1333ND23QNB190005.pdf
PDF 1 MB Posted
- Solicitation number
- 1333ND23QNB190005
About this file
This solicitation requests maintenance services for pure water and ultra-pure water systems located at the National Institute of Standards and Technology campus in Boulder, Colorado. The contractor shall perform monthly, semi-annual, and annual maintenance to ensure the pure water system generates at least 14 gallons per minute meeting CAP Type II standards while the ultra-pure water system meets Electronic Type E-1 requirements. Additional services include troubleshooting, repairs, replacements, and upgrades on an as-needed basis. The base period of performance is January 9, 2023 through January 8, 2024 with four one-year option periods. Responses are due by the date listed in block 8 with award anticipated on the date in block 3. Pricing shall be provided for labor rates in several contract line items.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQ IFB RFP
WOMEN-OWNED SMALL BUSINESS
(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
1. REQUISITION NUMBER PAGE OF
2. CONTRACT NO. 3. AWARD/EFFECTIVE
DATE
4. ORDER NUMBER 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE
DATE
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME b. TELEPHONE NUMBER (No collect calls)
8. OFFER DUE DATE/
LOCAL TIME
9. ISSUED BY
13b. RATING
14. METHOD OF SOLICITATION
CODE
15. DELIVER TO 16. ADMINISTERED BY CODE
18a. PAYMENT WILL BE MADE BY CODEFACILITY
CODE
CODE
TELEPHONE NO.
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN
OFFER
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK
BELOW IS CHECKED
SEE ADDENDUM
19.
ITEM NO.
20.
SCHEDULE OF SUPPLIES/SERVICES
21.
QUANTITY
22.
UNIT
23.
UNIT PRICE
24.
AMOUNT
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT (For Govt. Use Only)
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED
29. AWARD OF CONTRACT: REF.
DATED . YOUR OFFER ON SOLICITATION
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
30a. SIGNATURE OF OFFEROR/CONTRACTOR
30b. NAME AND TITLE OF SIGNER (Type or print) 30c. DATE SIGNED
31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)
31b. NAME OF CONTRACTING OFFICER (Type or print) 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA - FAR (48 CFR) 53.212
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
OFFER
13a. THIS CONTRACT IS A
RATED ORDER UNDER
DPAS (15 CFR 700)
11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
ARE ARE NOT ATTACHED
ARE ARE NOT ATTACHED
27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA
17a CONTRACTOR/
OFFEROR.
CODE
8 (A)
SIZE STANDARD:
NAICS:
% FOR:SET ASIDE:UNRESTRICTED OR
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
HUBZONE SMALL
BUSINESS
SMALL BUSINESS
10. THIS ACQUISITION IS
EDWOSB
SMALL BUSINESS PROGRAM
STANDARD FORM 1449 (REV. 2/2012) BACK
19.
ITEM NO.
20.
SCHEDULE OF SUPPLIES/SERVICES
21.
QUANTITY
22.
UNIT
23.
UNIT PRICE
24.
AMOUNT
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED:
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
40. PAID BY
32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f. TELPHONE NUMBER OF AUTHORZED GOVERNMENT REPRESENTATIVE
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
33. SHIP NUMBER 34. VOUCHER NUMBER 35. AMOUNT VERIFIED
CORRECT FOR
PARTIAL FINAL
37. CHECK NUMBER
38. S/R ACCOUNT NO. 39. S/R VOUCHER NUMBER
36. PAYMENT
COMPLETE PARTIAL FINAL
SCHEDULE Continued
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 Pure Water Systems Monthly Maintenance. The contractor shall perform maintenance on the Pure Water System in accordance with the PWS Section V, PW Monthly Requirements.
Period of Performance: 01/09/2023 to 01/08/2024
12.00 MO
0002 Pure Water Systems Semi-Annual Maintenance. The
System in accordance with the PWS Section VII, PW Semi-Annual Requirements.
2.00 EA
0003 Pure Water Systems Annual Maintenance. The
System in accordance with the PWS Section IX, PW Annual Requirements.
Period of Performance: 01/09/2023 to 01/08/2024
1.00 EA
NTE NTE
0004 Pure Troubleshoot and Repair, Provide all technical services, including parts, labor, as well as any subcontractors required, to troubleshoot and repair malfunctions of the ultra-pure water systems in accordance with PWS.
All work shall be authorized by the CO prior to any work being charged against this line item. Take note of the requirements contained within PWS, II. Objectives, 3.
Please provide an hourly labor rate: $____________
1.00 YR
0005 Ultra-Pure Water Systems Monthly Maintenance. The contractor shall perform maintenance on the Ultra-Pure Water System in accordance with the PWS Section VI, UPW Monthly Requirements.
0006 Ultra-Pure Water Systems Semi-Annual Maintenance.
The contractor shall perform maintenance on the Ultra- Pure Water System in accordance with the PWS Section VIII, UPW Semi-Annual Requirements.
0007 Ultra-Pure Water Systems Annual Maintenance. The contractor shall perform maintenance on the Ultra-Pure Water System in accordance with the PWS Section X, UPW Annual Requirements.
Period of Performance: 01/09/2023 to 01/08/2024
1.00 EA
NTE NTE
0008 Ultra-Pure Troubleshoot and Repair, Provide all technical services, including parts, labor, as well as any subcontractors required, to troubleshoot and repair malfunctions of the ultra-pure water systems in accordance with PWS.
All work shall be authorized by the CO prior to any work being charged against this line item. Take note of the requirements contained within PWS, II. Objectives, 3.
PAGE 3 OF 96 1333ND23QNB190005
Please provide an hourly labor rate: $____________
Period of Performance: 01/01/2023 to 12/31/2023
OPT
1001 Pure Water Systems Monthly Maintenance. The contractor shall perform maintenance on the Pure Water System in accordance with the PWS Section V, PW Monthly Requirements.
Period of Performance: 01/09/2024 to 01/08/2025
12.00 MO
OPT
1002 Pure Water Systems Semi-Annual Maintenance. The contractor shall perform maintenance on the Pure Water System in accordance with the PWS Section VII, PW Semi-Annual Requirements.
