RFQ IFB RFP
WOMEN-OWNED SMALL BUSINESS
(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
1. REQUISITION NUMBER PAGE OF
2. CONTRACT NO. 3. AWARD/EFFECTIVE
DATE
4. ORDER NUMBER 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE
DATE
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME b. TELEPHONE NUMBER (No collect calls)
8. OFFER DUE DATE/
LOCAL TIME
9. ISSUED BY
13b. RATING
14. METHOD OF SOLICITATION
CODE
15. DELIVER TO 16. ADMINISTERED BY CODE
18a. PAYMENT WILL BE MADE BY CODEFACILITY
CODE
CODE
TELEPHONE NO.
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN
OFFER
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK
BELOW IS CHECKED
SEE ADDENDUM
19.
ITEM NO.
20.
SCHEDULE OF SUPPLIES/SERVICES
21.
QUANTITY
22.
UNIT
23.
UNIT PRICE
24.
AMOUNT
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT (For Govt. Use Only)
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED
29. AWARD OF CONTRACT: REF.
DATED . YOUR OFFER ON SOLICITATION
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
30a. SIGNATURE OF OFFEROR/CONTRACTOR
30b. NAME AND TITLE OF SIGNER (Type or print) 30c. DATE SIGNED
31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)
31b. NAME OF CONTRACTING OFFICER (Type or print) 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA - FAR (48 CFR) 53.212
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
OFFER
13a. THIS CONTRACT IS A
RATED ORDER UNDER
DPAS (15 CFR 700)
11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
ARE ARE NOT ATTACHED
ARE ARE NOT ATTACHED
27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA
17a CONTRACTOR/
OFFEROR.
CODE
8 (A)
SIZE STANDARD:
NAICS:
% FOR:SET ASIDE:UNRESTRICTED OR
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
HUBZONE SMALL
BUSINESS
SMALL BUSINESS
10. THIS ACQUISITION IS
EDWOSB
SMALL BUSINESS PROGRAM
STANDARD FORM 1449 (REV. 2/2012) BACK
19.
ITEM NO.
20.
SCHEDULE OF SUPPLIES/SERVICES
21.
QUANTITY
22.
UNIT
23.
UNIT PRICE
24.
AMOUNT
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED:
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
40. PAID BY
32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f. TELPHONE NUMBER OF AUTHORZED GOVERNMENT REPRESENTATIVE
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
33. SHIP NUMBER 34. VOUCHER NUMBER 35. AMOUNT VERIFIED
CORRECT FOR
PARTIAL FINAL
37. CHECK NUMBER
38. S/R ACCOUNT NO. 39. S/R VOUCHER NUMBER
36. PAYMENT
COMPLETE PARTIAL FINAL
Attachment Page
PAGE 3 OF 78 1333ND23QNB190169
Requirement: Diesel Generator In-Skid Day Tank Installation
Enter PRICES IN SECTION B, TYPE OR USE BLACK INK.
The NAICS for this acquisition is 811310; the Small Business Size Standard is $12.5M.
See Clause 1352.270-71 for Site Visit Dates / Times.
See Addendum to 52.212-1 regarding due dates for site visit name submission and questions.
SCHEDULE Continued
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 Provide all labor, materials, equipment, and supplies to install an In-Skid Day Tank in accordance with the Statement of Work.
Period of Performance: 04/10/2023 to 08/08/2023
1.00 EA
PAGE 4 OF 78 1333ND23QNB190169
Table of Contents
Statement of Work
General Requirements
52.204-7 SYSTEM FOR AWARD MANAGEMENT (OCT 2018)
52.204-9 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (JAN 2011)
52.204-13SYSTEM FOR AWARD MANAGEMENT MAINTENANCE (OCT 2018)
52.204-16COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING (AUG 2020)
52.204-18COMMERCIAL AND GOVERNMENT ENTITY CODE MAINTENANCE (AUG 2020)
52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014)
52.204-22 ALTERNATIVE LINE ITEM PROPOSAL (JAN 2017)
52.212-1INSTRUCTIONS TO OFFERORS--COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (NOV 2021)
Addendum to 52.212-1
52.212-4CONTRACT TERMS AND CONDITIONS--COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (DEC 2022)
52.223-2 AFFIRMATIVE PROCUREMENT OF BIOBASED PRODUCTS UNDER SERVICE AND CONSTRUCTION CONTRACTS (SEP
2013)
52.223-5 POLLUTION PREVENTION AND RIGHT-TO-KNOW INFORMATION (MAY 2011)
52.223-6 DRUG-FREE WORKPLACE (MAY 2001)
52.223-17 AFFIRMATIVE PROCUREMENT OF EPA-DESIGNATED ITEMS IN SERVICE AND CONSTRUCTION CONTRACTS (AUG
2018)
52.232-40PROVIDING ACCELERATED PAYMENTS TO SMALL BUSINESS SUBCONTRACTORS (NOV 2021)
52.237-2 PROTECTION OF GOVERNMENT BUILDINGS, EQUIPMENT, AND VEGETATION (APR 1984)
1352.201-70 CONTRACTING OFFICER?s AUTHORITY (APR 2010)
1352.209-73 COMPLIANCE WITH THE LAWS (APR 2010)
1352.209-74 ORGANIZATIONAL CONFLICT OF INTEREST (APR 2010)
52.204-24REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT
(NOV 2021)
52.212-2EVALUATION--COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (NOV 2021)
Addendum 52.212-2
52.212-3OFFEROR REPRESENTATIONS AND CERTIFICATIONS--COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (DEC
2022)
52.212-5CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR EXECUTIVE ORDERS--COMMERCIAL
PRODUCTS AND COMMERCIAL SERVICES (DEC 2022)
52.217-8 OPTION TO EXTEND SERVICES (NOV 1999)
52.222-42 STATEMENT OF EQUIVALENT RATES FOR FEDERAL HIRES (MAY 2014)
52.222-55MINIMUM WAGES FOR CONTRACTOR WORKERS UNDER EXECUTIVE ORDER 14026. (JAN 2022)
52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
1352.201-72 CONTRACTING OFFICER`S REPRESENTATIVE (COR) (APR 2010)
1352.223-99ENSURING ADEQUATE COVID-19 SAFETY PROTOCOLS FOR FEDERAL CONTRACTORS (OCT 2021) (DEVIATION).62
1352.237-71 SECURITY PROCESSING REQUIREMENTS - LOW RISK CONTRACTS (APR 2010)
1352.242-70 POSTAWARD CONFERENCE (APR 2010)
