an infrared scan of each splice in cables and conductors No. 3 AWG and larger. Remove box and equipment covers so splices are accessible to portable scanner.

a. Follow-up Infrared Scanning: Perform an additional follow-up infrared scan of each splice 11 months after date of Substantial Completion.

b. Instrument: Use an infrared scanning device designed to measure temperature or to detect significant deviations from normal values. Provide calibration record for device.

GALESBURG-AUGUSTA PRIMARY SCHOOL TELESCOPING STANDS 26 0519 - 4

GALESBURG-AUGUSTA COMMUNITY SCHOOLS 08/21/2019

© 2019 Tower Pinkster Titus Associates - All Rights Reserved

c. Record of Infrared Scanning: Prepare a certified report that identifies splices checked and that describes scanning results. Include notation of deficiencies detected, remedial action taken, and observations after remedial action.

C. Remove and replace malfunctioning units and retest as specified above.

END OF SECTION 26 0519

PROJECT NO. 14-182.15 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

GALESBURG-AUGUSTA PRIMARY SCHOOL TELESCOPING STANDS 26 0529 - 1

GALESBURG-AUGUSTA COMMUNITY SCHOOLS 08/21/2019

© 2019 Tower Pinkster Titus Associates - All Rights Reserved

SECTION 26 0529 - HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes:

1. Hangers and supports for electrical equipment and systems.

2. Construction requirements for concrete bases.

1.2 PERFORMANCE REQUIREMENTS

A. Design supports for multiple raceways capable of supporting combined weight of supported systems and its contents.

B. Design equipment supports capable of supporting combined operating weight of supported equipment and connected systems and components.

C. Rated Strength: Adequate in tension, shear, and pullout force to resist maximum loads calculated or imposed for this Project, with a minimum structural safety factor of five times the applied force.

1.3 INFORMATIONAL SUBMITTALS

A. Welding certificates.

1.4 QUALITY ASSURANCE

A. Welding: Qualify procedures and personnel according to AWS D1.1/D1.1M, "Structural Welding Code - Steel."

B. Comply with NFPA 70.

PART 2 - PRODUCTS

2.1 SUPPORT, ANCHORAGE, AND ATTACHMENT COMPONENTS

A. Steel Slotted Support Systems: Comply with MFMA-4, factory-fabricated components for field assembly.

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. Allied Tube & Conduit.

b. Cooper B-Line, Inc.; a division of Cooper Industries.

c. ERICO International Corporation.

d. GS Metals Corp.

GALESBURG-AUGUSTA PRIMARY SCHOOL TELESCOPING STANDS 26 0529 - 2

GALESBURG-AUGUSTA COMMUNITY SCHOOLS 08/21/2019

© 2019 Tower Pinkster Titus Associates - All Rights Reserved

e. Thomas & Betts Corporation/ A Member of the ABB Group.

f. Unistrut; Tyco International, Ltd.

g. Wesanco, Inc.

2. Metallic Coatings: Hot-dip galvanized after fabrication and applied according to MFMA-4.

3. Nonmetallic Coatings: Manufacturer's standard PVC, polyurethane, or polyester coating applied according to MFMA-4.

4. Painted Coatings: Manufacturer's standard painted coating applied according to MFMA-4.

5. Channel Dimensions: Selected for applicable load criteria.

B. Raceway and Cable Supports: As described in NECA 1 and NECA 101.

C. Conduit and Cable Support Devices: Steel and malleable-iron hangers, clamps, and associated fittings, designed for types and sizes of raceway or cable to be supported.

D. Support for Conductors in Vertical Conduit: Factory-fabricated assembly consisting of threaded body and insulating wedging plug or plugs for non-armored electrical conductors or cables in riser conduits. Plugs shall have number, size, and shape of conductor gripping pieces as required to suit individual conductors or cables supported. Body shall be malleable iron.

E. Structural Steel for Fabricated Supports and Restraints: ASTM A 36/A 36M, steel plates, shapes, and bars; black and galvanized.