Period of Performance: 01/09/2024 to 01/08/2025
2.00 EA
OPT
1003 Pure Water Systems Annual Maintenance. The contractor shall perform maintenance on the Pure Water System in accordance with the PWS Section IX, PW Annual Requirements.
Period of Performance: 01/09/2024 to 01/08/2025
1.00 EA
NTE NTE/OPT
1004 Pure Troubleshoot and Repair, Provide all technical services, including parts, labor, as well as any subcontractors required, to troubleshoot and repair malfunctions of the ultra-pure water systems in accordance with PWS.
All work shall be authorized by the CO prior to any work being charged against this line item. Take note of the requirements contained within PWS, II. Objectives, 3.
Please provide an hourly labor rate: $____________
Period of Performance: 01/09/2024 to 01/08/2025
1.00 YR
OPT
1005 Ultra-Pure Water Systems Monthly Maintenance. The contractor shall perform maintenance on the Ultra-Pure Water System in accordance with the PWS Section VI, UPW Monthly Requirements.
Period of Performance: 01/09/2024 to 01/08/2025
12.00 MO
OPT
1006 Ultra-Pure Water Systems Semi-Annual Maintenance.
The contractor shall perform maintenance on the Ultra- Pure Water System in accordance with the PWS Section VIII, UPW Semi-Annual Requirements.
Period of Performance: 01/09/2024 to 01/08/2025
2.00 EA
OPT
1007 Ultra-Pure Water Systems Annual Maintenance. The contractor shall perform maintenance on the Ultra-Pure Water System in accordance with the PWS Section X, UPW Annual Requirements.
Period of Performance: 01/09/2024 to 01/08/2025
1.00 EA
NTE NTE/OPT
PAGE 4 OF 96 1333ND23QNB190005
1008 Ultra-Pure Troubleshoot and Repair, Provide all technical services, including parts, labor, as well as any subcontractors required, to troubleshoot and repair malfunctions of the ultra-pure water systems in accordance with PWS.
All work shall be authorized by the CO prior to any work being charged against this line item. Take note of the requirements contained within PWS, II. Objectives, 3.
Please provide an hourly labor rate: $____________
Period of Performance: 01/09/2024 to 01/08/2025
1.00 YR
OPT
2001 Pure Water Systems Monthly Maintenance. The contractor shall perform maintenance on the Pure Water System in accordance with the PWS Section V, PW Monthly Requirements.
Period of Performance: 01/09/2025 to 01/08/2026
12.00 MO
OPT
2002 Pure Water Systems Semi-Annual Maintenance. The contractor shall perform maintenance on the Pure Water System in accordance with the PWS Section VII, PW Semi-Annual Requirements.
Period of Performance: 01/09/2025 to 01/08/2026
2.00 EA
OPT
2003 Pure Water Systems Annual Maintenance. The contractor shall perform maintenance on the Pure Water System in accordance with the PWS Section IX, PW Annual Requirements.
Period of Performance: 01/09/2025 to 01/08/2026
1.00 EA
NTE NTE/OPT
2004 Pure Troubleshoot and Repair, Provide all technical services, including parts, labor, as well as any subcontractors required, to troubleshoot and repair malfunctions of the ultra-pure water systems in accordance with PWS.
All work shall be authorized by the CO prior to any work being charged against this line item. Take note of the requirements contained within PWS, II. Objectives, 3.
Please provide an hourly labor rate: $____________
Period of Performance: 01/09/2025 to 01/08/2026
1.00 YR
OPT
2005 Ultra-Pure Water Systems Monthly Maintenance. The contractor shall perform maintenance on the Ultra-Pure Water System in accordance with the PWS Section VI, UPW Monthly Requirements.
Period of Performance: 01/09/2025 to 01/08/2026
12.00 MO
OPT
2006 Ultra-Pure Water Systems Semi-Annual Maintenance.
The contractor shall perform maintenance on the Ultra- Pure Water System in accordance with the PWS Section VIII, UPW Semi-Annual Requirements.
PAGE 5 OF 96 1333ND23QNB190005
Period of Performance: 01/09/2025 to 01/08/2026
OPT
2007 Ultra-Pure Water Systems Annual Maintenance. The contractor shall perform maintenance on the Ultra-Pure Water System in accordance with the PWS Section X, UPW Annual Requirements.
Period of Performance: 01/09/2025 to 01/08/2026
1.00 EA
NTE NTE/OPT
2008 Ultra-Pure Troubleshoot and Repair, Provide all technical services, including parts, labor, as well as any subcontractors required, to troubleshoot and repair malfunctions of the ultra-pure water systems in accordance with PWS.
All work shall be authorized by the CO prior to any work being charged against this line item. Take note of the requirements contained within PWS, II. Objectives, 3.
Please provide an hourly labor rate: $____________
Period of Performance: 01/09/2025 to 01/08/2026
1.00 YR
OPT
3001 Pure Water Systems Monthly Maintenance. The contractor shall perform maintenance on the Pure Water System in accordance with the PWS Section V, PW Monthly Requirements.
Period of Performance: 01/09/2026 to 01/08/2027
12.00 MO
OPT
3002 Pure Water Systems Semi-Annual Maintenance. The contractor shall perform maintenance on the Pure Water System in accordance with the PWS Section VII, PW Semi-Annual Requirements.
Period of Performance: 01/09/2026 to 01/08/2027
2.00 EA
OPT
3003 Pure Water Systems Annual Maintenance. The contractor shall perform maintenance on the Pure Water System in accordance with the PWS Section IX, PW Annual Requirements.
Period of Performance: 01/09/2026 to 01/08/2027
1.00 EA
NTE NTE/OPT
3004 Pure Troubleshoot and Repair, Provide all technical services, including parts, labor, as well as any subcontractors required, to troubleshoot and repair malfunctions of the ultra-pure water systems in accordance with PWS.
All work shall be authorized by the CO prior to any work being charged against this line item. Take note of the requirements contained within PWS, II. Objectives, 3.