1352.246-70 PLACE OF ACCEPTANCE (APR 2010)
1352.270-70 PERIOD OF PERFORMANCE (APR 2010)
1352.270-71 PRE-BID / PRE-PROPOSAL CONFERENCE AND SITE VISIT (APR 2010)
NIST LOCAL-33U.S. DEPARTMENT OF LABOR WAGE DETERMINATION
NIST LOCAL-53CONTRACT PERFORMANCE DURING CHANGES IN NIST OPERATING STATUS
NIST LOCAL-54ELECTRONIC BILLING INSTRUCTIONS
NIST LOCAL-56INVOICING PROCESSING PLATFORM-ALTERNATE I (DEC 2022)
Wage Determination 2015-5421
PAGE 5 OF 78 1333ND23QNB190169
CLAUSES
Statement of Work
PAGE 6 OF 78 1333ND23QNB190169
STATEMENT OF WORK for:
Diesel Generator In-Skid Day Tank Installation
NATIONAL INSTITUTE OF STANDARDS & TECHNOLOGY
United States Department of Commerce
325 Broadway
Boulder, CO 80305 January 15, 2021
1.1 DESCRIPTION
Perform an In-Skid Day Tank installation for Onan Generator Model# DQDAA serial# 16533549K (EMG-W-019). Provide all labor, equipment, and materials to restore generator to Original Equipment Manufacturer (OEM) specifications in reference to fuel delivery system. This is to ensure compliance with current standards on the National Institute of Standards and Technology (NIST) located in Fort Collins, CO, cited here in this document. The work is to be performed in accordance with this Statement of Work (SOW).
1.2 PURPOSE
The purpose of this project is to install an In-Skid Diesel Generator Day Tank for EMG-W-019 generator to be restored to working order per OEM specifications in reference to fuel delivery system.
Install electrical power and controls to the In-Skid Day Tank, electrical solenoid anti-siphon valve, dual fuel transfer pump to Generator Set.
The work will be described in detail in the following section 1.4, “Summary of the Work” and must be code compliant as described in section 1.5 “Reference Standards,” safe, accessible, and easily maintainable.
The contractor is responsible for the following:
• Performing the work as described in this SOW.
• Performing a site walk prior to the start of work to fully understand the work required and the local conditions.
• Perform the work in accordance with 40 CFR 112.8 (SPCC), including chemical compatibility and secondary containment, Chapter 57 of the International Fire Code (IFC, UL listing (142 at minimum).
• Preparing and following a site-specific safety plan to be reviewed and accepted by NIST Safety Staff.
• Performing a daily Job Hazards Analysis (JHA).
• Coordinating all work with the Contracting Officer’s Representative (COR).
• Commission In-Skid Day Tank, electrical solenoid, and dual pump.
1.3 SPECIAL REQUIREMENTS
• Pre-proposal site visit is recommended.
• Contractor to verify all measurements and sizing in the field.
• Weekly progress meetings required when work is ongoing on site.
• Post award meeting required.
PAGE 7 OF 78 1333ND23QNB190169
• All documentation available from the original pump installation project will be provided.
1.4 SUMMARY OF THE WORK
A. General
1. Installation shall include, but is not limited to the following:
2. Provide all labor, install materials, equipment, and supplies in accordance with the SOW.
3. This project must be completed 120 calendar days after award. Provide to the COR for acceptance, detailed project schedules with the initial quote and prior to commencement of work. Final schedule shall be agreed upon after NTP at post-award meeting. Post-award meeting shall be held not later than 10 days after award.
4. Provide field supervision throughout the project duration.
5. Contractor must be familiar with the work required and local conditions affecting the work.
6. Ensure that the safety of the project is a top priority. Submit a site-specific safety plan with project proposal prior to commencement of work to the COR for acceptance.
7. Ensure due diligence and timely delivery of the project.
8. Correct errors and deficiencies in the services provided.
9. Cooperate with NIST Police and Security regarding site security. Contractor is responsible for ensuring its personnel meet all site access requirements. Provide a list of all anticipated employees at least two weeks in advance of their arrival. All employees must fill out specified background check forms for review by NIST Security before security badges will be issued. Return all security badges to NIST upon project completion.
10. Maintain a record set of all inspections, or other authorizations necessary for the work to proceed.
11. If “Hot Work” will be performed the Contractor must pull a hot work permit through the COR twenty-four (24) hours in advance of beginning associated work.
12. An “Impairment Permit” is required when project work produces Smoke; Sparks; Steam; Flames;
Fumes; and/or Dust; or other particulates within the buildings when working around fire detection devices. The Contractor must pull a permit through the COR twenty-four (24) hours in advance of beginning associated work.
13. Notify the COR of the work progress and any required inspections twenty-four (24) hours in advance of all inspections.
14. The contractor is responsible for correcting any damage caused to the NIST Boulder site and field sites as a result of their construction work and returning the site to previous conditions at no cost to the Government.
15. The Contractor shall perform final cleaning and detailing of work areas.
16. Upon substantial completion, notify the COR for the performance of a punch list inspection.
Submit a written list of items requiring completion or correction accompanied by an anticipated schedule.
