Raw Water Transmission Main – Phase 1 Bidding Documents

These are bidding and contract documents for the City of Haverhill, Massachusetts, for construction of a Raw Water Transmission Main – Phase 1 project. The project consists of approximately 5,000 linear feet of new 24-inch diameter ductile iron raw water main, including two stream crossings, air release valves and structures, and pavement restoration. The 24-inch ductile iron water main, gaskets, restrained joints, valves, and valve boxes will be pre-purchased by the Owner and made available to the Contractor; all other materials remain the Contractor's responsibility. The pre-bid conference is scheduled for Tuesday, November 17, 2026, at 10:00 AM, and sealed bids are due Wednesday, November 25, 2026, at 10:00 AM via the Wright-Pierce Online Plan Room. The contract time for substantial completion is 45 calendar days, with final completion within 60 calendar days after the Contract Time commences. Once a contract is issued, the Contractor may work 24 hours a day, 7 days a week, and is expected to mobilize and begin work within 10 days of the executed contract. The Contractor must furnish 100 percent performance and payment bonds with an acceptable surety.

The Owner anticipates the project's total bid price will be approximately $2,000,000. Bid security in the amount of 5 percent of the maximum bid price is required, submitted as a bid bond issued by an acceptable surety. Liquidated damages are assessed at $2,500 per day for failure to achieve substantial completion and $2,500 per day for failure to achieve final completion. The project is subject to Massachusetts General Laws Chapter 30, Section 39M procurement requirements and prevailing wage rates as determined by the Executive Office of Labor and Workforce Development. All employees must have completed a 10-hour OSHA-approved construction safety and health course before beginning work. The Contractor must comply with all applicable federal and state laws, including the Davis-Bacon Act minimum wage requirements, occupational safety and health regulations, and Massachusetts tax compliance requirements. Bidding documents are available for download from the Wright-Pierce online plan room at no cost, and prospective bidders are required to register as plan holders to receive addenda and official notifications.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RAW WATER TRANSMISSION MAIN

CITY OF HAVERHILL

HAVERHILL, MASSACHUSETTS

BIDDING/CONTRACT DOCUMENTS

AND TECHNICAL SPECIFICATIONS

NOVEMBER 2026

13582B

CITY OF HAVERHILL

HAVERHILL, MASSACHUSETTS

BIDDING/CONTRACT DOCUMENTS

AND TECHNICAL SPECIFICATIONS

FOR

RAW WATER TRANSMISSION MAIN

NOVEMBER 2026

Prepared By:

Wright-Pierce 78 Blanchard Road, Suite 404

Burlington, MA 01803 978-416-8000

Stacey Smith Williamson-MA

Stacey Smith rjw

Stacey Smith Typewriter 11/11/26

TABLE OF CONTENTS

SECTION TITLE

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00102 Advertisement for Bid 00200 Instructions to Bidders 00412 Form General Bid 00414 Certificate of Authority to Sign 00430 Bid Bond Penal Sum 00450 Qualifications Statement 00510 Notice of Award 00520 Agreement Stipulated Price 00550 Notice to Proceed 00610 Performance Bond 00615 Payment Bond 00620 Application for Payment 00700 General Conditions 00800 SC-1 to 19 Supplementary Conditions 00800 SC-20-1 Mass General Laws 00800 SC-32 Wage Rates 00830 Construction General Permit 00842 Change Order 00920 Certificate of Substantial Completion 00935 Notice of Acceptability of Work 00936 Consent of Surety to Final Payment 00937 Contractor's Affidavit 00938 Contractor's Release 00939 Waiver of Lien - Materials and Labor 00940 Work Change Directive 00941 Change Order

DIVISION 01 - GENERAL REQUIREMENTS

01010A Summary of Work 01050 Coordination 01070 Abbreviations & Symbols 01150C Measurement and Payment 01151 Special Provisions Price Adjustments 01200 Project Meetings 01310 Construction Schedules 01320 Safety and Health Plan 01340 Submittals 01370 Schedule of Values 01380 Construction Photographs 01400 Quality Control 01500 Temporary Facilities and Controls 01562 Dust Control 01570 Traffic Regulation 01572 Construction General Permit 01710 Project Cleaning 01715 Cleaning Testing and Disinfection 01720 Project Record Documents

TABLE OF CONTENTS (CONT.)

SECTION TITLE

13582B

DIVISION 02 - SITE CONSTRUCTION

02170 Rock Removal 02200 Earthwork 02225 Flowable Fill 02270 Temporary Erosion Control 02485 Loaming and Seeding 02501 Removal and Replacement of Paving 02577 Pavement Markings 02601 Covers and Frames 02610 Rigid Board Insulation for Pipe in Trenches 02614H Field Applied Pipe Insulation 02615 Ductile Iron Pipe and Fittings Buried Applications 02626 Copper Service Pipe and Fittings Buried Applications 02638 Butterfly Valves for Buried Applications 02642 Corporation-Stops 02646H Valve Box Debris Cap 02650 Buried Utility Markings 02655 Couplings and Connectors for Buried Applications 02656 Air Release Valves

DIVISION 03 - CONCRETE

03420 Precast Concrete Structures

END OF SECTION

00102-1

EJCDC® C-111, Advertisement for Bids for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Page 1 of 2 13582B

SECTION 00102

ADVERTISEMENT FOR BIDS

City of Haverhill Haverhill, Massachusetts

Raw Water Transmission Main – Phase 1

General Notice

The City of Haverhill (Owner) is requesting Bids for the construction of the following Project:

Raw Water Transmission Main – Phase 1

Sealed Bids for the construction of the Project will be received at the Wright-Pierce Online Plan Room until Wednesday November 25, 2026 at 10:00 AM local time. A conference call will be held at 10:00 AM and bids will be publicly opened and read. A link to the conference call will be sent to all registered plan holders prior to the bid opening. If anyone else wishes to attend, please contact Wright-Pierce to request a meeting link. The Project is being bid under the provisions of M.G.L. c.30, s39M.