F. Mounting, Anchoring, and Attachment Components: Items for fastening electrical items or their supports to building surfaces include the following:

1. Powder-Actuated Fasteners: Threaded-steel stud, for use in hardened portland cement concrete, steel, or wood, with tension, shear, and pullout capacities appropriate for supported loads and building materials where used.

a. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1) Hilti Inc.

2) ITW Ramset/Red Head; a division of Illinois Tool Works, Inc.

3) MKT Fastening, LLC.

4) Simpson Strong-Tie Co., Inc.; Masterset Fastening Systems Unit.

2. Mechanical-Expansion Anchors: Insert-wedge-type, zinc-coated steel, for use in hardened portland cement concrete with tension, shear, and pullout capacities appropriate for supported loads and building materials in which used.

a. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1) Cooper B-Line, Inc.; a division of Cooper Industries.

2) Empire Tool and Manufacturing Co., Inc.

3) Hilti Inc.

4) ITW Ramset/Red Head; a division of Illinois Tool Works, Inc.

5) MKT Fastening, LLC.

GALESBURG-AUGUSTA PRIMARY SCHOOL TELESCOPING STANDS 26 0529 - 3

GALESBURG-AUGUSTA COMMUNITY SCHOOLS 08/21/2019

© 2019 Tower Pinkster Titus Associates - All Rights Reserved

3. Concrete Inserts: Steel or malleable-iron, slotted support system units similar to MSS Type 18;

complying with MFMA-4 or MSS SP-58.

4. Clamps for Attachment to Steel Structural Elements: MSS SP-58, type suitable for attached structural element.

5. Through Bolts: Structural type, hex head, and high strength. Comply with ASTM A 325.

6. Toggle Bolts: All-steel springhead type.

7. Hanger Rods: Threaded steel.

2.2 FABRICATED METAL EQUIPMENT SUPPORT ASSEMBLIES

A. Description: Welded or bolted, structural-steel shapes, shop or field fabricated to fit dimensions of supported equipment.

B. Materials: Comply with requirements in Division 05 Section "Metal Fabrications" for steel shapes and plates.

PART 3 - EXECUTION

3.1 APPLICATION

A. Comply with NECA 1 for application of hangers and supports for electrical equipment and systems, except if requirements in this Section are stricter.

B. Maximum Support Spacing and Minimum Hanger Rod Size for Raceway: Space supports for EMT, IMC, and RMC as scheduled in NECA 1, where Table 1 lists maximum spacings less than stated in NFPA 70.

Minimum rod size shall be 1/4 inch(6 mm) in diameter.

C. Multiple Raceways or Cables: Install trapeze-type supports fabricated with steel slotted or other support system, sized so capacity can be increased by at least 25 percent in future without exceeding specified design load limits.

1. Secure raceways and cables to trapeze member with clamps approved for application.

2. Secure raceways and cables to these supports with single-bolt conduit clamps using spring friction action for retention in support channel.

D. Spring-steel clamps designed for supporting single conduits without bolts may be used for 1-1/2-inch(38-

mm) and smaller raceways serving branch circuits and communication systems above suspended ceilings and for fastening raceways to trapeze supports.

E. Provide independent support rings/shepherd hooks for any low voltage communications systems cabling.

Cabling shall not rest on ceiling and shall be organized neatly on hooks. Cable shall not be visible in exposed ceiling spaces.

3.2 SUPPORT INSTALLATION

A. Comply with NECA 1 for installation requirements, except as specified in this Article.

GALESBURG-AUGUSTA PRIMARY SCHOOL TELESCOPING STANDS 26 0529 - 4

GALESBURG-AUGUSTA COMMUNITY SCHOOLS 08/21/2019

© 2019 Tower Pinkster Titus Associates - All Rights Reserved

B. Raceway Support Methods: In addition to methods described in NECA 1, EMT may be supported by openings through structure members, as permitted in NFPA 70.

C. Strength of Support Assemblies: Where not indicated, select sizes of components so strength will be adequate to carry present and future static loads within specified loading limits. Minimum static design load used for strength determination shall be weight of supported components plus 200 lb(90 kg).