17. Contractor is responsible for determining order of work.
18. See COR for any conflicts associated with this Statement of Work, specifications, drawings, attachments, and appendixes.
19. Demobilize all elements of the Project.
B. Commission of in-skid day tank, electronic solenoid anti-siphon valve, and fuel transfer pump Installation
1. Perform Fuel leak checks on In-skid day tank, electronic solenoid anti-siphon valve, dual fuel transfer pump and fuel hoses. Document results for inclusion in commissioning report.
2. Perform troubleshooting of day tank installation, electronic solenoid anti-siphon valve, dual fuel transfer pump and fuel hoses per OEM specifications manual. Document results for inclusion in commissioning report.
PAGE 8 OF 78 1333ND23QNB190169
3. Commission the new in-skid day tank and all ancillary equipment installed per OEM instruction and recommendations.
4. Provide a report of all commissioning and testing of equipment.
5. Submit the operation and maintenance manuals on all equipment installed, for approval 15 days prior to scheduled training of government personnel, include the 15 days of government review in project schedules.
6. Provide up to four hours of training for government personnel on the operations of the day tank, electronic solenoid anti-siphon valve, dual fuel transfer pump system, include training in project schedules
7. Perform Load Bank of the Generator to check for proper operation
C. The project is to be performed on the NIST Radio Station WWV campus site in Fort Collins, CO.
D. In-Skid Day Tank Installation
a. NIST Equipment Number EMG-W-019 Radio Station WWV Emergency Generator, Onan
Power Generation, Model # 250DQDAA-1653549 K, Serial # K160121956, 3 Phase
277/480VAC.
1) Contractor shall install a 50-gallon Double Wall Steel In-Skid Day Tank with dual fuel transfer pump.
2) Contractor shall install solenoid actuated anti-siphon valve on 1,000 gallon Above Ground
Storage Tank (AST) outside the building.
3) Contractor shall install all necessary fuel fittings and fuel piping for supply and return lines per OEM specifications. Fuel supply lines should be sized to not exceed more than 16 inches of mercury as measured at the pump inlet manifold.
4) Contractor shall install all electrical wiring and control box for integration of In-Skid Day tank, fuel transfer pump and solenoid actuated anti-siphon valve to generator
5) Contractor shall install In-Skid Day tank in accordance with 40 CFR 112.8 (SPCC), including chemical compatibility and secondary containment, Chapter 57 of the International Fire Code (IFC, UL listing (142 at minimum).
6) Contractor shall arrange the In-Skid Day tank so that the highest level does not exceed the maximum height above the fuel injectors specified for the engine. The lowest level should be no less than 6 inches above the engine fuel pump inlet.
7) Contractor shall locate the in-skid day tank as close as possible to the generator set per OEM Specifications but leave room to accommodate inspections and maintenance of day tank.
8) Contractor shall provide a one-year warranty for parts and workmanship for new in-skid day tank and all ancillary equipment installed.
1.5 REFERENCE STANDARDS
A. The Contractor shall without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State, and municipal laws, codes, and regulations applicable to the performance of the work. The Contractor shall also be responsible for all damages to persons or property that occur as a result of the Contractor’s fault or negligence. The Contractor shall also be responsible for all materials delivered and work performed until completion and acceptance of the entire work, except for any completed unit of work which may have been accepted under the contract.
PAGE 9 OF 78 1333ND23QNB190169
1.6 DELIVERABLE SCHEDULE
A. Submittals are due to the CO/COR per this SOW. If no timeframe for delivery is listed, the contractor shall deliver submittals in a timely fashion to enable the completion of the scope of work before the contract end date. Provide a minimum of two weeks for government review of submittals. Resubmittal of disapproved submittals shall be returned by the date(s) marked on the NIST Material Submittal Form.
B. The NIST Material Submittal Form is included as attachment 15.
C. LIST OF DELIVERABLES
TASK SOW PARAGRAPH
REFERENCE
DELIVERY DUE
DATE
DELIVER TO WHO
TENTATIVE
SCHEDULE
1.4.A.3 WITH INITIAL
PROPOSAL
CO
FINAL SCHEDULE 1.4.A.3 10 DAYS AFTER
PROJECT AWARDED
COR
SITE SPECIFIC
SAFETY PLAN
PER GENERAL
INSTRUCTIONS
10 DAYS AFTER
PROJECT AWARDED
COR
DAILY JHA’S PER GENERAL
INSTRUCTIONS
DAILY WHEN
CONSTRUCTION
BEGINS ON SITE
NIST SAFETY
REPRESENTATIVE
AND COR
DAY TANK AND
ANCILLARY
EQUIPMENT
1.4.D.1 TO 1.4.D.5 15 DAYS BEFORE
SCHEDULED
PROCUREMENT
CO/COR
DAY TANK AND
EQUIPMENT LAYOUT
1.4.D.7 15 DAYS BEFORE
SCHEDULED
PROCUREMENT
CO/COR
OPERATION AND
MAINTENACE
MANUALS
1.4.B.5 PROJECT END DATE CO/COR
COMMISSIONING
REPORT
1.4.B.4 PROJECT END DATE CO/COR
WARRANTY
INFORMATION
1.4.D.8 PROJECT END DATE CO/COR
PAGE 10 OF 78 1333ND23QNB190169
GOVERNMENT
PERSONNEL
TRAINING
1.4.B.6 AS SCHEDULED COR
General Requirements
PAGE 11 OF 78 1333ND23QNB190169
General Instructions for Conducting Work at the NIST Boulder Campus
OFPM Rev. C 3-30-2020
Contents Part 1: GENERAL
1.1 INTRODUCTION:
1.2 BACKGROUND
1.3 HOURS OF OPERATION
1.4 UNFORESEEN FACILITY CLOSURES
1.5 SANITARY FACILITIES
1.6 EQUIPMENT AND MATERIAL STORAGE
1.7 ELECTRICITY AND WATER
1.8 TELEPHONE
1.9 ROADS
1.10 PARKING
1.11 CONTRACTOR’S USE OF PREMISES
PART 2: SAFETY
2.1 OCCUPATIONAL HEALTH AND SAFETY
2.2 CODES, ORDINANCES, REGULATIONS
2.3 RESPONSIBILITY AND LIABILITY
2.4 PRE-CONSTRUCTION/SAFETY MEETING
2.5 SAFETY INSPECTIONS
2.6 INCIDENTS ON THE JOB
2.8 PROPER WASTE DISPOSAL
2.9 STORM WATER PROTECTION/COMPLIANCE
2.10 FIRE PREVENTION/PROTECTION