The Project includes the following Work:

The City of Haverhill is under a water supply emergency. This project will provide needed infrastructure to allow them to replenish their supplies. Expediency is of the essence. The project consists of the construction of approximately 5,000 linear feet of new 24-inch diameter ductile iron raw water main. The work includes two stream crossings, air release valves and structures and pavement restoration. There are no services or hydrants. 24-inch ductile iron water main, gaskets and restrained joints, valves and valve boxes will be pre-purchased by the Owner and made available to the Contractor. All other materials needed will be the responsibility of the Contractor. It is the intent of the City to issue an award and execute a contract with the apparent low bidder as quickly as possible. The apparent low bidder will also be expected to mobilize and begin the work within 10 days of an executed contract. The time for completion of the work is 45 days. Once a contract has been issued, the contractor will be allowed to proceed and work 24 hours a day, 7 days a week.

Owner anticipates that the Project’s total bid price will be approximately $2M.

Obtaining the Bidding Documents

Information and Bidding Documents for the Project can be found at the following designated website:

https://www.wright-pierce.com/projects

Bidding Documents may be downloaded from the designated website at no cost.

To be considered a responsive Bidder, the Bidder shall have obtained at least one set of Bidding Documents from the “Issuing Office” (Wright-Pierce via its online plan room) using the name that is to appear on the Bid Form. The designated website will be updated periodically with addenda, lists of plan holders, reports, and other information relevant to submitting a Bid for the Project. All official notifications, addenda, and other Bidding Documents will be offered only through the designated website. Neither Owner nor Engineer will be responsible for Bidding Documents, including addenda, if any, obtained from sources other than the designated website. It is the Bidder’s responsibility to check the designated website for addenda. Bidders shall review and acknowledge all Addenda on the Bid Form.

Direct all questions regarding distribution of Bidding Documents to both Rob Williamson and Amy Coppers Costantino, via rob.williamson@wright-pierce.com and amy.coppers@wright-pierce.com mailto:rob.williamson@wright-pierce.com mailto:amy.coppers@wright-pierce.com

00102-2

ADVERTISEMENT FOR BIDS

EJCDC® C-111, Advertisement for Bids for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Page 2 of 2 13582B respectively. No response will be given to questions received less than five (5) days before the Bid opening date.

Prevailing Wage Applicability

Minimum Wage Rates as determined by the Executive Office of Labor and Workforce Development under the provision of the Massachusetts General Laws, Chapter 149, Sections 26 to 27D, as amended, apply to this project. It is the responsibility of the contractor, before bid opening, to request if necessary, any additional information on Minimum Wage Rates for those trades people who may be employed for the proposed work under this contract.

Pre-bid Conference

A pre-bid conference call for the Project will be held on Tuesday November 17 at 10 AM. A URL link and dial-in phone number for the conference call will be emailed to all registered plan holders prior to the pre-bid meeting. Attendance at the pre-bid conference is not mandatory but strongly encouraged.

Instructions to Bidders

For all further requirements regarding bid submittal, qualifications, procedures, and contract award, refer to the Instructions to Bidders that are included in the Bidding Documents.

The bidding and award of this Contract will be under the provisions of M.G.L. Chapter 30, Section 39M.

Complete instructions for filing Bids are included in the Instructions to Bidders.

Each Bid shall be submitted in accordance with the Instructions to Bidders and shall be accompanied by a Bid Security in the amount of 5 percent of the Bid.

No Bidder may withdraw their Bid for a period of thirty (30) days, excluding Saturdays, Sundays, and legal holidays after the actual date of the opening of the General Bids. This advertisement does not obligate the Owner for any costs associated with preparing or submitting bids.

Each Bid shall be submitted in accordance with the Instructions to Bidders and shall be accompanied by a Bid Security in the amount of 5 percent of the maximum Bid price made payable to Owner in the form of a bank money order or a Bid Bond issued by a surety meeting the requirements of paragraph 6.01 of the General and Supplementary Conditions.

The successful General Bidder must furnish a 100 percent Performance Bond and a 100 percent Payment Bond with a surety company acceptable to the Owner and conforming to the prerequisite requirements of Article 6 of the General Conditions.

The Owner reserves the right to waive any informality in or to reject any or all Bids if deemed to be in its best interest.

Bidders are required to certify, under penalty of perjury, that Bids have been prepared without collusion with other Bidders, subcontractors, suppliers, etc. This certification is included with the Bid Form and each Bidder must sign in the space provided.