D. Mounting and Anchorage of Surface-Mounted Equipment and Components: Anchor and fasten electrical items and their supports to building structural elements by the following methods unless otherwise indicated by code:

1. To Wood: Fasten with lag screws or through bolts.

2. To New Concrete: Bolt to concrete inserts.

3. To Masonry: Approved toggle-type bolts on hollow masonry units and expansion anchor fasteners on solid masonry units.

4. To Existing Concrete: Expansion anchor fasteners.

5. Instead of expansion anchors, powder-actuated driven threaded studs provided with lock washers and nuts may be used in existing standard-weight concrete 4 inches(100 mm) thick or greater. Do not use for anchorage to lightweight-aggregate concrete or for slabs less than 4 inches(100 mm) thick.

6. To Steel: Welded threaded studs complying with AWS D1.1/D1.1M, with lock washers and nuts, beam clamps (MSS Type 19, 21, 23, 25, or 27) complying with MSS SP-69 or spring-tension clamps.

7. To Light Steel: Sheet metal screws.

8. Items Mounted on Hollow Walls and Nonstructural Building Surfaces: Mount cabinets, panelboards, disconnect switches, control enclosures, pull and junction boxes, transformers, and other devices on slotted-channel racks attached to substrate.

E. Drill holes for expansion anchors in concrete at locations and to depths that avoid reinforcing bars.

3.3 INSTALLATION OF FABRICATED METAL SUPPORTS

A. Comply with installation requirements in Division 05 Section "Metal Fabrications" for site-fabricated metal supports.

B. Cut, fit, and place miscellaneous metal supports accurately in location, alignment, and elevation to support and anchor electrical materials and equipment.

C. Field Welding: Comply with AWS D1.1/D1.1M.

3.4 PAINTING

A. Touchup: Clean field welds and abraded areas of shop paint. Paint exposed areas immediately after erecting hangers and supports. Use same materials as used for shop painting. Comply with SSPC-PA 1 requirements for touching up field-painted surfaces.

1. Apply paint by brush or spray to provide minimum dry film thickness of 2.0 mils(0.05 mm).

B. Touchup: Comply with requirements in Division 09 painting Sections for cleaning and touchup painting of field welds, bolted connections, and abraded areas of shop paint on miscellaneous metal.

GALESBURG-AUGUSTA PRIMARY SCHOOL TELESCOPING STANDS 26 0529 - 5

GALESBURG-AUGUSTA COMMUNITY SCHOOLS 08/21/2019

© 2019 Tower Pinkster Titus Associates - All Rights Reserved

C. Galvanized Surfaces: Clean welds, bolted connections, and abraded areas and apply galvanizing-repair paint to comply with ASTM A 780.

END OF SECTION 26 0529

PROJECT NO. 14-182.15 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS

GALESBURG-AUGUSTA PRIMARY SCHOOL TELESCOPING STANDS 26 0533 - 1

GALESBURG-AUGUSTA COMMUNITY SCHOOLS 08/21/2019

© 2019 Tower Pinkster Titus Associates - All Rights Reserved

SECTION 26 0533 - RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Metal conduits, tubing, and fittings.

1.2 DEFINITIONS

A. GRC: Galvanized rigid steel conduit.

B. IMC: Intermediate metal conduit

1.3 ACTION SUBMITTALS

A. Product Data: For surface raceways, wireways and fittings, floor boxes, hinged-cover enclosures, and cabinets.

B. Shop Drawings: For custom enclosures and cabinets. Include plans, elevations, sections, hand holes and attachment details.

1.4 INFORMATIONAL SUBMITTALS

A. Coordination Drawings: Conduit routing plans, drawn to scale, on which the following items are shown and coordinated with each other, using input from installers of items involved:

1. Structural members in paths of conduit groups with common supports.

2. HVAC and plumbing items and architectural features in paths of conduit groups with common supports.

1.5 COORDINATION

A. Coordinate layout and installation of raceways, boxes, enclosures, cabinets, and suspension system with other construction that penetrates ceilings or is supported by them, including light fixtures, HVAC equipment, fire-suppression system, and partition assemblies.