2.11 EMERGENCY RESPONSE PROCEDURES FOR THE UNSCHEDULED MINOR DISTURBANCES OF ASBESTOS-CONTAINING
MATERIAL (ACM)
PART 3: PERSONAL/PHYSICAL SECURITY & PROPRIETARY INFORMATION
3.1 GENERAL
3.2 CONTRACTOR’S SECURITY POINT OF INTEREST
3.3 PERSONAL SECURITY & EMPLOYEE IDENTIFICATION
PART 4: PROJECT PROCEDURES
4.1 GENERAL DESCRIPTION
4.2 PROJECT DOCUMENTATION PROCEDURES
4.3 PERMIT REQUIRED OPERATIONS DURING CONSTRUCTION OR MAINTENANCE ACTIVITIES
PAGE 12 OF 78 1333ND23QNB190169
4.4 MAINTENANCE OF WORK SITE
4.5 WORK REQUIRING ADVANCE NOTICE AND COORDINATION
Appendix
Roof Access Permit
Penetration Permit
Hot Work Permit
Fire Protection System Impairment
Excavation Permit
PAGE 13 OF 78 1333ND23QNB190169
Part 1: GENERAL
1.1 INTRODUCTION:
1. This document is intended to provide the necessary information/requirements for all contractors performing work at
Department of Commerce (DOC) facilities. It is understood all information in this document may not apply for the specific project described in the Statement of Work; however, it is the responsibility of the contractor to ensure the requirements are met when applicable.
2. Specifics of the activities are described in the attached Statement of Work and supporting documentation.
3. Questions about the requirements can be addressed to the Contracting Officer (CO) and Contracting Officers Representative
(COR)/Project Manager designated for the specific task order.
1.2 BACKGROUND
The Office of Facilities and Property Management (OFPM) Division manages and provides services to the DOC staff in support of their research, technical, and administrative programs. DOC agencies serviced by OFPM include but may not be limited to: The National Oceanic and Atmospheric Administration (NOAA), The National Telecommunications and Information Administration (NTIA), and The National Institute of Standards and Technology (NIST).
1.3 HOURS OF OPERATION
1. DOC hours of operations are from 7:00 AM to 5:00 PM, Monday through Friday, on normal Federal workdays. Should the
Contractor desire to work at times other than those specified above, the dates and hours must be scheduled at least 10 working days in advance and approved in writing by the Contracting Officer’s Representative (COR).
2. Use the Main Entrance at the DOC site for materials supply and entry for:
a. Special arrangements may be made through the COR for delivery of material/supplies, and/or overtime beyond these hours or on holidays.
b. Check-in required at DOC Visitor’s Center located at the site main entrance.
3. Employee identification shall include the name, country of citizenship, employer, and green card (if applicable) is needed for each Contractor and Subcontractor's employee working on the DOC site. These shall be submitted to the COR for review 10 days prior to the work date. After hours work will require a hard badge from the General Contractor and a COR/Federal escort 100 percent of time if accessing DOC buildings (see section 3.3). Follow the specific procedures pertaining to security and work hours prescribed by the COR/Security. Contractor vehicles must show current registration and proof of insurance.
4. Department of Homeland Security (DHS) Advisory System:
Note: The following paragraphs describe the threat levels that may be changes at any time due to national security issues. If a change is issued by the DHS all changes in procedures/directions for entering and performing work at the site will be communicated to the contractor through the COR. Contractor’s access to the DOC campus grounds may occasionally be restricted as a result of a change in the Nation’s Threat Level when publicly announced by DHS.
5. National Terrorism Advisory System (NTAS)
a. The National Terrorism Advisory System, or NTAS, replaces the color-coded Homeland Security Advisory System (HSAS).
This new system will more effectively communicate information about terrorist threats by providing timely, detailed information to the public, government agencies, first responders, airports and other transportation hubs, and the private sector.
b. It recognizes that Americans all share responsibility for the nation’s security and should always be aware of the heightened risk of terrorist attack in the United States and what they should do.
6. NTAS Alerts
a. After reviewing the available information, the Secretary of Homeland Security will decide, in coordination with other
Federal entities, whether an NTAS Alert should be issued.
PAGE 14 OF 78 1333ND23QNB190169
b. NTAS Alerts will only be issued when credible information is available.
c. These alerts will include a clear statement that there is an imminent threat or elevated threat. Using available information, the alerts will provide a concise summary of the potential threat, information about actions being taken to ensure public safety, and recommended steps that individuals, communities, businesses and governments can take to help prevent, mitigate or respond to the threat.
d. The NTAS Alerts will be based on the nature of the threat: in some cases, alerts will be sent directly to law enforcement or affected areas of the private sector, while in others, alerts will be issued more broadly to the American people through both official and media channels.
e. NTAS Alerts contain a sunset provision indicating a specific date when the alert expires - there will not be a constant NTAS Alert or blanket warning that there is an overarching threat. If threat information changes for an alert, the Secretary of Homeland Security may announce an updated NTAS Alert. All changes, including the announcement that cancels an NTAS Alert, will be distributed the same way as the original alert.
f. Contractor coordinates procedures with COR.
g. Threat Levels:
i. Low Condition (Green): A Low Condition is declared when there is a low risk of terrorist attacks.
