This document is an Amendment (0002) to a federal solicitation for Uninterruptible Power Supply (UPS) Battery Replacement at the Weather Forecast Office (WFO) in Guam. The amendment modifies several key requirements, most notably removing previous language about personnel certification by Vertiv Group Corp in working on Liebert UPS systems. The solicitation seeks a contractor to replace 24 batteries in an existing Liebert eXM Uninterruptible Power System, conduct system testing, and properly dispose of old batteries, with a 90-day period of performance.
The amendment extends the quote submission deadline to Tuesday, June 24, 2025, at 1:00 PM Hawaii Time. The procurement is a total small business set-aside with NAICS code 335910 and a small business size standard of 1,250 employees. The government will evaluate quotes based on technical approach and capability, past performance, price, and previously required personnel certification (now removed). The contract will be awarded as a trade-off, single firm fixed-price purchase order with Net 30 payment terms, with the non-price technical solution considered significantly more important than price in the evaluation process.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation Q and A 1333MH25Q0002.pdf | ||
| Past Performance Questionnaire_UPS Battery.pdf | ||
| Sol_1333MH25Q0002.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: is not is required copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7.ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
PAGESOF
Contractor
The hour and date specified for receipt of Offers to sign this document and return
KATY REANO
See continuation page
NWS Field Delegates
601 EAST 12TH STREET SUITE 1746
KANSAS CITY MO 64106
NWS-FD
1333MH25Q0002
06/09/2025
06/09/2025
1 11
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
1333MH25Q0002/0002
AMENDMENT 0002
Solicitation 1333MH25Q0002 is amended as follows:
1. "Personnel Certification (by Vertiv Group
Corp in working on Liebert UPS Systems)" has been DELETED from 52.212-1 Instructions to
Offerors-Commercial Products and Commercial
Services (Sep 2023).
2. "The contractor personnel performing all requirements specified in this SOW shall be certified by Vertiv Group Corp in working on
Liebert UPS systems" has been DELETED from FAR
52.212-2 Evaluation - Commercial Products and
Commercial Services.
3. Section 2.2.4 of the Statement of Work (SOW) with the sentence "The Contractor shall perform any manufacturer firmware updates for the UPS and verify operation" has been DELETED from the
SOW.
4. Section 4.1 Qualified Personnel of the SOW has been revised. The sentence "Personnel shall be certified by Vertiv Group Corp in working on
Liebert UPS systems" has been DELETED from the
SOW.
5. Amendment 0002 supersedes Amendment 0001.
6. The Due date for Quotes has been extended to
Tuesday, June 24, 2025, 1:00 PM HT.
****END AMENDMENT 0002****
1333MH25Q0002 0002
Section II - Supplies or Services and Price/Costs
CLIN List
Section III - Description/Specifications
Summary of Clause Changes:
Clause Statement of Work is incorporated as follows:
Statement of Work SOW
STATEMENT OF WORK (SOW)
National Oceanic and Atmospheric Administration (NOAA) National Weather Service (NWS) - Weather Forecast Office (WFO) Guam Uninterruptible Power Supply (UPS) Battery Replacement
PR #: 142060-25-0061
1.0 GENERAL
1.1 BACKGROUND
The Weather Forecast Office (WFO) Guam, provides current weather and accurate information used for air traffic operations, real time weather reporting and weather forecasting. Equipment critical to this mission is supported by the station's Uninterruptible Power Supply (UPS) system which is currently showing critical faults and batteries that do not support the electrical load during power outages.
1.2 SCOPE
The scope of this contract is to replace 24 batteries in the existing Liebert UPS at WFO Guam and conduct a system test to ensure the UPS and batteries are working properly. In addition, the contractor is responsible for disposal of the old batteries, clearing any errors and reporting any irregularities with the UPS.
1.3 OBJECTIVE
The objective of this contract is for the contractor to successfully replace all UPS batteries, clear all error codes related to battery system faults and demonstrate that the UPS is capable of enabling a seamless transfer of power during outages (commercial power to UPS to generator and back to commercial power).