GALESBURG-AUGUSTA PRIMARY SCHOOL TELESCOPING STANDS 26 0533 - 2

GALESBURG-AUGUSTA COMMUNITY SCHOOLS 08/21/2019

© 2019 Tower Pinkster Titus Associates - All Rights Reserved

PART 2 - PRODUCTS

2.1 METAL CONDUIT AND TUBING

A. Listing and Labeling: Metal conduits, tubing, and fittings shall be listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

B. EMT: Comply with ANSI C80.3 and UL 797.

C. Fittings for Metal Conduit: Comply with NEMA FB 1 and UL 514B.

1. Conduit Fittings for Hazardous (Classified) Locations: Comply with UL 886 and NFPA 70.

2. Fittings for EMT:

a. Material: Steel.

b. Type: Setscrew or compression.

3. Expansion Fittings: PVC or steel to match conduit type, complying with UL 651, rated for environmental conditions where installed, and including flexible external bonding jumper.

D. Joint Compound for IMC or GRC: Approved, as defined in NFPA 70, by authorities having jurisdiction for use in conduit assemblies, and compounded for use to lubricate and protect threaded conduit joints from corrosion and to enhance their conductivity.

2.2 SURFACE RACEWAYS

A. Listing and Labeling: Surface raceways and tele-power poles shall be listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

B. Surface Metal Raceways: Galvanized steel with snap-on covers. Finish with manufacturer's standard prime coating and ivory finish coat.

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. Thomas & Betts Corporation / A Member of the ABB Group.

b. Walker Systems, Inc.; Wiremold Company (The).

c. Wiremold Company (The); Electrical Sales Division.

C. Surface Metal Raceways: Satin anodized extruded aluminum with snap-on covers.

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. Post Glover

b. Thomas & Betts Corporation / A Member of the ABB Group

c. Wiremold Company

D. Types, sizes, and channels as indicated and required for each application, with fittings that match and mate with raceways. Provide concealed support clips or fasten raceway internally. Do not use external mounting straps.

GALESBURG-AUGUSTA PRIMARY SCHOOL TELESCOPING STANDS 26 0533 - 3

GALESBURG-AUGUSTA COMMUNITY SCHOOLS 08/21/2019

© 2019 Tower Pinkster Titus Associates - All Rights Reserved

2.3 BOXES, ENCLOSURES, AND CABINETS

A. General Requirements for Boxes, Enclosures, and Cabinets: Boxes, enclosures, and cabinets installed in wet locations shall be listed for use in wet locations.

B. Sheet Metal Outlet and Device Boxes: Comply with NEMA OS 1 and UL 514A.

C. Cast-Metal Outlet and Device Boxes: Comply with NEMA FB 1, ferrous alloy, Type FD, with gasketed cover.

D. Small Sheet Metal Pull and Junction Boxes: NEMA OS 1.

E. Box extensions used to accommodate new building finishes shall be of same material as recessed box.

F. Hinged-Cover Enclosures: NEMA 250, Type 1, with continuous hinge cover and flush latch.

1. Metal Enclosures: Steel, finished inside and out with manufacturer's standard enamel.

2. Nonmetallic Enclosures: Plastic, finished inside with radio-frequency-resistant paint.

G. Cabinets: NEMA 250, Type 1, galvanized steel box with removable interior panel and removable front, finished inside and out with manufacturer's standard enamel. Hinged door in front cover with flush latch and concealed hinge. Key latch to match panelboards. Include metal barriers to separate wiring of different systems and voltage and include accessory feet where required for freestanding equipment.

2.4 FACTORY FINISHES

A. Finish: For raceway, enclosure, or cabinet components, provide manufacturer's standard gray paint applied to factory-assembled surface raceways, enclosures, and cabinets before shipping.

2.5 CABLE PATHWAY AND FIRESTOP DEVICE

A. Manufacturer:

1. Specified Technologies, Inc., EZ-Path fire rated pathway.

2. Wiremold, FlameStopper FS Series thru-wall fitting for fire walls.

B. Description: Through-the-wall 3” x 3” steel wiring channel or 4” EMT equipped with heat expanding intumescent fire stopping material.