1. Federal departments and agencies will implement general and agency-specific Protective Measures to assure that all facilities and regulated sectors take reasonable measures to mitigate vulnerabilities to terrorist attack.
2. Contractor coordinates procedures with COR.
ii. Guarded Condition (Blue): A Guarded Condition is declared when there is a general risk of terrorist attacks.
1. In addition to Protective Measures taken in previous Threat Condition, Federal departments and agencies will implement general measures in addition to agency-specific Protective Measures to check communications with designated emergency response or command locations, update emergency response measures, and provide public with information.
2. Contractor coordinates procedures with COR.
iii. Elevated Condition (Yellow). An Elevated Condition is declared when there is a significant risk of terrorist attacks.
1. In addition to Protective Measures taken in previous Threat Conditions, Federal departments and agencies may develop protective measures for the DOC campus grounds such as increased surveillance, coordinating emergency plans as appropriate with nearby jurisdictions, and implementing contingency and emergency response plans.
2. Contractor coordinates procedures with COR.
iv. High Condition (Orange): A High Condition is declared when there is a high risk of terrorist attacks.
1. In addition to Protective Measures taken in previous Threat Conditions, Federal departments and agencies will implement general and agency-specific Protective Measures for the DOC campus grounds.
2. At this Threat Level the Government may restrict access to site and facility to essential personnel only.
3. Contractor coordinates procedures with COR.
v. Severe Condition (Red). A Severe Condition reflects a severe risk of terrorist attacks.
1. Under most circumstances, the Protective Measures for a Severe Condition are not intended to be sustained for substantial periods of time. In addition to Protective Measures for previous Threat Conditions, Federal departments and agencies may close Public and Government sites and facilities as a protective measure.
2. Contractor coordinates procedures with COR.
1.4 UNFORESEEN FACILITY CLOSURES
1. When an unforeseen facility closure occurs, the Contractor will either reschedule the work or perform the work on the next regularly scheduled workday. If the facility is closed, the contractor is not to be on-site unless notified by the contracting officer they are essential. Contractor personnel may be required by the COR to remain on site to handle problems as a result of a closure, e.g., severe weather, national emergency, changes in national security levels.
2. Information about the status of the site may be obtained by calling the switch board at 303-497-3000. Usually the day’s site status is available by 6 AM MST. Contractor can verify site status and sign up for email and text site notifications at the following website:
http://www.boulder.doc.gov/cgi-bin/docstatus.cgi
1.5 SANITARY FACILITIES
PAGE 15 OF 78 1333ND23QNB190169
Toilet rooms in existing buildings may be used by the Contractor when performing work inside DOC owned buildings at the discretion of the COR. When toilet rooms in existing buildings are not available or work is being conducted outside the Contractor shall:
1. Provide temporary toilet facilities for use of all workmen.
2. Provide the COR with keys to all temporary structures.
3. Maintain toilet facilities in a clean, sanitary condition.
4. Provide adequate supplies of toilet paper, cleaning and other required items.
a. Holding tanks for the collection of sanitary waste will not be permitted.
b. Contractor shall install all pipes serving these trailers underground with appropriate cleanouts and provide measures to prevent them from freezing.
c. Piping shall be run in an organized and pre-planned fashion and all piping shall be removed from the DOC campus upon demobilization of the Construction trailer(s) and the sewer main piping shall be restored to its original condition.
1.6 EQUIPMENT AND MATERIAL STORAGE
1. The contractor shall provide and store, in an area designated by the COR, all equipment, materials and required to complete the project. The materials are required to be kept undamaged, clean and dry throughout the duration of the project. The contractor shall also coordinate location of any trash receptacles, if necessary, with the COR and shall keep the construction area free of trash and debris. All equipment, materials and garbage shall be kept in a manner to avoid causing a hazard by accidental shifting, ignition or other hazardous qualities.
2. Prior to the start of work, Contractor shall meet with all Subcontractors to arrange and prepare a plot plan defining staging, storage, field office and traffic areas within lay-down/staging and trailer/parking areas designated.
a. Submit a plan for COR's approval not less than 10 working days prior to the installation of temporary facilities.
b. Except as specifically provided, working and storing outside these areas will not be permitted.
c. Arrange and locate temporary structures and storage to avoid interfering with construction.
3. Within the area designated for its use, provide suitable and sufficient enclosed and covered spaces with raised flooring, to protect materials and equipment from damage by weather, construction work, or other hazards.
a. Maintain storage and working areas in clean and orderly condition.
b. Tie down canvas and other coverings sufficiently to be maintained in conditions of high winds.
c. At completion of contract, contractor shall remove all storage areas and return any disturbed areas to original condition or better.
1.7 ELECTRICITY AND WATER
1. DOC may make available, at no cost to the contractor, electricity and water during the course of this project. The contractor is responsible for making connections to the existing systems. (see FAR 52.236-14, Availably and Use of Utility Services)
2. Electricity: Temporary electrical work shall meet the requirements of NFPA 70-1996 (NEC), Article 305.
a. Temporary electrical service shall be provided from existing campus power distribution system.
i. If the contractor chooses to use Governments electrical service, then the Contractor is responsible for connection, installation, and maintenance of all portions of the temporary electrical service, and connected equipment.
ii. Verify connection location with COR.
b. Make arrangements for all equipment, poles, meter, wiring, switches, outlets, etc., for all lighting and power requirements for construction purposes.
i. Permanent existing campus power distribution system may be used.
ii. Remove all temporary electrical equipment, when no longer needed.
iii. Immediately preceding completion, remove and replace all damaged parts of permanent systems.
c. Temporary electrical power derived from existing site distribution system will be paid for by the Government. Any other power generation shall be paid for by Contractor.
i. The use of resistive heating devices is prohibited.
ii. Turn off all lighting and/or equipment not in use.