This Advertisement is issued by:

Owner: City of Haverhill, Massachusetts By: Robert E. Ward, DPW Director Date: 11-11-2026

00200-1

EJCDC® C-200, Instructions to Bidders for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

TOC Page1 of 1 13582B

SECTION 00200

INSTRUCTIONS TO BIDDERS FOR CONSTRUCTION CONTRACT

TABLE OF CONTENTS

Page

Article 1— Defined Terms

Article 2— Bidding Documents

Article 3— Qualifications of Bidders

Article 4— Pre-Bid Conference

Article 5— Site and Other Areas; Existing Site Conditions; Examination of Site; Owner’s Safety Program;

Other Work at the Site

Article 6— Bidder’s Representations and Certifications

Article 7— Interpretations and Addenda

Article 8— Bid Security

Article 9— Contract Times

Article 10— Substitute and “Or Equal” Items

Article 11— Subcontractors, Suppliers, and Others

Article 12— Preparation of Bid

Article 13— Basis of Bid

Article 14— Submittal of Bid

Article 15— Modification and Withdrawal of Bid

Article 16— Opening of Bids

Article 17— Bids to Remain Subject to Acceptance

Article 18— Evaluation of Bids and Award of Contract

Article 19— Bonds and Insurance

Article 20— Signing of Agreement

Article 21— Sales and Use Taxes

Article 22— Contracts to Be Assigned

Article 23— Deletion of Items

Article 24— Federal Requirements

Article 25— Special Legal Requirements

00200-1

INSTRUCTIONS TO BIDDERS FOR CONSTRUCTION CONTRACT

EJCDC® C-200, Instructions to Bidders for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Page 1 of 14 13582B

ARTICLE 1—DEFINED TERMS

1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General Conditions and Supplementary Conditions.

1.02 Additional terms used in these Instructions to Bidders have the meanings indicated below:

A. Issuing Office—The office from which the Bidding Documents are to be issued, and which registers plan holders.

B. Bidder – The individual or entity who submits a Bid directly to the Owner.

C. Successful Bidder – The lowest responsible and eligible Bidder submitting a responsive Bid to whom Owner (on the basis of Owner’s evaluation as hereinafter provided) makes an award.

ARTICLE 2—BIDDING DOCUMENTS

2.01 Bidder shall obtain a complete set of Bidding Requirements and proposed Contract Documents (together, the Bidding Documents). See the Agreement for a list of the Contract Documents. It is Bidder’s responsibility to determine that it is using a complete set of documents in the preparation of a Bid. Bidder assumes sole responsibility for errors or misinterpretations resulting from the use of incomplete documents, by Bidder itself or by its prospective Subcontractors and Suppliers.

2.02 Bidding Documents are made available for the sole purpose of obtaining Bids for completion of the Project and permission to download or distribution of the Bidding Documents does not confer a license or grant permission or authorization for any other use. Authorization to download documents, or other distribution, includes the right for plan holders to print documents solely for their use, and the use of their prospective Subcontractors and Suppliers, provided the plan holder pays all costs associated with printing or reproduction. Printed documents may not be re-sold under any circumstances.

2.03 Owner has established a Bidding Documents Website as indicated in the Advertisement or invitation to bid. Owner recommends that Bidder register as a plan holder with the Issuing Office at such website, and obtain a complete set of the Bidding Documents from such website.

Bidders may rely that sets of Bidding Documents obtained from the Bidding Documents Website are complete, unless an omission is blatant. Registered plan holders will receive Addenda issued by Owner.

2.04 Bidder may register as a plan holder and obtain complete sets of Bidding Documents, in the number and format stated in the Advertisement or invitation to bid, from the Issuing Office.

Bidders may rely that sets of Bidding Documents obtained from the Issuing Office are complete, unless an omission is blatant. Registered plan holders will receive Addenda issued by Owner. All official notifications, addenda, and other Bidding Documents will be offered only through the designated website. Neither Owner nor Engineer will be responsible for Bidding Documents, including addenda, if any, obtained from sources other than the designated website. It is the Bidder’s responsibility to check the designated website for addenda. Bidders shall review and acknowledge all Addenda on the Bid Form.

00200-2

EJCDC® C-200, Instructions to Bidders for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Page 2 of 14 13582B

2.05 Electronic Documents

A. When the Bidding Requirements indicate that electronic (digital) copies of the Bidding Documents are available, such documents will be made available to the Bidders as Electronic Documents in the manner specified.

1. Bidding Documents will be provided in Adobe PDF (Portable Document Format) (.pdf).

It is the intent of the Engineer and Owner that such Electronic Documents are to be exactly representative of the paper copies of the documents. However, because the Owner and Engineer cannot totally control the transmission and receipt of Electronic Documents nor the Contractor’s means of reproduction of such documents, the Owner and Engineer cannot and do not guarantee that Electronic Documents and reproductions prepared from those versions are identical in every manner to the paper copies.

B. Unless otherwise stated in the Bidding Documents, the Bidder may use and rely upon complete sets of Electronic Documents of the Bidding Documents, described in Paragraph 2.06.A above. However, Bidder assumes all risks associated with differences arising from transmission/receipt of Electronic Documents versions of Bidding Documents and reproductions prepared from those versions and, further, assumes all risks, costs, and responsibility associated with use of the Electronic Documents versions to derive information that is not explicitly contained in printed paper versions of the documents, and for Bidder’s reliance upon such derived information.