Please provide an hourly labor rate: $____________
Period of Performance: 01/09/2026 to 01/08/2027
1.00 YR
OPT
3005 Ultra-Pure Water Systems Monthly Maintenance. The contractor shall perform maintenance on the Ultra-Pure
PAGE 6 OF 96 1333ND23QNB190005
Water System in accordance with the PWS Section VI, UPW Monthly Requirements.
Period of Performance: 01/09/2026 to 01/08/2027
OPT
3006 Ultra-Pure Water Systems Semi-Annual Maintenance.
The contractor shall perform maintenance on the Ultra- Pure Water System in accordance with the PWS Section VIII, UPW Semi-Annual Requirements.
Period of Performance: 01/09/2026 to 01/08/2027
2.00 EA
OPT
3007 Ultra-Pure Water Systems Annual Maintenance. The contractor shall perform maintenance on the Ultra-Pure Water System in accordance with the PWS Section X, UPW Annual Requirements.
Period of Performance: 01/09/2026 to 01/08/2027
1.00 EA
NTE NTE/OPT
3008 Ultra-Pure Troubleshoot and Repair, Provide all technical services, including parts, labor, as well as any subcontractors required, to troubleshoot and repair malfunctions of the ultra-pure water systems in accordance with PWS.
All work shall be authorized by the CO prior to any work being charged against this line item. Take note of the requirements contained within PWS, II. Objectives, 3.
Please provide an hourly labor rate: $____________
Period of Performance: 01/09/2026 to 01/08/2027
1.00 YR
OPT
4001 Pure Water Systems Monthly Maintenance. The contractor shall perform maintenance on the Pure Water System in accordance with the PWS Section V, PW Monthly Requirements.
Period of Performance: 01/09/2027 to 01/08/2028
12.00 MO
OPT
4002 Pure Water Systems Semi-Annual Maintenance. The contractor shall perform maintenance on the Pure Water System in accordance with the PWS Section VII, PW Semi-Annual Requirements.
Period of Performance: 01/09/2027 to 01/08/2028
2.00 EA
OPT
4003 Pure Water Systems Annual Maintenance. The contractor shall perform maintenance on the Pure Water System in accordance with the PWS Section IX, PW Annual Requirements.
Period of Performance: 01/09/2027 to 01/08/2028
1.00 EA
NTE NTE/OPT
4004 Pure Troubleshoot and Repair, Provide all technical services, including parts, labor, as well as any subcontractors required, to troubleshoot and repair malfunctions of the ultra-pure water systems in accordance with PWS.
PAGE 7 OF 96 1333ND23QNB190005
All work shall be authorized by the CO prior to any work being charged against this line item. Take note of the requirements contained within PWS, II. Objectives, 3.
Please provide an hourly labor rate: $____________
Period of Performance: 01/09/2027 to 01/08/2028
OPT
4005 Ultra-Pure Water Systems Monthly Maintenance. The contractor shall perform maintenance on the Ultra-Pure Water System in accordance with the PWS Section VI, UPW Monthly Requirements.
Period of Performance: 01/09/2027 to 01/08/2028
12.00 MO
OPT
4006 Ultra-Pure Water Systems Semi-Annual Maintenance.
The contractor shall perform maintenance on the Ultra- Pure Water System in accordance with the PWS Section VIII, UPW Semi-Annual Requirements.
Period of Performance: 01/09/2027 to 01/08/2028
2.00 EA
OPT
4007 Ultra-Pure Water Systems Annual Maintenance. The contractor shall perform maintenance on the Ultra-Pure Water System in accordance with the PWS Section X, UPW Annual Requirements.
Period of Performance: 01/09/2027 to 01/08/2028
1.00 EA
NTE NTE/OPT
4008 Ultra-Pure Troubleshoot and Repair, Provide all technical services, including parts, labor, as well as any subcontractors required, to troubleshoot and repair malfunctions of the ultra-pure water systems in accordance with PWS.
All work shall be authorized by the CO prior to any work being charged against this line item. Take note of the requirements contained within PWS, II. Objectives, 3.
Please provide an hourly labor rate: $____________
Period of Performance: 01/09/2027 to 01/08/2028
PAGE 8 OF 96 1333ND23QNB190005
Table of Contents
Statement of Work
SPECIAL INVOICING INSTRUCTIONS
52.202-1DEFINITIONS (JUN 2020)
52.203-3 GRATUITIES (APR 1984)
52.203-5 COVENANT AGAINST CONTINGENT FEES (MAY 2014)
52.203-12LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS (JUN 2020)
52.203-17CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS AND REQUIREMENT TO INFORM EMPLOYEES OF WHISTLEBLOWER
RIGHTS (JUN 2020)
52.204-4 PRINTED OR COPIED DOUBLE-SIDED ON POSTCONSUMER FIBER CONTENT PAPER (MAY 2011)
52.204-7 SYSTEM FOR AWARD MANAGEMENT (OCT 2018)
52.204-9 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (JAN 2011)
52.204-13SYSTEM FOR AWARD MANAGEMENT MAINTENANCE (OCT 2018)
52.204-16COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING (AUG 2020)
52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014)
52.212-1INSTRUCTIONS TO OFFERORS--COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (NOV 2021)
FP Addendum 52.212-1
52.212-4CONTRACT TERMS AND CONDITIONS--COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (NOV 2021)
52.217-5 EVALUATION OF OPTIONS (JUL 1990)
52.223-2 AFFIRMATIVE PROCUREMENT OF BIOBASED PRODUCTS UNDER SERVICE AND CONSTRUCTION CONTRACTS (SEP
2013)
52.232-40PROVIDING ACCELERATED PAYMENTS TO SMALL BUSINESS SUBCONTRACTORS (NOV 2021)
52.253-1 COMPUTER GENERATED FORMS (JAN 1991)
1352.209-73 COMPLIANCE WITH THE LAWS (APR 2010)
1352.209-74 ORGANIZATIONAL CONFLICT OF INTEREST (APR 2010)
52.204-24REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT
(NOV 2021)
