1333ND25QNB190211 AMD 0003 RFIs and WDs.pdf
PDF 8 MB Posted
- Attached to
- NOAA Anderson Ditch Project
- Solicitation number
- 1333ND25QNB190211
About this file
This document is an Amendment (0003) to a federal solicitation for the NOAA Anderson Ditch Project, issued by the National Institute of Standards and Technology. The amendment incorporates three Requests for Information (RFIs) and their corresponding government responses, including details about relocating picnic tables and a memorial plaque, stockpiling trees and mulch outside a 12-foot easement, and badging requirements for project personnel. Additionally, the amendment updates two wage determinations: the Service Wage Determination (2015-5415, Revision 27) and the Construction Wage Determination (20250002, Modification Number 5) for Boulder, Colorado.
The solicitation remains a 100% small business set-aside for NAICS code 237990, with an estimated value of $45.0 Million. The offer due date remains unchanged at July 31, 2025, no later than 2:00 PM Mountain Time. Contractors are advised that both prime and subcontractor personnel must complete a full badging process, with temporary daily badges required until permanent badging is completed. All stockpiled trees and mulch must be fully removed and properly disposed of offsite by the end of the contract's performance period.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NUMBER
IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
Attachment Page
PAGE 2 OF 28 1333ND25QNB1902110003
The purpose of this amendment (0003) is to incorporate requests for information (RFI) and government responses:
A. Incorporate the following received RFIs with the government response to the subject solicitation:
[OFFEROR RFI 06] “Do we need to relocate the picnic tables and memorial?”
[GOV RESPONSE 06] Yes, there are picnic tables and one memorial plaque that need to be relocated. The COR will provide the contractor with the designated relocation area.
[OFFERER RFI 07] “Can they confirm that we are allowed to stockpile trees and mulch on the east side as long as it is outside the 12' easement?”
[GOV RESPONSE 07] The contractor is permitted to stockpile trees and mulch on the east side of the Anderson Ditch, provided the materials are placed outside of the designated 12-foot easement. All stockpiled trees and mulch in this area must be fully removed and properly disposed of offsite by the end of the period of performance.
[OFFEROR RFI 08] “Will we be issued badges? One time so we don’t have to get them on a daily or weekly?”
[GOV RESPONSE 08] Both prime and subcontractor personnel are required to complete the full badging process, which may be time-consuming. Until the permanent badging process is completed, all personnel must obtain temporary badges on a daily basis in order to access the site.
B. Section J List of Attachments, Incorporate revised wage determinations:
REVISE: J.7 Service Wage Determination, incorporate 2015-5415, Revision Number 27, dated July 15, 2025, Boulder, Co
REVISE: J.8 Construction Wage Determination, incorporate 20250002, Modification Number 5, dated July 17, 2025, Heavy, Boulder, Co
C. The Offer Due Date, Block 13.a. of the Standard Form (SF) 1442, remains unchanged at July 31, 2025, no later than 2:00 PM MT.
C. No other changes occur as a result of this amendment.
Table of Contents
SECTION J LIST OF ATTACHMENTS
J.1 Service Wage Determination
J.2 Construction Wage Determination
PAGE 3 OF 28 1333ND25QNB1902110003
SECTION J
LIST OF ATTACHMENTS
J.1 Service Wage Determination
PAGE 4 OF 28 1333ND25QNB1902110003
PAGE 5 OF 28 1333ND25QNB1902110003
PAGE 6 OF 28 1333ND25QNB1902110003
PAGE 7 OF 28 1333ND25QNB1902110003
PAGE 8 OF 28 1333ND25QNB1902110003
PAGE 9 OF 28 1333ND25QNB1902110003
PAGE 10 OF 28 1333ND25QNB1902110003
PAGE 11 OF 28 1333ND25QNB1902110003
PAGE 12 OF 28 1333ND25QNB1902110003
PAGE 13 OF 28 1333ND25QNB1902110003
PAGE 14 OF 28 1333ND25QNB1902110003
PAGE 15 OF 28 1333ND25QNB1902110003
PAGE 16 OF 28 1333ND25QNB1902110003
PAGE 17 OF 28 1333ND25QNB1902110003
J.2 Construction Wage Determination
PAGE 18 OF 28 1333ND25QNB1902110003
PAGE 19 OF 28 1333ND25QNB1902110003
PAGE 20 OF 28 1333ND25QNB1902110003
PAGE 21 OF 28 1333ND25QNB1902110003
PAGE 22 OF 28 1333ND25QNB1902110003
PAGE 23 OF 28 1333ND25QNB1902110003
PAGE 24 OF 28 1333ND25QNB1902110003
PAGE 25 OF 28 1333ND25QNB1902110003
PAGE 26 OF 28 1333ND25QNB1902110003
PAGE 27 OF 28 1333ND25QNB1902110003
PAGE 28 OF 28 1333ND25QNB1902110003
1.2
C:\PERFORM\FORMS\S30.FRP
Forms Management
C:PERFORMFORMSS30.FRP
Acrobat PDFWriter 2.01 for Windows D:19971010095222 D:19990614133004 Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER
3. EFFECTIVE DATE
4. REQUISITION/PURCHASE REQUISITION NUMBER
5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6)
CODE
STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended.
is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY
CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer) Previous edition unusable
| Descript: |
| Descript1: See Attachment Page. |
| AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT: |
| IDCode: |
| pdfpage1: 1 |
| Pages: 28 |
| DocNo: 1333ND25QNB1902110003 |
| EffDate: JUL 24, 2025 |
| ReqNo: NB194000-25-01539 |
| ProjNo: |
| IssuedByCode: 000014 |
| IssuedBy: NATIONAL INST OF STDS AND TECHNOLOGY |
325 BROADWAY
BOULDER CO 80305-3328
| AdminByCode: |
| AdminBy: See Block 6 |
| ContractorCode: |
| FacCode: |
| SolNo: 1333ND25QNB190211 |
| SolDate: JUN 11, 2025 |
| AwdNo: |
| AwdDate: |
| NoCopies: 1 |
| Amended: Yes |
| OffrExt: Off |
| OffrNoEx: No |
| ApprData: See Schedule |
| ChgeOrd: Off |
| ChgeOrder: |
| Modify: Off |
| B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).: |
| SuppAgre: Off |
| SuppAuth: |
| ModOthr: Off |
| OthrSpec: |
| NoReq: Off |
| Require: Off |
| Copies: |
| SignName: |
| SignTitl: |
| ContDate: |
| ContrOfficerInfo: |
| CODate: |
| Contractor Info: |
| ContractorPOC: |
| Contractor: |
| ModAmount: |
| 15B. CONTRACTOR/OFFEROR: |
| signature: |
| AwdChg: Off |
| SolChg: Yes |
| Header: |
| Footer1: |
File details come from the government source that posted it. Updated .