ARTICLE 3—QUALIFICATIONS OF BIDDERS

3.1 To demonstrate Bidder’s qualifications to perform the Work, each Bidder must submit with its bid a completed Qualifications Statement (Section 00450) and such other data as may be called for below or in the Supplementary Conditions. Each Bid must contain evidence of the Bidder's qualification to do business in the state where the Project is located or covenant to obtain such qualification prior to award of contract.

3.2 Minimum criteria to ensure bidders finish the project on time shall include:

1. Documentation sufficient to demonstrate that the bidder has adequate personnel, equipment, and financial capability to complete the Contract within the schedule set forth in the Bid Documents. Such documentation shall include:

1. List of all personnel that will be assigned to the Contract including full name, and indication of whether personnel will be assigned full time to the Project or, if not, the Full Time Equivalent (FTE) (e.g., 0.5 FTE for an individual assigned for twenty hours per week).

2. List of all equipment available to the prospective bidder to conduct the work necessary to complete the Project.

3. List of all projects in construction or under bid by the prospective bidder that may overlap with the Project schedule, including project location; estimated project schedule, including commencement and completion dates; project size, including construction estimate, if known; and whether project is in construction or under bid.

4. Completed financial information form, which is included in Specification Section 00450 Qualifications Statement.

00200-3

EJCDC® C-200, Instructions to Bidders for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Page 3 of 14 13582B

3.03 No requirement in this Article 3 to submit information will prejudice the right of Owner to seek additional pertinent information regarding Bidder’s qualifications, such as written evidence such as financial data, previous experience, present commitments, and such other data as may be identified herein or requested by Owner and/or Engineer. This documentation, if requested by the Owner and/or Engineer, must be provided within ten (10) days of the request.

3.04 To be considered a responsive Bidder, the Contractor shall have obtained at least one set of Bidding Documents from the Issuing Office. The Bid will not be awarded to a Bidder unless a record for obtaining at least one set of Bidding Documents exists in the Issuing Office. To meet this requirement and to establish the record of receipt, a prospective Bidder must obtain Bidding Documents using the name that is to appear on the Bid Form.

ARTICLE 4—PRE-BID CONFERENCE

4.01 A non-mandatory pre-bid conference will be held at the time and location indicated in the Advertisement or invitation to bid. Representatives of Owner and Engineer will be present to discuss the Project. Prospective Bidders are strongly encouraged to attend.

4.02 Information presented at the pre-Bid conference does not alter the Contract Documents.

Owner will issue Addenda to make any changes to the Contract Documents that result from discussions at the pre-Bid conference. Information presented, and statements made at the pre-bid conference or any oral representation by the Owner or Owner’s representatives will not be binding or legally effective unless incorporated in an Addendum.

ARTICLE 5—SITE AND OTHER AREAS; EXISTING SITE CONDITIONS; EXAMINATION OF SITE; OWNER’S

SAFETY PROGRAM; OTHER WORK AT THE SITE

5.01 Site and Other Areas

A. The Site is identified in the Bidding Documents. By definition, the Site includes rights-of-way, easements, and other lands furnished by Owner for the use of the Contractor. Any additional lands required for temporary construction facilities, construction equipment, or storage of materials and equipment, and any access needed for such additional lands, are to be obtained and paid for by Contractor.

5.02 Existing Site Conditions

A. Subsurface and Physical Conditions; Hazardous Environmental Conditions

1. The Supplementary Conditions identify the following regarding existing conditions at or adjacent to the Site:

a. Those reports of explorations and tests of subsurface conditions at or adjacent to the Site that contain Technical Data.

b. Those drawings known to Owner of existing physical conditions at or adjacent to the Site, including those drawings depicting existing surface or subsurface structures at or adjacent to the Site (except Underground Facilities), that contain Technical Data.

c. Reports and drawings known to Owner relating to Hazardous Environmental Conditions that have been identified at or adjacent to the Site.

d. Technical Data contained in such reports and drawings.

00200-4

EJCDC® C-200, Instructions to Bidders for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Page 4 of 14 13582B

2. Owner will make copies of reports and drawings referenced above available to any Bidder on request. These reports and drawings are not part of the Contract Documents, but the Technical Data contained therein upon whose accuracy Bidder is entitled to rely, as provided in the General Conditions, has been identified and established in the Supplementary Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any Technical Data or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.

3. If the Supplementary Conditions do not identify Technical Data, the default definition of Technical Data set forth in Article 1 of the General Conditions will apply.

B. Underground Facilities: Underground Facilities are shown or indicated on the Drawings, pursuant to Paragraph 5.05 of the General Conditions, and not in the drawings referred to in Paragraph 5.02.A of these Instructions to Bidders. Information and data regarding the presence or location of Underground Facilities are not intended to be categorized, identified, or defined as Technical Data.

5.03 Other Site-related Documents

A. In addition to the documents regarding existing Site conditions referred to in Paragraph 5.02.A, the following other documents relating to conditions at or adjacent to the Site are known to Owner and made available to Bidders for reference:

1. None known

B. Owner has not verified the contents of these other Site-related documents, and Bidder may not rely on the accuracy of any data or information in such documents. Bidder is responsible for any interpretation or conclusion Bidder draws from the other Site-related documents.