1.4 APPLICABLE DOCUMENTS
The following documents will be used to complete the work specified in this SOW:
1.4.1 Compliance Documents
The following documents provide specifications, standards, or guidelines that must be complied with in order to meet the requirements of this contract:
National Fire Protection Association 70 – National Electrical Code (NEC)
1.4.2 Reference Documents
The following documents may be helpful to the Contractor in performing the work described in this about:blank document:
Liebert® EXM™ 10-40kVA, 50/60Hz User Manual-Table 23
2.0 SPECIFIC REQUIREMENTS/TASKS
The Contractor shall meet the following requirements/tasks:
2.1 TASK ONE - Replace UPS Batteries
The Contractor shall complete the following to replace the UPS batteries:
2.1.1 The contractor shall ship and deliver 24 UPS batteries to the WFO Guam. The contractor shall protect batteries during shipment assuming the possibility of inclement weather and that the delivery/storage location on site may be outside in the elements.
2.1.2 Coordinate the safe delivery of the batteries to the WFO Guam site with the Technical Point of Contact (TPOC).
2.1.3 Remove old batteries for UPS and install new batteries in accordance with the latest applicable standards of the NEC and the manufacturer’s specifications.
2.1.4 The contractor shall ensure no power disruptions to the office while work is accomplished. There shall be minimal or no down time.
2.2 TASK TWO – UPS Battery Testing and System Updates
The Contractor shall complete the following to test the UPS batteries and system:
2.2.1 The Contractor shall conduct a system test on the new batteries and UPS system ensuring there are no faults or errors. The UPS batteries must be able to carry the full electrical loads during a commercial power outage for the time it takes for power to switch to generator power.
2.2.2 Battery replacement and testing shall take no longer than one 8-hour work day. If battery replacement is to take longer than 8 hours, the contractor shall notify the TPOC.
2.2.3 The contractor shall perform operational checks of the following: UPS interface, battery monitoring system, electrical bypass systems (external & UPS internal), UPS automatic transfer and load test.
2.2.4 The contractor shall perform any manufacturer firmware updates for the UPS and verify operation.
2.2.5 The Contractor shall perform corrective actions necessary to ensure full operation of the system, except where replacement parts are needed.
2.2.6 The Contractor shall provide a report to document the installation and all UPS findings and repairs.
2.3 TASK THREE – UPS Battery Disposal
The contractor shall dispose of used batteries in accordance with all local, State and Federal Environmental Protection Agency (EPA) standards.
3.0 TECHNICAL SPECIFICATIONS
3.1 Current UPS System AND BATTERY
UPS System Liebert eXM Uninterruptible Power System - 30kVA, 208V Model: 47SA030DAC02115 Serial: M17AZB0018
UPS Battery Cabinet Leibert eXM Battery Cabinet Model Number: 47BEDTA61L10097 Serial Number: M17ACG0044 Volts: 288 Amps: 139
Current Battery Information Manufacturer: C&D Technologies Model number: UPS12-350MR Volts: 12 Ampere-Hour: 93AH (20 hour rate to 1.75VPC @77'F Watt-Hour: 350 WPC (15 Minute rate to 1.67VPC @ 77'F Float Charge Voltage: 13.5 to 13.8 VDC @ 77'F (25'C) IEC Rating: 85.7AH (10 hour rate to 1.80 VPC @ 20'C)
4.0 CONTRACTOR PERSONNEL
4.1 QUALIFIED PERSONNEL
The Contractor shall provide qualified personnel to perform all requirements specified in this SOW.
Personnel shall be certified by Vertiv Group Corp in working on Liebert UPS systems.
4.2 EMPLOYEE IDENTIFICATION
4.2.1 Contractor employees visiting Government facilities shall comply with all Government escort rules and requirements. All Contractor employees shall identify themselves as Contractors when their status is not readily apparent and display all identification and visitor badges in plain view above the waist at all times.