52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)
52.212-2EVALUATION--COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (NOV 2021)
Addendum to 52.212-2 Evaluation - Commercial Items
52.212-3OFFEROR REPRESENTATIONS AND CERTIFICATIONS--COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (MAY
2022)
52.212-5CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR EXECUTIVE ORDERS--COMMERCIAL
PRODUCTS AND COMMERCIAL SERVICES (MAY 2022)
52.217-8 OPTION TO EXTEND SERVICES (NOV 1999)
52.217-9 OPTION TO EXTEND THE TERM OF THE CONTRACT (MAR 2000)
1352.201-70 CONTRACTING OFFICER?s AUTHORITY (APR 2010)
1352.201-72 CONTRACTING OFFICER`S REPRESENTATIVE (COR) (APR 2010)
1352.208-70 RESTRICTIONS ON PRINTING AND DUPLICATING (APR 2010)
1352.209-72 RESTRICTIONS AGAINST DISCLOSURE (APR 2010)
1352.233-71 GAO AND COURT OF FEDERAL CLAIMS PROTESTS (APR 2010)
1352.237-71 SECURITY PROCESSING REQUIREMENTS - LOW RISK CONTRACTS (APR 2010)
1352.246-70 PLACE OF ACCEPTANCE (APR 2010)
1352.270-70 PERIOD OF PERFORMANCE (APR 2010)
1352.270-71 PRE-BID / PRE-PROPOSAL CONFERENCE AND SITE VISIT (APR 2010)
NIST LOCAL-33U.S. DEPARTMENT OF LABOR WAGE DETERMINATION
NIST LOCAL-54ELECTRONIC BILLING INSTRUCTIONS
Past Performance Questionnaire
Small Business Participation Commitment Document
Specification Section 15485
WAGE DETERMINATION
PAGE 9 OF 96 1333ND23QNB190005
CLAUSES
Statement of Work
PAGE 10 OF 96 1333ND23QNB190005
Performance Work Statement Pure and Ultra Pure Water
July 2022
I. Background
NIST-Boulder has a state-of-the-art research laboratory (the Katharine Bloggett Gebbie Building) to support the most sensitive research done at NIST. Included in this building is a Class 100 microelectronics fabrication facilities, called the Boulder Micro-Fabrication Facility (BMF). Among the many critical pieces of infrastructure in this laboratory are the pure water system (PW) in the instrument laboratories, and the ultrapure water system (UPW) in the BMF.
II. Objectives
1. The objective of this acquisition is to:
A. Provide a consistent and reliable product water quality of the buildings PW and UPW systems, B. Minimize unscheduled downtime, C. Complete scheduled maintenance in a timely manner defined in the specifications of the work, D. Provide a mechanism for repairs, replacements, necessary upgrades, and unscheduled maintenance,
2. The tasks for the water system maintenance is divided between the PW and UPW systems and are specified separately. The maintenance of these systems shall be based on the ASTM D5127-13 “Standard Guide for Ultra- Pure Water Used in the Electronics and Semiconductor Industries” and the methods and requirements of Submittal Section 15485 (see reference section). The PW system must meet or exceed the CAP Type II (Resistivity: 2 MOhm/cm @ 25 C): College of American Pathologists Standards. The UPW system must meet or exceed Electronic Type E-1 (Resistivity 18.1 MOhm/cm @ 25 C, without dissolved oxygen requirements): ASTM D-5127 standard.
3. In addition to the preventative maintenance requirement (CLINs X001, X002, X003, X005, X006 and X007), the contractor shall provide all technical services, including parts, labor, as well as any subcontractors required, to troubleshoot and repair malfunctions of the PW and UPW Systems (CLINs X004 and X008). NOTE: these repairs are on an as needed basis. The contractor shall provide all labor, material, and equipment to perform authorized repair services.
A. The contractor shall submit a quote for repair and/or troubleshooting when requested by the contracting officer's representative (COR). The quote shall include a detailed description of the work to be accomplished and a complete/detailed price breakdown to include all costs related to supervision, labor, material, and equipment to perform repair services once authorized.
B. The quote will then be evaluated for price reasonableness. The contracting officer (CO) will approve the Work Order Authorization based on the evaluated quote and concurrence from the COR. The contractor exceeds the amount approved by the CO at their risk as only the work contained in the Work Order Authorizations will be paid by NIST.
C. The contractor shall include a copy of the approved Work Order Authorization as an attachment to each applicable invoice.
III. Scope
1. The contractor shall on a scheduled basis visually inspect, service, and maintain the PW and UPW systems as outlined below.
A. PW / UPW monthly scope of work
PAGE 11 OF 96 1333ND23QNB190005
B. PW / UPW semi-annual scope of work C. PW / UPW annual scope of work
2. In addition, the scope includes contract line items for the repairs, replacement, necessary upgrades, and unscheduled maintenance
IV. General Information
1. All contractor staff must complete NIST Security badging process. No one may enter the site without a badge.
Contractor shall provide personnel that are US Citizens who pass required government background checks to be issued badges for work on site.
2. A minimum of two people shall be hard badged with 24-hour access.
3. All maintenance will be scheduled with the COR at least 1 week prior to arrival to do the work.
4. During the performance of the work, if the contractor deems it necessary to shut down either the PW or UPW system, the contractor shall notify the COR. However, if there is imminent threat of damage to life or property, contractor has the authority to shut down the system without notifying the COR for approval.