C. The other Site-related documents are not part of the Contract Documents.

D. Bidders are encouraged to review the other Site-related documents, but Bidders will not be held accountable for any data or information in such documents. The requirement to review and take responsibility for documentary Site information is limited to information in (1) the Contract Documents and (2) the Technical Data.

5.04 Site Visit and Testing by Bidders

A. Bidder is required to visit the Site and conduct a thorough visual examination of the Site and adjacent areas. During the visit the Bidder must not disturb any ongoing operations at the Site.

B. Bidders visiting the Site are required to arrange their own transportation to the Site.

C. All access to the Site other than during a regularly scheduled Site visit must be coordinated through the following Owner or Engineer contact for visiting the Site: Shaun Burrier, City of Haverhill, 978-945-1133. Bidder must conduct the required Site visit during normal working hours.

D. Bidder is not required to conduct any subsurface testing, or exhaustive investigations of Site conditions. However, submission of a bid shall be based on a thorough understanding of the existing site conditions.

E. On request, and to the extent Owner has control over the Site, and schedule permitting, the Owner will provide Bidder general access to the Site to conduct such additional examinations, investigations, explorations, tests, and studies as Bidder deems necessary for

00200-5

EJCDC® C-200, Instructions to Bidders for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Page 5 of 14 13582B preparing and submitting a successful Bid. Owner will not have any obligation to grant such access if doing so is not practical because of existing operations, security or safety concerns, or restraints on Owner’s authority regarding the Site. Bidder is responsible for establishing access needed to reach specific selected test sites.

F. Bidder must comply with all applicable Laws and Regulations regarding excavation and location of utilities, obtain all permits, and comply with all terms and conditions established by Owner or by property owners or other entities controlling the Site with respect to schedule, access, existing operations, security, liability insurance, and applicable safety programs.

G. Bidder must fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies.

5.05 Owner’s Safety Program

A. Site visits and work at the Site may be governed by an Owner safety program. If an Owner safety program exists, it will be noted in the Supplementary Conditions. Bidder is solely responsible for the safety of all property, equipment and personnel at the site.

5.06 Other Work at the Site

A. Reference is made to Article 8 of the Supplementary Conditions for the identification of the general nature of other work of which Owner is aware (if any) that is to be performed at the Site by Owner or others (such as utilities and other prime contractors) and relates to the Work contemplated by these Bidding Documents. If Owner is party to a written contract for such other work, then on request, Owner will provide to each Bidder access to examine such contracts (other than portions thereof related to price and other confidential matters), if any.

ARTICLE 6—BIDDER’S REPRESENTATIONS AND CERTIFICATIONS

6.01 Express Representations and Certifications in Bid Form, Agreement

A. The Bid Form that each Bidder will submit contains express representations regarding the Bidder’s examination of Project documentation, Site visit, and preparation of the Bid, and certifications regarding lack of collusion or fraud in connection with the Bid. Bidder should review these representations and certifications, and assure that Bidder can make the representations and certifications in good faith, before executing and submitting its Bid.

B. If Bidder is awarded the Contract, Bidder (as Contractor) will make similar express representations and certifications when it executes the Agreement.

ARTICLE 7—INTERPRETATIONS AND ADDENDA

7.01 Owner on its own initiative may issue Addenda to clarify, correct, supplement, or change the Bidding Documents.

7.02 Bidder shall submit all questions about the meaning or intent of the Bidding Documents to Engineer in writing. Contact information and submittal procedures for such questions are as follows:

00200-6

EJCDC® C-200, Instructions to Bidders for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Page 6 of 14 13582B

A. Contacts for the project are as follows. If responding by email BOTH contacts must be included:

Rob Williamson Wright-Pierce 207.523.1403 rob.williamson@wright-pierce.com and

Amy Coppers Costantino Wright-Pierce 617.750.3052 amy.coppers@wright-pierce.com

7.03 Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda delivered to all registered plan holders. Questions received less than five (5) working days prior to the date for opening of Bids may not be answered. Addenda will be issued not later than three (3) working days before the bid opening.

Bidders are responsible for determining that they have received all Addenda issued.

7.04 Only responses set forth in an Addendum will be binding. Oral and other interpretations or clarifications will be without legal effect. Responses to questions are not part of the Contract Documents unless set forth in an Addendum that expressly modifies or supplements the Contract Documents.

7.05 Failure of a bidder to receive any addendum, or to acknowledge receipt thereof, will not relieve such bidder from conforming with the requirements which such addendum impose on his Bid or the Contract Documents, and may subject his Bid to disqualification by Owner.

ARTICLE 8—BID SECURITY

8.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of five (5) percent of Bidder’s maximum Bid price (determined by adding the base bid and all alternates) and in the form of a Bid bond issued by a surety meeting the requirements of Paragraph 6.01 of the General Conditions. Such Bid bond will be issued in the form included in the Bidding Documents. Bid security must be at least 5% of the Bidder’s maximum Bid price.