4.2.2 The contractor shall provide a list of employees that will be working on site prior to entering the facility.
4.2.3 All contractor employees will sign in using the office visitor log book.
4.2.5 All contractor employees shall be escorted by federal personnel while on site.
4.3 EMPLOYEE CONDUCT
Contractor’s employees shall comply with all applicable Government regulations, policies and procedures (e.g., fire, safety, sanitation, environmental protection, security, “off limits” areas, etc.)
when visiting or working at Government facilities. The Contractor shall ensure Contractor employees present a professional appearance at all times and that their conduct shall not reflect discredit on the United States or the Department of Commerce. The Contractor shall ensure Contractor employees understand and abide by Department of Commerce established rules, regulations and policies concerning safety and security.
4.6 REMOVING EMPLOYEES FOR MISCONDUCT OR SECURITY REASONS
The Government may, at its sole discretion (in coordination with the Contracting Officer where practical), direct the Contractor to remove any Contractor employee from NOAA facilities for misconduct or security reasons. Removal does not relieve the Contractor of the responsibility to continue providing the services required under the contract. The Contracting Officer will provide the Contractor with a written explanation to support any request to remove an employee.
5.0 OTHER APPLICABLE CONDITIONS
5.1 PERIOD OF PERFORMANCE
The period of performance for this contract is 90 days from the date of award.
5.2 PLACE OF PERFORMANCE
The primary place of performance will be at the WFO Guam office located at:
Weather Forecast Office Guam 3232 Hueneme Road Barrigada, Guam 96913
5.3 HOURS OF OPERATION
Contractor employees shall generally perform all work between the hours of 7:00 a.m. and 4:00 p.m.
ChST, Monday through Friday (except Federal holidays). However, there may be occasions when Contractor employees shall be required to work other than normal business hours, including weekends and holidays, to fulfill requirements under this SOW.
5.4 TRAVEL
Contractor will support any travel involved.
5.5 POST AWARD CONFERENCE
The Contractor shall attend a Post Award Conference with the Contracting Officer and the TPOC no later than 14 business days after the date of award. The purpose of the Post Award Conference is to discuss technical and contracting objectives.
5.6 FINAL INSTALLATION AND TEST REPORT
The Contractor shall provide a final report to the Contracting Officer and TPOC via electronic mail. This report shall include a summary of all Contractor work performed and any Contractor concerns or recommendations.
5.7 GENERAL REPORT REQUIREMENTS
The Contractor shall provide all written reports in electronic format with read/write capability using applications that are in Microsoft Word or PDF format.
5.8 TECHNICAL POINT OF CONTACT
The government’s TPOCs are:
To be advised at award.
6.0 GOVERNMENT TERMS & DEFINITIONS
EPA - Environmental Protection Agency NEC – National Electric Code NOAA – National Oceanic and Atmospheric Administration NWS – National Weather Service TPOC – Technical Point Of Contact UPS - Uninterruptible Power Supply WFO – Weather Forecast Office
7.0 GOVERNMENT FURNISHED RESOURCES
The Government will not furnish any resources to the Contractor in support of this contract.
8.0 CONTRACTOR FURNISHED PROPERTY
The Contractor shall furnish all labor, materials and equipment necessary to fulfill the requirements of this contract.
9.0 GOVERNMENT ACCEPTANCE PERIOD
The TPOC will review deliverables prior to acceptance and provide the contractor with an e-mail that provides documented reasons for non-acceptance. If the deliverable is acceptable, the TPOC will send an e-mail to the Contractor notifying it that the deliverable has been accepted.
9.1 The TPOC will have the right to reject or require correction of any deficiencies found in the deliverables that are contrary to the information contained in the Contractor’s accepted proposal. In the event of a rejected deliverable, the Contractor will be notified in writing by the TPOC of the specific reasons for rejection. The Contractor may have an opportunity to correct the rejected deliverable and return it per delivery instructions.