PAGE 16 OF 78 1333ND23QNB190169
d. Extend warranty or guarantee period on permanent systems used during construction period so they commence on date of Acceptance.
e. Provide UL approved extension cords where necessary.
f. Contractor to submit after hours lighting plan to COR for approval at least 10 working days prior to installation and use.
g. Provide temporary electrical systems which meet Government approval.
h. Contractor shall remove same from the DOC campus at such time as temporary lighting is no longer required.
3. Water:
a. During construction/renovation/and maintenance projects the contractor, with the consent/approval of the COR, shall:
i. Make all arrangements; install equipment, backflow preventer, piping, and outlets for an adequate supply of clean water for construction purposes.
ii. Existing water lines may be used for temporary service.
1. Contractor shall tie into existing domestic water line at a location designated and approved by COR, and shall provide all materials, labor and equipment necessary for the connection of all trailers requiring a domestic water connection.
b. Contractor shall install all pipes serving these trailers underground with appropriate shut-off valves for isolation of each branch connection and shall provide measures to prevent them from freezing.
c. Piping shall be run in an organized and pre-planned fashion and all piping shall be removed from the DOC campus upon demobilization, and the domestic water main piping shall be restored to its original condition.
1.8 TELEPHONE
Telephone service is not normally available on-site for the Contractor’s use.
1.9 ROADS
1. Do not block access to existing facilities.
2. Under no circumstances will egresses be blocked. Any changes in egress shall be approved by COR.
3. Any road closures, full or partial, require notification and approval of COR a minimum of 10 working days prior to closure.
4. Contractor shall be required to remove dirt or debris from road surfaces that are a direct result of contractor operations.
1.10 PARKING
1. Personnel performing the work shall not park in any Government parking lot without prior express consent of COR.
2. Contractor acknowledges that any personnel violating this requirement do so at their own risk and will inform personnel that vehicles may be towed at their expense.
3. Parking in residential and other areas in immediate vicinity of Project site is prohibited.
4. Contractor to keep all personnel, vehicles and operations on Project site within designated limits.
5. If authorized by the COR, temporary parking areas shall be surfaced with crushed stone and maintained by the Contractor to prevent deterioration (ruts, mud, etc.) as approved by the COR.
a. Direct personnel performing the work to use access to site designated by COR.
b. The Contractor shall provide parking and transportation for Contractor personnel off the Project site if designated onsite parking areas are inadequate for Contractor needs.
1.11 CONTRACTOR’S USE OF PREMISES
1. Contractor must coordinate all field investigations with COR prior to accessing ceiling/interstitial spaces. Fire alarm system may need to be impaired.
PAGE 17 OF 78 1333ND23QNB190169
2. Leave undisturbed as much of the site as practical.
a. Land disturbed but not designated for disturbance on the drawings or by the Government shall be restored to its original condition at Contractor's cost. (See FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities and Improvements).
b. Leave root zones of trees undisturbed.
c.
3. Provide warranty and/or guarantee on permanent items and systems used during construction, commencing on date of acceptance, for specified duration(s). (See FAR 52.246-21, Warranty of Construction)
4. Contractor acknowledges that there is wildlife on the Project site. Take all necessary measures to ensure that all such wildlife is protected from execution of the work. Prohibit hunting of any sort.
5. Investigation Equipment: Site investigations and field work may require the use of a stepladder and/or other investigative equipment (measuring tapes, flashlights, screwdrivers, etc.). Contractors shall provide their own stepladders and/or investigative equipment. The stepladders shall be Type 1 (industrial) or Type II (commercial).
6. Operating Equipment: Do not turn off or adjust any equipment without prior authorization from the COR. Work carefully around rotating equipment. Loosely fitting clothes (neckties, dangling jewelry, etc.) shall not be worn when near rotating equipment. Long hair shall be secured. Some equipment may start automatically. Take care when working around this equipment. (NOTE: It may become necessary to implement appropriate lock-out, tag-out procedures to control hazardous energy sources to ensure that personnel do not activate equipment during investigation, servicing, or maintenance).
7. Mechanical/Electrical Rooms: Obtain authorization from the COR prior to working in electrical and/or mechanical rooms.
Lock rooms after use. Do not operate any valves, switches, or breakers without prior approval from the COR. Adhere to all OSHA Lock-Out, Tag-Out Regulations (29 CFR 1910.147).
8. It is the prime contractor’s responsibility to ensure Contractor employees and Subcontractors become familiar with and obey all DOC site regulations, including fire, traffic, and security regulations. All personnel employed on the site shall keep within the limits of the work (and avenues of ingress and egress) and shall not enter any restricted areas unless required to do so and are cleared for such entry. The Contractor's vehicles and equipment shall be conspicuously marked for identification.
PART 2: SAFETY
2.1 OCCUPATIONAL HEALTH AND SAFETY
1. Contractor(s) acknowledges that by working at the National Institute of Standards and Technology (NIST), a Federal
Government facility located in Boulder, Colorado, they are subject to the jurisdiction of the U.S. Department of Labor's Occupational Safety and Health Administration (OSHA). The Regional Office has authority to assign a Compliance Safety and Health Officer (CSHO) to conduct safety and health inspections regarding the Contractors operations at the NIST Boulder site. In addition to OSHA oversight, the Contractor is required to follow NIST health and safety instructions and the Office of Facilities and Property Management (OFPM) safety policies and procedures applicable to their operations.