8.02 All Bid Securities of General Bidders except those of the three lowest responsible and eligible General Bidders will be returned within five (5) days, Saturdays, Sundays, and legal holidays excluded, after opening of the General Bids. The Bid security of the three lowest Bidders will be retained until the successful Bidder has executed the Contract Documents, furnished the required contract security and met the other conditions of the Notice of Award. If the Successful Bidder fails to execute and deliver the Contract Documents and furnish the required contract security within fifteen (15) days after the Notice of Award, Owner may consider the Bidder to be in default, annul the Notice of Award, and the Bid security of that Bidder will be forfeited to the Owner as liquidated damage. The amount forfeited to Owner shall not exceed the difference between the Bid Price of said Bidder and that of the next lowest responsible and eligible bidder and provided further that, in case of death, disability, or other unforeseen circumstances affecting the Bidder, such Bid Security may be returned to the Bidder.

mailto:rob.williamson@wright-pierce.com mailto:amy.coppers@wright-pierce.com

00200-7

EJCDC® C-200, Instructions to Bidders for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Page 7 of 14 13582B

ARTICLE 9—CONTRACT TIMES

9.01 The number of days within which, or the dates by which, the Work is to be (a) substantially completed and (b) ready for final payment, and (c) Milestones (if any) are to be achieved, are set forth in the Agreement.

9.02 Provisions for liquidated damages, if any, for failure to timely attain a Milestone, Substantial Completion, or completion of the Work in readiness for final payment, are set forth in the Agreement.

ARTICLE 10—SUBSTITUTE AND “OR EQUAL” ITEMS

10.01 The Contract, as awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents without consideration during the bidding and Contract award process of possible substitute or “or-equal” items. Procurement standards under M.G.L.

Chapter 30, Section 39M requires specifications be written for competitive bidding by at least three (3) manufacturers or suppliers for each item of material to be furnished under the contract. If three manufacturers or suppliers are not listed, then a substitute or “or-equal” item of material or equipment may be furnished or used by Contractor, if acceptable to Engineer.

Application for such acceptance will not be considered by Engineer until after the Effective Date of the Agreement. The procedure for submission of any such application by Contractor and consideration by Engineer is set forth in the General Conditions and may be supplemented in the General Requirements. The materials and equipment described in the Bidding Documents establish a standard of required type, function, and quality to be met by any proposed substitute or “or-equal” item. The burden of proof of the merit of the proposed item is upon Contractor. Engineer’s decision of approval or disapproval of a proposed item will be final and binding on the Contractor. Refer to General Conditions and Supplementary Conditions.

10.02 All prices that Bidder sets forth in its Bid will be based on the presumption that the Contractor will furnish the materials and equipment specified or described in the Bidding Documents, as supplemented by Addenda. Any assumptions regarding the possibility of post-Bid approvals of “or-equal” or substitution requests are made at Bidder’s sole risk.

10.03 Wherever it is written that an equipment manufacturer must have a specified period of experience with its product, equipment which does not meet the specified experience period can be considered if the equipment supplier or manufacturer is willing to provide a bond or cash deposit for the duration of the specified time period which will guarantee replacement of that equipment in the event of failure. Such bond shall be an Efficiency Guarantee Bond executed on a form to be approved by the OWNER.

ARTICLE 11—SUBCONTRACTORS, SUPPLIERS, AND OTHERS

11.01 A Bidder must be prepared to retain specific Subcontractors and Suppliers for the performance of the Work if required to do so by the Bidding Documents or in the Specifications. If a prospective Bidder objects to retaining any such Subcontractor or Supplier and the concern is not relieved by an Addendum, then the prospective Bidder should refrain from submitting a Bid.

00200-8

EJCDC® C-200, Instructions to Bidders for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Page 8 of 14 13582B

11.02 The apparent Successful Bidder, and any other Bidder so requested, must submit to Owner a list of the Subcontractors or Suppliers proposed for the following portions of the Work within five days after Bid opening:

11.03 If requested by Owner, such list must be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor or Supplier. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor or Supplier, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit an acceptable substitute.

11.04 If the apparent Successful Bidder submits a substitute, Bidder’s Bid price will be increased (or decreased) by the difference in cost occasioned by such substitution, and Owner may consider such price adjustment in evaluating Bids and making the Contract award.

11.05 If apparent Successful Bidder declines to make any such substitution, Owner may award the Contract to the next lowest Bidder that proposes to use acceptable Subcontractors and Suppliers. Declining to make requested substitutions will constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor or Supplier, so listed and against which Owner or Engineer makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Engineer subject to subsequent revocation of such acceptance as provided in Paragraph 7.07 of the General Conditions.

ARTICLE 12—PREPARATION OF BID

12.01 The Bid Form is included with the Bidding Documents.

A. All blanks on the Bid Form must be completed in ink and the Bid Form signed in ink. Erasures or alterations must be initialed in ink by the person signing the Bid Form. A Bid price must be indicated for each section, Bid item, alternate, adjustment unit price item, and unit price item listed therein.

B. If the Bid Form expressly indicates that submitting pricing on a specific alternate item is optional, and Bidder elects to not furnish pricing for such optional alternate item, then Bidder may enter the words “No Bid” or “Not Applicable.”

12.02 If Bidder has obtained the Bidding Documents as Electronic Documents, then Bidder shall prepare its Bid on a paper copy of the Bid Form printed from the Electronic Documents version of the Bidding Documents. The printed copy of the Bid Form must be clearly legible, printed on 8½ inch by 11-inch paper and as closely identical in appearance to the Electronic Document version of the Bid Form as may be practical. The Owner reserves the right to accept Bid Forms which nominally vary in appearance from the original paper version of the Bid Form, providing that all required information and submittals are included with the Bid.