5. The PW system consists of the following components:
A. PW Water softener (two membrane tanks, a brine tank, and controllers) -
1) Ecodyne Multiport Valve Softener
B. PW Multimedia filter
1) Ecodyne Multiport Valve Filter
C. PW Activated carbon filter
1) Ecodyne Multiport Valve Filter
D. PW Reverse osmosis (RO)
1) GE E4H Series Water Purification Machines
2) Model Number: E4H-21K-DLX, 460, 6, 50-75
3) RO Pump 1 Model Number: SS2823G
4) CIP Pump Model Number: SS2805AZ
E. PW Continuous electrical de-ionizer (CEDI)
1) Ion Pure LX
2) Model Number: IP-LXM30X-3
F. PW storage tank
G. PW re-pressurization pumps (two)
1) Grundfos CRN64
2) Type: CRN64-2-1 A-G-G-V-KUHV
3) Model: A96426505-P11104505 & A96423893P112370153
H. PW UV sterilization lamps (UV1) 254 nm
1) Aquafine Corporation CSL
2) Model Number: CSL-12R-60
PAGE 12 OF 96 1333ND23QNB190005
I. PW filters (0.2 µm)
1) Shelco MicroGuardian
2) Model: 21FOS3-SB-316-222-3F-GB-E-UP
J. PW sensors
1) Supply pressure. For more information, please see Submittal Section 15485 Section 2.14(see reference section)
2) Supply resistivity. For more information, please see Submittal Section 15485 Section 2.15(see reference section)
K. Control PLC
1) Allen-Bradley Panel View C600
2) Allen-Bradley Micro Logix 1400
3) Mettler Toledo Thornton M300
4) Mettler Toledo Thornton 770 Max
5) For more information, please see Submittal Section 15485 Section 3.1-B (see reference section)
6. The UPW system consists of the following components:
A. UPW storage tank
B. UPW re-pressurization pumps (two)
1. Grundfos CRN10
2. Type: CRN10-05 A-FGJ-G-V-HUUV
3. Model: A978597850791-P11107404 & A978597850791-P11107405
C. UPW UV sterilization lamps (UV2) 254 nm
1. Aquafine Corporation CSL
2. Model Number: CSL-8R
D. UPW resin bed deionizers
E. UPW filters (0.2 µm)
1. Shelco MicroGuardian
2. Part Number: 3SFV3C22215TC25
F. UPW UV sterilization lamps (UV3) 185 nm
1. Aquafine Corporation CSL
2. Model Number: CSL-4R
G. UPW filters (0.05 µm)
1. Shelco MicroGuardian
2. Part Number: 7SFN3SB22215TC2
H. UPW sensors
1. Flow meter. For more information, please see Submittal Section 15485 Section 2.13 (see reference section)
2. Pressure sensor. For more information, please see Submittal Section 15485 Section 2.14 (see reference section)
3. Output water resistivity. For more information, please see Submittal Section 15485 Section 2.15 (see reference section)
PAGE 13 OF 96 1333ND23QNB190005
4. Return water resistivity. For more information, please see Submittal Section 15485 Section 2.15 (see reference section)
I. Total Organic Content Analyzer GE Sievers 500 RL On-Line TOC Analyzer
V. PW Monthly Requirements
1. During the first full week of each month, the contractor shall visually inspect, service, and maintain the PW system.
The PW system must generate 14 gpm of purified water that meets or exceeds the CAP Type II (Resistivity: 2 MOhm/cm @ 25 C): College of American Pathologists Standards. The maintenance of these systems shall be based on the ASTM D5127-13 “Standard Guide for Ultra-Pure Water Used in the Electronics and Semiconductor Industries”. For each listed subsystem, the contractor shall:
A. PW water softener (two membrane tanks, a brine tank, and controllers)
1. During normal operation, inspect all serviceable components within the system as defined in the owner’s manual.
2. Visually inspect control valves and seals for signs of moisture and leaks and if present, repair the system to the ASTM D5127-13 standard.
3. Record inlet and outlet hardness levels of the system. The outlet hardness must be maintained to a target level of <10 ppm hardness with an upper control limit of 17.1 ppm or 1.0 grain/gallon hardness.
4. Check the operation and salt level of the brine tank. NIST will add salt on a regular basis. If during inspection, salt level is low the vendor shall notify the COR.
5. If any of the above are not in compliance with the manufacture’s recommended values, repair the system to the manufactures standard in a method in accordance with the ASTM D5127-13 standard and the methods and requirements of Submittal Section 15485 (see reference section). If the contractor deems it to be more cost effective to replace the item, the contractor shall contact the COR for authorization to replace (See section II, paragraph 3).
B. PW multimedia filter
1. During normal operation, inspect all serviceable components within the system as defined in the owner’s manual.
2. Visually inspect control valves and seals for signs of moisture and leaks.
3. If any of the above are not in compliance with the manufacture’s recommended values, repair the system to the manufactures standard in a method in accordance with the ASTM D5127-13 standard and the methods and requirements of Submittal Section 15485 (see reference section). If the contractor deems it to be more cost effective to replace the item, the contractor shall contact the COR for authorization to replace.
(See section II, paragraph 3)
C. PW activated carbon filter
1. During normal operation, inspect all serviceable components within the system as defined in the owner’s manual.
2. Visually inspect control valves and seals for signs of moisture and leaks and if present, repair the system to the ASTM D5127-13 standard.
3. Record inlet and outlet chlorine levels of the system. The outlet chlorine levels must be maintained to a target level of 0.0 ppm total chlorine with an upper control limit of <0.05 ppm total chlorine.
4. If any of the above are not in compliance with the manufacture’s recommended values, repair the system to the manufactures standard in a method in accordance with the ASTM D5127-13 standard and the methods and requirements of Submittal Section 15485 (see reference section). If the contractor deems it to be more cost effective to replace the item, the contractor shall contact the COR for authorization to replace (See section II, paragraph 3).
PAGE 14 OF 96 1333ND23QNB190005
D. PW reverse osmosis
1. During normal operation, inspect all serviceable components within the system as defined in the owner’s manual.
2. Replace the two pre-filters with filters as specified by the manufacturer.
3. Verify that the system flushes automatically as specified by the manufacturer. If it does not, notify the
COR.
4. Record:
4.i. Inlet, outlet, and differential pressure of the pre-filter 4.ii. Primary pump pressure 4.iii. Concentrate pressure 4.iv. System differential pressure 4.v. Permeate Flow 4.vi. Concentrate Flow 4.vii. Percent Recovery 4.viii.Feed water temperature 4.ix. Feed water conductivity 4.x. Product water conductivity 4.xi. Concentrate water conductivity 4.xii. Percent rejection
5. If any of these sensors or associated readout electronics required for the above measurements are not operational or if any of the above are not in compliance with the manufacture’s recommended values, repair to the manufactures standard in a method in accordance with the ASTM D5127-13 standard and the methods and requirements of Submittal Section 15485 (see reference section). If the contractor deems it to be more cost effective to replace the item, the contractor shall contact the COR for authorization to replace (See section II, paragraph 3).