2. CITATIONS AND NOTICE OF PENALTY FOR NONCOMPLIANCE WITH OSHA STANDARDS
a. To protect NIST’s interests, the Contractor acknowledges that NIST may conduct periodic safety, health and environmental inspections to assure that staff and property are not at risk of injury or damage; also, from Citations issued by OSHA for multi-employer worksites.
b. The Contractor is required to implement and manage a job specific Safety, Health and Environmental plan. NIST will review and evaluate the Contractor’s Safety, Health and Environmental plan to assure that it is site specific for the work being performed. The Safety Plan Requirements Checklist in Appendix A requires a site and job specific plan to be developed and submitted to the government for review and acceptance. No site work may be started until the Site- Specific Safety Plan is accepted. 2. In the event of an onsite emergency, first call 303-497-7777 or 7777 from a campus phone; and then call 911. The Contractor will report the following details: Location (NIST), name, building name or number, room number, and a brief description of the emergency.
PAGE 18 OF 78 1333ND23QNB190169
2.2 CODES, ORDINANCES, REGULATIONS
Contractors are required to comply with all applicable codes, ordinances and regulations as stated in this document. Contractor to use version below, or most current version adopted by Boulder with amendments in effect on the date of the solicitation.)
These include, but may not be limited to:
1. Code of Federal Regulations (CFR):
a. OSHA General Industry Safety and Health Standards (29 CFR 1910);
b. OSHA Construction Industry Standards (29 CFR 1926);
c. National Emission Standards for Hazardous Air Pollutants (40 CFR 61);
d. Resource Conservation and Recovery Act standards for hazardous waste disposal (40 CFR 260-281); and
e. Toxic Substance Control Act rules related to asbestos and PCB’s (40 CFR Part 761).
2. National Fire Protection Association (NFPA):
a. NFPA 30 – Flammable and Combustible Liquids Code;
b. NFPA 101 – Life Safety Code;
c. NFPA 45 – Fire Protection for Laboratories using Chemicals;
d. NFPA 54 – National Fuel Gas Code; and
e. NFPA 70 – National Electrical Code.
3. Life Accessibility Standards (USFAS).
4. American National Standards Institute (ANSI) A117.1 – American National Standard Specifications for Making Buildings and Facilities Accessible and useable by the physically handicapped, latest edition.
5. Colorado Department of Public Health and Environment Regulations, Chapter 8.
6. State of Colorado Hazardous Waste Regulations 6 CCR 1007-3
7. Industrial Discharge Permit (2010-1)
8. Municipal Separate Storm Sewer System (MS4) Permit COR042002
9. Construction Permit (Air Pollutant Emissions) 09BO0159
10. Air Quality Control Commission regulation; Number 3, 5 CCR 1001-5
11. NIST ESO Site Security Specifications
12. International Building Code – IBC 2012
13. International Energy Conservation Code – IECC 2012
14. International Fuel Gas Code – IFGC 2012
15. International Mechanical Code – IMC 2012
16. International Fire Code – IFC 2012
17. International Plumbing Code – IPC 2012
18. International Electric Code Administrative Provisions – IEC 2012
19. US Department of Energy Regulations – 10 CFR 435
20. US Environmental Protection Agency Regulations – 40 CFR
21. State of Colorado Department of Public Health & Environment Regulations for Air Quality Control of Stationary Sources
22. State of Colorado Department of Labor and Employment Division of Oil & Public Safety – C.R.S. § 9-4-101
23. U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1 (applies to fall protection only)
2.3 RESPONSIBILITY AND LIABILITY
1. The Contractor is to comply with all applicable regulations pertaining to the health and safety of their personnel and subcontractor personnel during the execution of the project. The Contractor will hold the Government harmless from any liability for any action incurred during the execution of the project by their personnel and subcontractor personnel, which results in property damage, illness, injury and/or death.
2. The Contractor is responsible for locating all underground and building utilities prior to starting work. Contractor is to stop excavation and notify COR immediately if any unexpected materials, such as utilities or concrete are encountered underground.
PAGE 19 OF 78 1333ND23QNB190169
3. Contractor is responsible for locating all utilities 18" either side of the marked utility and shall manually locate any utility prior to mechanical excavation. If identified utilities are not located within the 36" area, the contractor shall notify the COR immediately.
4. The Contractor is responsible for confirming all dimensions and locations in the field.
2.4 PRE-CONSTRUCTION/SAFETY MEETING
The Contractor may be required to participate in a Preconstruction Conference (see FAR 52.236-26) prior to the start of work for the purpose of reviewing NIST and OFPM site safety regulations, policies and procedures; and to discuss contractual requirements. The Contractor will submit a copy of their Site-Specific Safety Plan to the Contracting Officers Representative (COR) prior to the scheduled Pre-Construction meeting for review, comment, and approval. NTP will not be issued until Site- Specific Safety Plan is approved.
2.5 SAFETY INSPECTIONS
1. The Government will conduct safety inspections of work performed by the Contractor. Unsafe conditions and/or practices by the Contractor will be brought to their attention for correction. The COR or Contracting Officers Safety Representative (COSR) has the authority to “STOP WORK” until the unsafe site or unsafe condition is deemed safe by the COR or COSR and then work can continue. If the Contractor is in non-compliance with safety rules and regulations the COR/COSR will notify the Contractor’s site superintendent/safety point of contact verbally and in writing for immediate corrective action.
Immediate corrective action is required, and a written report of corrective action(s) taken is required to be returned to the
COR/COSR.
2. If Contractor personnel are removed from the project as the result of unsafe actions or conduct the Government may, at any time, require a meeting with the Contractor’s management and safety personnel to discuss corrective actions.