9.2 The TPOC will have 5 business days to review deliverables and make comments. The Contractor shall have 5 business days to make corrections and redeliver.
9.3 All other review times and schedules for deliverables shall be agreed upon by the parties based on the final approved Project Plan. The Contractor shall be responsible for timely delivery to Government personnel in the agreed upon review chain, at each stage of the review. The Contractor shall work with personnel reviewing the deliverables to assure that the established schedule is maintained.
10.0 DELIVERABLES
The Contractor shall consider items in BOLD as having mandatory due dates.
ITEM SOW REFERENCE DELIVERABLE / EVENT DUE BY DISTRIBUTION
1 4.5 Post Award Conference 14 days after award N/A
2 3.2.3 List of personnel 7 days before entering facility TPOC
3 4.6 Final Installation and Test Report
7 days after completion of work
TPOC, Contracting Officer
Section IX - Contract Clauses
Summary of Clause Changes:
Clause 52.212-1 is incorporated as follows:
FAR 52.212-1 Instructions to Offerors - Commercial Products and Commercial Services. (SEP 2023)
NOTICE TO OFFERORS: Instructions for submitting quotations under this request for quote must be followed. Failure to provide all information to aid in the evaluation may be considered non-responsive.
Offers that are non-responsive may be excluded from further evaluation and rejected without further notification to the offeror.
1. Submit PDF or Microsoft Word format quotations to the office specified in this solicitation at or before the time specified in the solicitation. Quote documents shall include signed copies of the SF 18 and SF 30(s) to acknowledge the solicitation and any applicable amendments. Email quotes are required and can be sent to Katy.reano@noaa.gov.
2. Offeror shall have an active registration in the System for Award Management (SAM found at https://sam.gov/content/home) in order to provide a quote and be eligible for award. Must provide their UEID/CAGE CODE with their quote.
3. Offerors shall assume that the Government has no prior knowledge of them or their capability.
4. Offerors must provide all evaluation criteria in accordance with FAR 52.212-2. Offerors who do not provide all evaluation criteria may not be considered.
1. Technical Approach and Capability
2. Past Performance
3. Price
4. Personnel Certification
“THE GOVERNMENT DOES NOT ACCEPT RESPONSIBILITY FOR NON-RECEIPT OF QUOTES. IT IS THE CONTRACTOR’S RESPONSIBILITY TO REQUEST AND RECEIVE A CONFIRMATION OF THE QUOTE RECEIPT”.
Clause 52.212-2 is incorporated as follows:
FAR 52.212-2 Evaluation - Commercial Products and Commercial Services. (NOV 2021)
Offers will be evaluated based on price and the factors set forth in paragraph (a).
The evaluation will consider the Non-Price Technical Solution (Technical Approach and Past Performance) to be significantly more important than price. However, as quotes are determined to be more equal in the non-price evaluation factor, price becomes more important and may become the determining factor for award. If, at any stage of the evaluation, all vendors are determined to have submitted equal, or virtually equal, Non-Price Technical Solutions, price could become the factor in determining which vendor will receive the award.
The Government intends to evaluate the quotes and award a purchase order based on the Offeror’s initial quote; therefore, the Offeror’s initial quote should contain the Offeror’s best terms from a Non- Price Technical Solution and price standpoint.
The Government reserves the right not to award a purchase order depending on the quality of the quote(s) submitted and the availability of funds. Furthermore, the Government may waive informalities and minor irregularities or omissions in quotes received.
The Government may make award to other than the lowest-priced Offeror or the Offeror with the highest technical rating if the Contracting Officer determines that to do so would result in the best value to the Government. The Government will not make an award at a significantly higher overall price to achieve only slightly superior performance capability.
(a) The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered.