C. Wiring channel shall be provided with steel wall plates allowing for single or multiple channels to be ganged together.

D. Wiring channel shall have an F rating equal to the rating of the barrier in which it is installed.

E. Wiring channel shall be capable of allowing a 0 to 100 percent visual fill of cable.

F. Wiring channel shall be tested in accordance with ASTM E 814 (ANSI/UL1479). Channel shall bear the UL classification marking.

GALESBURG-AUGUSTA PRIMARY SCHOOL TELESCOPING STANDS 26 0533 - 4

GALESBURG-AUGUSTA COMMUNITY SCHOOLS 08/21/2019

© 2019 Tower Pinkster Titus Associates - All Rights Reserved

G. Provide the quantity of devices needed to allow a cable pass cross section capacity of 50 percent of the adjacent cable tray cross section.

PART 3 - EXECUTION

3.1 RACEWAY APPLICATION

A. Indoors:

1. Exposed in Unfinished Utility Spaces (mechanical rooms, electrical rooms and tunnels): EMT.

2. Exposed in Finished Spaces: All conduit shall be concealed unless specifically indicated on plans.

3. Exposed and Subject to Severe Physical Damage: Rigid steel conduit or IMC.

4. Concrete Floors: RNC.

5. Concealed in Ceilings and Interior Walls and Partitions: EMT

6. Connection to Vibrating Equipment (Including Transformers and Hydraulic, Pneumatic, Electric

Solenoid, or Motor-Driven Equipment): FMC; except use LFMC in damp or wet locations.

7. Damp or Wet Locations: Rigid steel conduit or IMC.

8. Boxes and Enclosures: NEMA 250, Type 1, except as follows:

B. Minimum Raceway Size: 1/2-inch trade size(16mm).

C. Raceway Fittings: Compatible with raceways and suitable for use and location.

1. Intermediate Steel Conduit: Use threaded rigid steel conduit fittings, unless otherwise indicated.

3.2 INSTALLATION

A. Comply with NECA 1 and NECA 101 for installation requirements except where requirements on Drawings or in this Article are stricter. Comply with NFPA 70 limitations for types of raceways allowed in specific occupancies and number of floors.

B. Provide separate raceways for lighting, receptacle, and motor loads. Do not mix branch circuit wiring for these different loads in the same raceway.

C. Keep raceways at least 6 inches (150 mm) away from parallel runs of flues and steam or hot-water pipes.

Install horizontal raceway runs above water and steam piping.

D. Complete raceway installation before starting conductor installation.

E. Support raceways as specified in Division 26 Section "Hangers and Supports for Electrical Systems."

F. Install temporary closures to prevent foreign matter from entering raceways.

G. Protect stub-ups from damage where conduits rise through floor slabs. Arrange so curved portions of bends are not visible above finished slab.

H. Install no more than the equivalent of three 90-degree bends in any conduit run except for communications conduits, for which fewer bends are allowed.

GALESBURG-AUGUSTA PRIMARY SCHOOL TELESCOPING STANDS 26 0533 - 5

GALESBURG-AUGUSTA COMMUNITY SCHOOLS 08/21/2019

© 2019 Tower Pinkster Titus Associates - All Rights Reserved

I. Make bends and offsets so ID is not reduced. Keep legs of bends in same plane and keep straight legs of offsets parallel, unless otherwise indicated.

J. Conceal conduit and EMT within finished walls, ceilings, and floors, unless otherwise indicated.

1. Install concealed raceways with a minimum of bends in shortest practical distance, considering type of building construction and obstructions, unless otherwise indicated.

2. Conduit and EMT may be surface mounted in Mechanical and Electrical Rooms except for wiring devices, light switches, low voltage devices or any other device shall be concealed in new wall.

3. Surface mounted conduit or EMT may be used where specifically approved by Architect/Engineer.

In such situations, the conduit, fastening devices, and junction boxes shall be painted to match the adjacent surface.

K. Raceways Embedded in Slabs: Install in middle 1/3 of slab thickness where practical and leave at least 2 inches (50 mm) of concrete cover.