2.6 INCIDENTS ON THE JOB
1. The Contractor is responsible for keeping the Government informed of all incidents during the execution of the project. If an on-the-job incident occurs during the execution of a project at the NIST Boulder site, the Contractor shall immediately notify the COR by phone and will submit a preliminary incident report to the COR no later than two (2) calendar days after the incident occurred. The incident report shall contain date of incident, type of incident (injury, fire, property damage, spill, etc.), a brief description of the accident, the cause of the incident, lessons learned, and corrective actions taken to prevent it from reoccurring. The contractor shall submit a final report including all the information listed above as well as any additional information as required by the CO and/or COR within seven (7) calendar days after the incident occurred.
2. The contractor is responsible for correcting any damage caused to the NIST Boulder site and field sites as a result of their construction work and returning the site to previous conditions at no cost to the Government.
3. A written report summarizing incidents for the previous month will be sent to NIST via email not later than the 5th working day of the month. The report must contain the following information:
a. NAICS Code
b. Total number of man-hours worked in the month
c. Injury and illness experience for the month
d. Near miss incidents for the month
e. Fire or property damage incidents
4. If deemed necessary, the Government reserves the right to conduct a full investigation of all Contractor operations associated with the incident(s).
2.8 PROPER WASTE DISPOSAL
1. The Contractor will remove all materials that are not an integral part of the project, including paint, chemicals and debris in accordance with all applicable Federal, State, and/or Municipal laws, regulations, or requirements. Materials will not be
PAGE 20 OF 78 1333ND23QNB190169
disposed of by flushing them into a drainage system. When hazardous materials from the performance of this contract are disposed of off-site, submit copies of permits from applicable Federal, State, or Municipal authorities, manifests and/or certificates-of-destruction to demonstrate that the material has been disposed as per all applicable regulations.
2. The contractor will coordinate the location of the any dumpsters provided by the contractor for the removal of waste during the project with the COR while developing the staging plan.
3. If dumpster is to be located within 100 ft of a building, the contractor is required to secure all dumpster openings with covers and locks. This shall be part of the staging plan submittal to be reviewed by NIST Security and approved by COR.
2.9 STORM WATER PROTECTION/COMPLIANCE
1. Contractors are responsible for cleanup of sediment that erodes from a job site and may be held financially responsible for removal of sedimentation from streams or storm drains.
2. Contractors must protect streams, ditches, basins, drainage swales and other water bodies from deposition of sediment from sites on which they are working.
3. Soil may not be stockpiled on paved surfaces without using best management practices such as first laying down plastic and placing straw barriers on the down gradient side of the stockpile.
4. Disturbed soil must be stabilized after 14 days have passed without work being performed in that location. Temporary stabilization is acceptable for sites that are intermittently worked.
5. Soil piles remaining after completion of work must be removed before the contractor leaves the site or within 14 days of completing work whichever is earlier.
6. All disturbed soil must be stabilized before work will be accepted as complete. Ineffective stabilization (does not prevent erosion) must be replaced.
7. Stabilization work may be delayed if the soil is frozen or covered with snow/ice.
8. Any discharge to the storm drain, other than the ones listed below, is prohibited under the Municipal Separate Storm Sewer
System (MS4) permit issued to the Department of Commerce Boulder Laboratories by the U.S. Environmental Protection Agency (EPA). Note: Many of these permitted discharges do not occur at the DoC Boulder Laboratories.
a. Discharges authorized by a separate NPDES permit;
b. Discharges in compliance with instructions of an On-Scene-Coordinator pursuant to 40 CFR part 300 or 33 CFR 153.10(e);
c. Water line flushing;
d. Landscape irrigation;
e. Diverted stream flows;
f. Rising ground waters;
g. Uncontaminated ground water infiltration;
h. Uncontaminated pumped ground water;
i. Discharges from potable water sources;
j. Foundation drains;
k. Air conditioning condensate;
l. Irrigation water;
m. Springs;
n. Water from crawl space pumps;
o. Footing drains;
p. Lawn watering;
q. Individual residential car washing (not including construction equipment);
r. Flows from riparian habitats and wetlands;
s. De-chlorinated swimming pool discharges;
t. Street wash water;
u. Power washing where no chemicals are used;
PAGE 21 OF 78 1333ND23QNB190169
v. Roof drains;
w. Fire hydrant flushing;
x. Non-storm water discharges resulting from a spill which are the result of an unusual and severe weather event where reasonable and prudent measures have been taken to minimize the impact of such discharge;
y. Emergency discharges required to prevent imminent threat to human health or severe property damage, provided that reasonable and prudent measures have been taken to minimize the impact of such discharges; and
z. Discharges or flows from firefighting activities occurring during emergency situations.
9. Construction projects greater than one acre in area or part of a larger development plan greater than one acre in area must be permitted through the EPA electronic notice-of-intent (eNOI) system. Stormwater management on projects required to be permitted under the eNOI system must comply with the EPA Construction General Permit (CGP). See below for the permitting process.
a. A CGP-compliant Stormwater Pollution Prevention Plan must be submitted to NIST for review. The MS4 permit requires compliance with the Best Management Practices (BMPs) specified in the Urban Drainage and Flood Control District Criteria Manual. http://www.udfcd.org/downloads/down_critmanual.htm
i. After NIST reviews and approves the SWPPP, the contractor shall submit the NOI.
ii. The SWPPP must conform to the requirements of the Construction General Permit. Note: Revisions will be required if the SWPPP does not comply with the CGP.
iii. Guidance for developing SWPPPs that conform to EPA requirements may be found at:
http://cfpub.epa.gov/npdes/stormwater/swppp.cfm.
b. The contractor must register on the EPA Central Data Exchange (CDX) in order to electronically file the eNOI. To register, go to https://cdx.epa.gov/SSL/CDX/terms.asp?Referer=registration&RetrievalKey=. For more information on the NOI system, go to http://cfpub.epa.gov/npdes/stormwater/enoi.cfm.
c. The contractor shall submit the…