E. PW continuous electrical de-ionizer (CEDI)
1. During normal operation, inspect all serviceable components within the system as defined in the owner’s manual.
2. Record:
2.i. Feed water temperature 2.ii. Feed water hardness 2.iii. Feed water pH 2.iv. Feed water conductivity 2.v. Product water resistivity 2.vi. DC voltage 2.vii. DC current 2.viii.Product flow 2.ix. Reject flow 2.x. Dilute inlet pressure 2.xi. Dilute outlet pressure 2.xii. Product differential pressure 2.xiii.Concentrate inlet pressure 2.xiv.Concentrate outlet pressure 2.xv. Concentrate differential pressure
3. If any of these sensors or associated readout electronics required for the above measurements are not operational or if any of the above are not in compliance with the manufacture’s recommended values, repair to the manufactures standard in a method in accordance with the ASTM D5127-13 standard and the methods and requirements of Submittal Section 15485 (see reference section). If the contractor deems it to
PAGE 15 OF 96 1333ND23QNB190005
be more cost effective to replace the item, the contractor shall contact the COR for authorization to replace (See section II, paragraph 3).
F. PW storage tank During normal operation, inspect all serviceable components within the system as defined in the owner’s manual. If any maintenance is required, repair the system to the manufactures standard in a method in accordance with the ASTM D5127-13 standard and the methods and requirements of Submittal Section 15485 (see reference section). If the contractor deems it to be more cost effective to replace the item, the contractor shall contact the COR for authorization to replace (See section II, paragraph 3).
G. PW re-pressurization pumps (two)
1. During normal operation, inspect all serviceable components within the system as defined in the owner’s manual.
2. Visually inspect mechanical seals for signs of leaks and if present, repair the system to the manufactures standard in a method in accordance with the ASTM D5127-13 standard and the methods and requirements of Submittal Section 15485 (see reference section). If the contractor deems it to be more cost effective to replace the item, the contractor shall contact the COR for authorization to replace (See section II, paragraph 3).
H. PW UV sterilization lamps (UV1) 254 nm
1. During normal operation, inspect all serviceable components within the system as defined in the owner’s manual.
2. Record UV intensity. If this value is not in compliance with the manufacturer’s recommended values, repair the system to the manufactures standard in a method in accordance with the ASTM D5127-13 standard and the methods and requirements of Submittal Section 15485 (see reference section). UV lamps must be replaced with 254 nm DE validated lamps as specified by the manufacturer. If the contractor deems it to be more cost effective to replace the item, the contractor shall contact the COR for authorization to replace (See section II, paragraph 3).
I. PW filters (0.2 µm)
1. During normal operation, inspect all serviceable components within the system as defined in the owner’s manual.
2. Record inlet, outlet, and differential pressures. If any of these values are not in compliance with the manufacture’s recommended values, repair the system to the manufactures standard in a method in accordance with the ASTM D5127-13 standard and the methods and requirements of Submittal Section 15485 (see reference section). If the contractor deems it to be more cost effective to replace the item, the contractor shall contact the COR for authorization to replace (See section II, paragraph 3).
J. PW sensors
1. Record:
1.i. Supply resistivity.
1.ii.Supply pressure
2. If any of these sensors or associated readout electronics are not operational, repair the system to the manufactures standard in a method in accordance with the ASTM D5127-13 standard and the methods and requirements of Submittal Section 15485 (see reference section). If the contractor deems it to be more cost effective to replace the item, the contractor shall contact the COR for authorization to replace (See section II, paragraph 3).
K. PW monthly system report. The contractor shall supply the COR with a copy of a report summarizing work done, values recorded, any issues identified, and any repairs or replacements made
PAGE 16 OF 96 1333ND23QNB190005
VI. UPW Monthly Requirements
1. On a monthly basis, during the first full week of the month, the contractor shall visually inspect, service, and maintain the UPW system. The UPW system must generate 30 gpm of purified water that meets or exceeds the Electronic Type E-1 (Resistivity 18.1 MOhm/cm @ 25 C, without dissolved oxygen requirements): ASTM D-5127 standard into the storage tank, and then recirculates through the BMF. The UPW is supplied with input water from the PW system. The maintenance of these systems shall be based on the ASTM D5127-13 “Standard Guide for Ultra-Pure Water Used in the Electronics and Semiconductor Industries”. For each listed subsystem, the contractor shall:
A. UPW storage tank During normal operation, inspect the nitrogen conservation system. If it is not operating according to the manufacturer’s specifications, the contractor shall repair the system to the manufactures standard in a method in accordance with the ASTM D5127-13 standard and the methods and requirements of Submittal Section 15485 (see reference section). If the contractor deems it to be more cost effective to replace the item, the contractor shall contact the COR for authorization to replace (See section II, paragraph 3).
B. UPW re-pressurization pumps (two)
1. During normal operation, inspect all serviceable components within the system as defined in the owner’s manual.
2. Visually inspect mechanical seals for signs of leaks and if present, repair the system to the manufactures standard in a method in accordance with the ASTM D5127-13 standard and the methods and requirements of Submittal Section 15485 (see reference section). If the contractor deems it to be more cost effective to replace the item, the contractor shall contact the COR for authorization to replace (See section II, paragraph 3).
C. UPW UV sterilization lamps (UV2) 254 nm
1. During normal operation, inspect all serviceable components within the system as defined in the owner’s manual.
2. Record UV intensity. If this value is not in compliance with the manufacturer’s recommended values, repair the system to the manufactures standard in a method in accordance with the ASTM D5127-13 standard and the methods and requirements of Submittal Section 15485 (see reference section). UV lamps must be replaced with 254 nm DE validated lamps as specified by the manufacturer. If the contractor deems it to be more cost effective to replace the item, the contractor shall contact the COR for authorization to replace (See section II, paragraph 3).