1. Secure raceways to reinforcing rods to prevent sagging or shifting during concrete placement.

2. Space raceways laterally to prevent voids in concrete.

3. Run conduit larger than 1-inch trade size (27mm) parallel or at right angles to main reinforcement.

Where at right angles to reinforcement, place conduit close to slab support.

4. Change from nonmetallic tubing to rigid steel conduit, or IMC before rising above floor.

L. Install exposed raceways parallel or at right angles to nearby surfaces or structural members and follow surface contours as much as possible.

1. Run parallel or banked raceways together on common supports.

2. Make parallel bends in parallel or banked runs. Use factory elbows only where elbows can be installed parallel; otherwise, provide field bends for parallel raceways.

M. Stub-ups to Above Recessed Ceilings:

1. Use EMT, IMC, or RMC for raceways.

2. Use a conduit bushing or insulated fitting to terminate stub-ups not terminated in hubs or in an enclosure.

N. Join raceways with fittings designed and approved for that purpose and make joints tight.

1. Use insulating bushings to protect conductors.

O. Tighten set screws of threadless fittings with suitable tools.

P. Terminations:

1. Where raceways are terminated with locknuts and bushings, align raceways to enter squarely and install locknuts with dished part against box. Use two locknuts, one inside and one outside box.

2. Where raceways are terminated with threaded hubs, screw raceways or fittings tightly into hub so end bears against wire protection shoulder. Where chase nipples are used, align raceways so coupling is square to box; tighten chase nipple so no threads are exposed.

3. Telephone, data and fiber optic cable conduits shall be provided with bushings on conduit ends.

Q. Install pull wires in empty raceways. Use polypropylene or monofilament plastic line with not less than 200-lb (90-kg) tensile strength. Leave at least 12 inches (300 mm) of slack at each end of pull wire.

GALESBURG-AUGUSTA PRIMARY SCHOOL TELESCOPING STANDS 26 0533 - 6

GALESBURG-AUGUSTA COMMUNITY SCHOOLS 08/21/2019

© 2019 Tower Pinkster Titus Associates - All Rights Reserved

R. Color-Coding: Paint fire alarm system junction boxes and covers red.

S. Raceways for Optical Fiber and Communications Cable: Install as follows:

1. 3/4-Inch(19-mm) Trade Size and Smaller: Install raceways in maximum lengths of 50 feet(15 m).

2. 1-Inch(25-mm) Trade Size and Larger: Install raceways in maximum lengths of 75 feet(23 m).

3. Install with a maximum of two 90-degree bends or equivalent for each length of raceway unless

Drawings show stricter requirements. Separate lengths with pull or junction boxes or terminations at distribution frames or cabinets where necessary to comply with these requirements.

T. Install raceway sealing fittings at suitable, approved, and accessible locations and fill them with UL-listed sealing compound. For concealed raceways, install each fitting in a flush steel box with a blank cover plate having a finish similar to that of adjacent plates or surfaces. Install raceway sealing fittings at the following points:

1. Where conduits pass from warm to cold locations, such as boundaries of refrigerated spaces.

2. Where otherwise required by NFPA 70.

U. Expansion-Joint Fittings:

1. Install in each run of aboveground RNC that is located where environmental temperature change may exceed 30 deg F (17 deg C) and that has straight-run length that exceeds 25 feet (7.6 m).

Install in each run of aboveground RMC and EMT conduit that is located where environmental temperature change may exceed 100 deg F (55 deg C) and that has straight-run length that exceeds 100 feet (30 m).

2. Install type and quantity of fittings that accommodate temperature change listed for each of the following locations:

a. Outdoor Locations Not Exposed to Direct Sunlight: 125 deg F (70 deg C) temperature change.

b. Outdoor Locations Exposed to Direct Sunlight: 155 deg F (86 deg C) temperature change.

c. Indoor Spaces Connected with Outdoors without Physical Separation: 125 deg F (70 deg C) temperature change.

d. Attics: 135 deg F (75 deg C) temperature change.

3. Install fitting(s) that provide expansion and contraction for at least 0.00041 inch per foot of length of straight run per deg F (0.06 mm per meter of length of straight run per deg C) of…