12.03 A Bid by a corporation must be executed in the corporate name by a corporate officer (whose title must appear under the signature), accompanied by evidence of authority to sign. The corporate address and state of incorporation must be shown.

12.04 A Bid by a partnership must be executed in the partnership name and signed by a partner (whose title must appear under the signature), accompanied by evidence of authority to sign.

The official address of the partnership must be shown.

12.05 A Bid by a limited liability company must be executed in the name of the firm by a member or other authorized person and accompanied by evidence of authority to sign. The state of formation of the firm and the official address of the firm must be shown.

00200-9

EJCDC® C-200, Instructions to Bidders for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Page 9 of 14 13582B

12.06 A Bid by an individual must show the Bidder’s name and official address.

12.07 A Bid by a joint venture must be executed by an authorized representative of each joint venturer in the manner indicated on the Bid Form. The joint venture must have been formally established prior to submittal of a Bid, and the official address of the joint venture must be shown.

12.08 All names must be printed in ink below the signatures.

12.09 The Bid must contain an acknowledgment of receipt of all Addenda, the numbers of which must be filled in on the Bid Form.

12.10 Postal and e-mail addresses and telephone number for communications regarding the Bid must be shown.

12.11 The Bid must contain evidence of Bidder’s authority to do business in the state where the Project is located, or Bidder must certify in writing that it will obtain such authority within the time for acceptance of Bids and attach such certification to the Bid.

12.12 The products furnished are to meet or exceed all specified requirements of the Bidding Documents. No evaluation of submittals will be made prior to the Bid opening.

12.13 If Bidder is required to be licensed to submit a Bid or perform the Work in the state where the Project is located, the Bid must contain evidence of Bidder’s licensure, or Bidder must certify in writing that it will obtain such licensure within the time for acceptance of Bids and attach such certification to the Bid. Bidder’s state contractor license number, if any, must also be shown on the Bid Form.

12.14 Bidders attention is drawn to the requirements of M.G.L. c. 30 section 39L regarding registration of foreign businesses with the Secretary of the Commonwealth.

ARTICLE 13—BASIS OF BID

13.01 Lump Sum with Unit Prices and Alternates

A. Bidders must submit a Bid on a lump sum basis for each lump sum item, and on a unit price basis for each unit price item of Work listed in the Bid Form for the base Bid and include a separate price for each alternate described in the Bidding Documents and as provided for in the Bid Form. The price for each alternate will be the amount added to or deleted from the base Bid if Owner selects the alternate.

B. The “Bid Price” (sometimes referred to as the extended price) for each unit price Bid item will be the product of the “Estimated Quantity”, which Owner or its representative has set forth in the Bid Form, for the item and the corresponding “Bid Unit Price” offered by the Bidder. The final quantities and Contract Price will be determined in accordance with Paragraph 13.03 of the General Conditions.

C. Discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.

D. The total of all unit price “Bid Prices” and all lump sum items will be used by Owner for Bid comparison purposes.

E. Should the Bidder provide a different unit price for a Unit Price Bid Item included in an Alternative from the unit price for that same Unit Price Bid Item provided in the Base Bid, the

00200-10

EJCDC® C-200, Instructions to Bidders for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Page 10 of 14 13582B unit price provided in the Base Bid will be applied to the alternate and a corrected sum will be applied to the Bid.

13.02 Allowances

A. For cash allowances the Bid price must include such amounts as the Bidder deems proper for Contractor's overhead, costs, profit, and other expenses on account of cash allowances, if any, named in the Contract Documents, in accordance with Paragraph 13.02.B of the General Conditions.

13.03 Resolution of Discrepancies

A. Where there are discrepancies between numbers and words, words shall prevail.

ARTICLE 14—SUBMITTAL OF BID

14.01 Deleted.

14.02 A Bid must be received no later than the date and time prescribed and at the place indicated in the Advertisement or invitation to bid and must be enclosed in a plainly marked package with the Project title, and, if applicable, the designated portion of the Project for which the Bid is submitted, the name and address of Bidder, and must be accompanied by the Bid security and other required documents. If a Bid is sent by mail or other delivery system, the sealed envelope containing the Bid must be enclosed in a separate package plainly marked on the outside with the notation “BID ENCLOSED.” A mailed Bid must be addressed to the location designated in the Advertisement.

14.03 Bids received after the date and time prescribed for the opening of bids, or not submitted at the correct location or in the designated manner, will not be accepted and will be returned to the Bidder unopened.

ARTICLE 15—MODIFICATION AND WITHDRAWAL OF BID

15.01 An unopened Bid may be withdrawn by an appropriate document duly executed in the same manner that a Bid must be executed and delivered to the place where Bids are to be submitted prior to the date and time for the opening of Bids. Upon receipt of such notice, the unopened Bid will be returned to the Bidder.

15.02 If a Bidder wishes to modify its Bid prior to Bid opening, Bidder must withdraw its initial Bid in the manner specified in Paragraph 15.01 and submit a new Bid prior to the date and time for the opening of Bids.