D. UPW resin bed deionizers
1. During normal operation, inspect all serviceable components within the system as defined in the owner’s manual.
2. Record:
i. Feed water pH
ii. Inlet, outlet, and differential pressure
iii. Loop supply flow rate
iv. Loop supply resistivity
3. If any of the above are not in compliance with the manufacture’s recommended values, repair the system to the manufactures standard in a method in accordance with the ASTM D5127-13 standard and the methods and requirements of Submittal Section 15485 (see reference section). If the contractor deems it to be more cost effective to replace the item, the contractor shall contact the COR for authorization to replace
E. UPW filters (0.2 µm)
PAGE 17 OF 96 1333ND23QNB190005
1. During normal operation, inspect all serviceable components within the system as defined in the owner’s manual.
2. Record inlet, outlet, and differential pressures. If any of the above values are not in compliance with the manufacture’s recommended values, repair the system to the manufactures standard in a method in accordance with the ASTM D5127-13 standard and the methods and requirements of Submittal Section 15485 (see reference section). If the contractor deems it to be more cost effective to replace the item, the contractor shall contact the COR for authorization to replace (See section II, paragraph 3).
F. UPW UV sterilization lamps (UV3) 185 nm
1. During normal operation, inspect all serviceable components within the system as defined in the owner’s manual.
2. Record UV intensity. If this value is not in compliance with the manufacturer’s recommended values, repair the system to the manufactures standard in a method in accordance with the ASTM D5127-13 standard and the methods and requirements of Submittal Section 15485 (see reference section). UV lamps must be replaced with 185 nm DE validated lamps as specified by the manufacturer. If the contractor deems it to be more cost effective to replace the item, the contractor shall contact the COR for authorization to replace (See section II, paragraph 3).
G. UPW filters (0.05 µm)
1. During normal operation, inspect all serviceable components within the system as defined in the owner’s manual.
2. Record inlet, outlet, and differential pressures. If any of these values are not in compliance with the manufacturer’s recommended values, repair the system to the manufactures standard in a method in accordance with the ASTM D5127-13 standard and the methods and requirements of Submittal Section 15485 (see reference section). If the contractor deems it to be more cost effective to replace the item, the contractor shall contact the COR for authorization to replace (See section II, paragraph 3).
L. UPW sensors
1. Record:
1.i. Flow rate 1.ii. Water pressure 1.iii. Output water resistivity 1.iv. Return water resistivity
2. If any of these sensors or associated readout electronics are not operational, repair the system to the manufactures standard in a method in accordance with the ASTM D5127-13 standard and the methods and requirements of Submittal Section 15485 (see reference section). If the contractor deems it to be more cost effective to replace the item, the contractor shall contact the COR for authorization to replace (See section II, paragraph 3).
H. Total Organic Content Analyzer
1. During normal operation, inspect all serviceable components within the system as defined in the owner’s manual.
2. Record loop supply quality. Total organic content must meet or exceed Electronic Type E-1 (Resistivity
18.1 MOhm/cm @ 25 C, without dissolved oxygen requirements): ASTM D-5127 standard.
3. If any parts of this analyzer or its associated readout electronics are not operational, repair the system to the manufactures standard in a method in accordance with the ASTM D5127-13 standard and the methods and requirements of Submittal Section 15485 (see reference section). If the contractor deems it to be more cost effective to replace the item, the contractor shall contact the COR for authorization to replace (See section II, paragraph 3).
PAGE 18 OF 96 1333ND23QNB190005
I. UPW monthly system report. The contractor shall supply the COR with a copy of a report summarizing work done, values recorded, any issues identified, and any repairs or replacements made within 3 business days of completion of the work.
VII. PW Semi-Annual Requirements
1. On a semi-annual basis, during the annual maintenance and during the first full week of the month six months after the annual maintenance, the contractor shall visually inspect, service, and maintain the PW system. The PW system must generate 14 gpm of purified water that meets or exceeds the CAP Type II (Resistivity: 2 MOhm/cm @ 25 C):
College of American Pathologists Standards. The contractor shall perform the following maintenance using methods based on the ASTM D5127-13 “Standard Guide for Ultra-Pure Water Used in the Electronics and Semiconductor Industries”:
1. PW continuous electrical de-ionizer (CEDI) - Tune the unit to optimize current, voltage, and flow between the two sides.
2. PW reverse osmosis - Clean membranes to manufacturer specifications.
B. PW semi-annual system report. The contractor shall supply the COR with a copy of a report summarizing work done, values recorded, any issues identified, and any repairs or replacements made within 3 business days of completion of the work.
VIII. UPW Semi-Annual Requirements
1. On a semi-annual basis, during the annual maintenance and during the first full week of the month six months after the annual maintenance, the contractor shall visually inspect, service, and maintain the UPW system. For the UPW system to generate 30 gpm of water that meets or exceeds the Electronic Type E-1 (Resistivity 18.1 MOhm/cm @ 25 C, without dissolved oxygen requirements): ASTM D-5127 standard. The contractor shall perform the following maintenance using methods based on the ASTM D5127-13 “Standard Guide for Ultra-Pure Water Used in the Electronics and Semiconductor Industries”:
A. UPW resin bed deionizers
1. Resin bed deionizers must meet the requirements of Reference Submittal Section 15485 (section 2.9-B) with the modification that the tanks are filled with virgin resin.
2. The contractor shall supply tanks with virgin resin and NIST shall receive credit for returned resin to be used for the purchase of future resin.
3. Total Organic Content Analyzer (TOC) - Replace total oxidizable carbons lamp using a part number and method as specified by the manufacturer.
B. UPW semi-annual system report. The contractor shall supply the COR with a copy of a report summarizing work done, values recorded, any issues identified, and any repairs or replacements made within 3 business days of completion of the work.
IX. PW Annual Requirements
1. In addition to the monthly and semi-annual maintenance, annual maintenance is required for the PW system to generate 14 gpm of purified water that meets or exceeds the CAP Type II (Resistivity: 2 MOhm/cm @ 25 C):
College of American Pathologists Standards.