Paragraph (a) is hereby completed as follows: Evaluation will be based on the following:
1. Technical Approach and Capability.
The Offeror’s overall technical approach will be evaluated to assess the Government's level of confidence in the Offeror’s understanding of, approach to, and ability to successfully perform the requirements as described in the Statement of Work. Provide a detailed description of the company’s experience performing similar services. A detailed technical approach write-up describing how the Offeror will perform this service is required to be submitted with the quote regardless of whether a site visit was made or not. The technical approach write-up must not be a reiteration of the Statement of Work, but how your company plans on performing the tasks listed in the attached Statement of Work. (i.e. performance checklists, anticipated number of employees, anticipated hours at the facility and/or confirmation of supplies being provided, etc.)
2. Past Performance.
Quote shall include at least two references from at least two separate contracts for similar and relevant recent services within the past two years including the name, phone number, full address, and e-mail address of the reference to demonstrate the offeror’s capability to successfully perform the services listed in the Statement of Work.
The offeror is required to fill out blocks 1-4 and send the attached Past Performance Questionnaire to the references provided by the offeror in their submission. The references should complete the Past Performance Questionnaire and then email it directly to Katy.reano@noaa.gov by the closing date and time of this solicitation. The Government reserves the right to consider past performance report forms received after the due date and time of the solicitation, past performance questionnaires submitted from previous solicitations, and to contact references for verification or additional information.
The Offeror's past performance on related contracts will be evaluated to determine, as appropriate, successful performance of contract requirements, quality and timeliness of delivery of goods and services, cost management, communications between contracting parties, proactive management and customer satisfaction. The Government will use its discretion to determine the sources of past performance information used in the evaluation, and the information may be obtained from references provided by the Offeror, the agency’s knowledge of Offeror performance, other government agencies or commercial entities, or past performance databases, and will be based on responsiveness, quality, and customer services.
Offerors lacking relevant past performance history, or for whom past performance information is either not available or has not been submitted to the Government, will receive a neutral rating for past performance. A good past performance rating provides higher confidence than a neutral or satisfactory rating.
3. Price.
The Government will evaluate the price quote for completeness and reasonableness in relation to the RFQ requirements. Quoted prices must be entirely compatible with the Non-Price Technical Solution.
4. Certification.
The Contractor personnel performing all requirements specified in this SOW shall be certified by Vertiv Group Corp in working on Liebert UPS systems.
The Government intends to award a trade-off, single firm fixed-price purchase order on an all or none basis with payment terms of Net 30.
(b) Options. The Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. The Government may determine that an offer is mailto:Katy.reano@noaa.gov unacceptable if the option prices are significantly unbalanced. Evaluation of options shall not obligate the Government to exercise the option(s).
(c) A written notice of award or acceptance of an offer, mailed or otherwise furnished to the successful offeror within the time for acceptance specified in the offer, shall result in a binding contract without further action by either party. Before the offer’s specified expiration time, the Government may accept an offer (or part of an offer), whether or not there are negotiations after its receipt, unless a written notice of withdrawal is received before award.
(End of provision)
| Amendment of solicitation/modification of contract |
| Contract ID code |
| Amendment/modification number |
| Effective date |
| Requisition/purchase requisition number |
| Project number |
| Issued by |
| Code |
| Administered by |
| Code |
| Name and address of contractor |
| Code |
| Facility code |
| Amendment of solicitation number |
| Dated |
| Modification of contract/order number |
| Dated |
| This item only applies to amendments of solicitations |
| Accounting and appropriation data |
| This item applies only to modifications of contracts/orders. |
| This change order is issued pursuant to: |
| The above numbered contract/order is modified to reflect the administrative changes |
| This supplemental agreement is entered into pursuant to authority of: |
| Other |
| Important: |
| Description of amendment/modification |
| Name and title of signer |
| Contractor/offeror |
| Date signed |
| Name and title of contracting officer |
| Signature of Contracting Officer |
| Date signed |
| Previous edition unusable |
| Standard form 30 (rev. 11/2016) |
| Continuation sheet |
| Reference Number |
| Name of Offeror or Contractor |
| OPTIONAL FORM 336 (4-86)) |
Sponsored by GSA FAR (48 CFR) 53.110
File details come from the government source that posted it. Updated .