15.03 If within 24 hours after Bids are opened any Bidder files a duly signed written notice with Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the preparation of its Bid, the Bidder may withdraw its Bid, and the Bid security will be returned. Thereafter, if the Work is rebid, the Bidder will be disqualified from further bidding on the Work.

ARTICLE 16—OPENING OF BIDS

16.01 Bids will be opened at the time and place indicated in the advertisement or invitation to bid and, unless obviously non-responsive, read aloud publicly. An abstract of the amounts of the

00200-11

EJCDC® C-200, Instructions to Bidders for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Page 11 of 14 13582B base Bids and major alternates, if any, will be made available to Bidders after the opening of Bids.

16.02 At a minimum, bid documents shall be reviewed/inspected for conformance with the following requirements in the order presented below. Failure to comply with any of these requirements may render the bid non-responsive and upon determination of such non-responsiveness, such bid shall be rejected immediately, set aside, and shall receive no further consideration at the sole discretion of the Owner.

A. Timeliness – The bid must be filed at the place and within the time specified therefore in the invitation to bid, and no bid shall be accepted after such time. The time at which a bid is filed should be time/date stamped or otherwise prominently noted on the bid;

B. Bid Security – Properly executed bid security, in the amount and terms specified in the invitation to bid (equal to 5% of Highest Possible Amount considering all alternatives) shall be submitted electronically with the bid;

C. Bid Bond - The Bid bond must be dated On or Before the Bid Date; Issued by a Bonding Company Licensed in Massachusetts; Accompanied by a Current Power of Attorney; Signed by Surety;

D. Check - The Check must be a Certified, Cashiers or Bank Treasurer’s; Dated on or Before the Bid Date;

E. Bid Signature – The bid and all accompanying documents so required shall be signed by the bidder or its authorized representative before submission;

F. Addenda –All bidders shall include with their bids written acknowledgement of receipt of all addenda, which acknowledgement may be on a form provided therefore by the Owner;

G. Alternates – Alternatives, if any, shall be acknowledged.

16.3 This is not an all-inclusive list of items that need to be included in the bid proposal. Refer to Section 00412 for a full listing of documents to be provided.

ARTICLE 17—BIDS TO REMAIN SUBJECT TO ACCEPTANCE

17.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.

ARTICLE 18—EVALUATION OF BIDS AND AWARD OF CONTRACT

18.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner also reserves the right to waive all minor Bid informalities.

18.02 Owner will reject the Bid of any Bidder that Owner finds, after reasonable inquiry and evaluation, to not be responsible.

00200-12

EJCDC® C-200, Instructions to Bidders for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Page 12 of 14 13582B

18.03 If Bidder purports to add terms or conditions to its Bid, takes exception to any provision of the Bidding Documents, or attempts to alter the contents of the Contract Documents for purposes of the Bid, whether in the Bid itself or in a separate communication to Owner or Engineer, then Owner will reject the Bid as nonresponsive.

18.04 If Owner awards the contract for the Work, such award will be to the responsible Bidder submitting the lowest responsive Bid.

18.05 Evaluation of Bids

A. In evaluating Bids, Owner will consider whether the Bids comply with the prescribed requirements, and such alternates, unit prices, and other data, as may be requested in the Bid Form or prior to the Notice of Award.

B. Deleted.

C. For the determination of the apparent low Bidder when unit price bids are submitted, Bids will be compared on the basis of the total of the products of the estimated quantity of each item and unit price Bid for that item, together with any lump sum items.

D. Deleted.

E. Deleted.

18.06 In evaluating whether a Bidder is responsible, Owner will consider the qualifications of the Bidder and may consider the qualifications and experience of Subcontractors and Suppliers proposed for those portions of the Work for which the identity of Subcontractors and Suppliers must be submitted as provided in the Bidding Documents.

18.07 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders and any proposed Subcontractors or Suppliers.

18.08 All protests arising from the Owner's procurement practices must be submitted to the Owner as soon as practical. Owner will investigate the basis for the protest, seek advice of legal counsel, document all meeting and actions, and attempt to resolve the protest promptly and equitably. In the event the protest cannot be settled, an appeal may be filed with the Attorney General’s Bid Protest Unit.

ARTICLE 19—BONDS AND INSURANCE

19.01 Article 6 of the General Conditions, as may be modified by the Supplementary Conditions, sets forth Owner’s requirements as to performance and payment bonds, other required bonds (if any), and insurance. When the Successful Bidder delivers the executed Agreement to Owner, it must be accompanied by required bonds and insurance documentation.

19.02 Article 8, Bid Security, of these Instructions, addresses any requirements for providing bid bonds as part of the bidding process.

ARTICLE 20—SIGNING OF AGREEMENT

20.01 When Owner issues a Notice of Award to the Successful Bidder, it will be accompanied by the unexecuted counterparts of the Agreement along with the other Contract Documents as identified in the Agreement. Within 15 days thereafter, Successful Bidder must execute and deliver the required number of counterparts of the Agreement and any bonds and insurance

00200-13

EJCDC® C-200, Instructions to Bidders for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Page 13 of 14 13582B documentation required to be delivered by the Contract Documents to Owner. Within 10 days thereafter, Owner will deliver one fully executed counterpart of the Agreement to Successful Bidder, together with printed and electronic copies of the…