2. The annual and one of the corresponding semi-annual and monthly maintenance for the PW system shall be completed during the first complete weekend of December which consists of the time between the close of business on Friday 5:00 pm Mountain Time until the start of business the next Monday at 7:00 am Mountain Time. The contractor shall:
PAGE 19 OF 96 1333ND23QNB190005
A. PW Water Softener - Obtain a core sample of the resin and determine the resin quality. If the resin quality is not at the manufacturer recommendations inform the COR for authorization to replace (See section II, paragraph 3).
B. PW Multimedia Filter - During only the first year of the contract, replace and rebed the multimedia filter to manufacturer specifications.
C. PW Activated Carbon Filter - Replace and rebed carbon filter. The media shall be made from selected grades of bituminous coal combined with suitable binders, and shall have an iodine number of at least 850 and a minimum abrasion number of 75. Particle retention shall be 40 micron and larger. The filter size is 30 cubic feet.
D. PW Continuous Electrical De-Ionizer (CEDI) - Perform manufacturer recommended annual maintenance on CEDI including calibration of all water flow rates and water electrical conductivity. Cleaning shall be done based on differential pressure and quality.
E. PW Storage Tank - Replace storage tank vent filter with parts and methods as specified by the manufacturer.
F. PW UV Sterilization Lamps (UV1) 254 nm - Every year, replace all UV lamps with 254 nm DE validated lamps, quartz sleeves, and O-rings with parts and methods as specified by the manufacturer. There are a total of 12 lamps. O-rings shall be Viton or Chemraz.
G. PW Filters (0.2 µm) - Replace all 0.2 micron final filters with parts and methods as specified by the manufacturer. There are a total of 42 filters.
H. PW Reverse Osmosis - Perform manufacturer recommended annual maintenance including calibration of all water flow rates and water electrical conductivity.
I. Disinfect the entire PW system (distribution loop lines plus a 2200 gallon storage tank) using a level of ozone approved by the COR based on contractors accepted ozone generation method and NIST system requirements.
The contractor shall supply a method of generating ozone to properly disinfect the PW system to a level that meets or exceeds the CAP Type II (Resistivity: 2 MOhm/cm @ 25 C): College of American Pathologists Standards. NIST does not have the capability to generate ozone. After disinfection, the PW system must generate 14 gpm of purified water that meets or exceeds the CAP Type II (Resistivity: 2 MOhm/cm @ 25 C):
College of American Pathologists Standards.
J. PW annual system report. The contractor shall supply the COR with a copy of a report summarizing work done, values recorded, any issues identified, and any repairs or replacements made within 3 business days of completion of the work.
X. UPW Annual Requirements
1. In addition to the monthly and semi-annual maintenance, annual maintenance is required for the UPW system to generate 30 gpm of purified water that meets or exceeds the Electronic Type E-1 (Resistivity 18.1 MOhm/cm @ 25 C, without dissolved oxygen requirements): ASTM D-5127 standard annual maintenance is required.
2. The annual and one of the corresponding semi-annual and monthly maintenance for the PW and UPW systems shall be completed during the first complete weekend of December which consists of the time between the close of business on Friday 5:00 pm Mountain Time until the start of business the next Monday at 7:00 am Mountain Time.
The contractor shall:
A. UPW storage tank
PAGE 20 OF 96 1333ND23QNB190005
1. Replace storage tank vent filter with parts and methods as specified by the manufacturer.
2. Inspect the nitrogen blanket system. Verify there are no tears in membranes. Verify the nitrogen flow and pressure are set to the manufacturer’s recommended values.
3. If the UPW storage tank is not in compliance with the manufacturer’s recommended values, repair the system to the manufactures standard in a method in accordance with the ASTM D5127-13 standard and the methods and requirements of Submittal Section 15485 (see reference section). If the contractor deems it to be more cost effective to replace the item, the contractor shall contact the COR for authorization to replace
B. UPW UV Sterilization Lamps (UV2) 254 nm - Replace all UV lamps with 254 nm DE validated lamps, quartz sleeves and O-rings with parts and methods as specified by the manufacturer. There are a total of 8 lamps.
C. UPW Filters (0.2 µm) - Replace all 0.2 micron final filters with parts and methods as specified by the manufacturer. There are a total of 6 filters.
D. UPW UV Sterilization Lamps (UV3) 185 nm - Replace all UV lamps with 185 nm DE validated lamps, quartz sleeves and O-rings with parts and methods as specified by the manufacturer. There are a total of 4 lamps.
E. UPW Filters (0.05 µm) - Replace all 0.05 micron final filters with parts and methods as specified by the manufacturer. There are a total of 14 filters.
F. Total Organic Content Analyzer
1. Replace total oxidizable carbons pumps with parts and methods as specified by the manufacturer. There are a total of 2 pumps.
2. Replace the total oxidizable carbons filter with parts and methods as specified by the manufacturer.
G. Disinfect The Entire UPW System (distribution loop lines plus a 2200 gallon storage tank) using a level of ozone based on contractors ozone generation method and NIST system requirements. The contractor shall supply a method of generating ozone to properly disinfect the PW system to a level that meets or exceeds the Electronic Type E-1 (Resistivity 18.1 MOhm/cm @ 25 C, without dissolved oxygen requirements): ASTM D- 5127 standard. NIST does not have the capability to generate ozone. After disinfection, the UPW system must generate 30 gpm of purified water that meets or exceeds the Electronic Type E-1 (Resistivity 18.1 MOhm/cm @ 25 C, without dissolved oxygen requirements): ASTM D-5127 standard.
H. UPW Annual System Report. The contractor shall supply the COR with a copy of a report summarizing work done, values recorded, any issues identified, and any repairs or replacements made within 3 business days of completion of the work.
PAGE 21 OF 96 1333ND23QNB190005
XI Performance Standards
Performance Requirements and Surveillance Table
TASK PERFORMANCE STANDARD FREQUENCY STANDARD
Perform Monthly Maintenance and Repair of PW and UPW Systems
Maintenance performed to manufacturer specifications using OEM components for each piece of equipment. Work is performed within the work week with minimal disruption to system.
Report summarizing work done, values recorded,…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .