SFC_MACC_Offer_Schedule_00015.pdf
PDF 33 KB Posted
- Attached to
- MACC for SFC ABQ area Federal contract opportunity
- Solicitation number
- 13-161-SOL-00015
About this file
Offer Schedule
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_3_Attachment_5_--_Updated_Schedule_Revision_3.pdf | ||
| Offer_Schedule_-_Revision_3_2013_06-20.pdf | ||
| Offer_Schedule_-_Revised_2013_06-06__.pdf | ||
| MACC_13_161_SOL_00015_PPQ_Only.doc | DOC document | |
| Amendment_2_Attachment_4_--_Due_date_change.pdf | ||
| Amendment_1_Attachment_3_--_site_time_change.pdf | ||
| MACC_13_161_SOL_00015_3_May__2013_SFC_FINAL_Draft_with_dates_and_times.pdf | ||
| Construction_Specifications_AL-12-143.pdf | ||
| Sheet All 22 pages.pdf | ||
| IHS_AAO_Standard_Specifications_and_Details_AUGUST_2012.pdf | ||
| SFC_MACC_SOW_00015.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offer Schedule Mescalero Summit & Fence Canyon Water Mains Mescalero Apache Tribe, NM IHS Project No. AL-12-143
No. Item Description Quantity Unit Unit Cost Total Cost Schecule A - Summit Water Main
1 Connection to existing water main 3 EA
2 8" PVC water main & fittings 5,126 EA
3 6" PVC water main & fittings 1,775 EA
4 2" PVC water main & fittings 20 LF
5 8" Gate valve & box 5 EA
6 6" Gate valve & box 4 EA
7 2" Gate valve & box 1 EA
8 Air relief valve 1 EA
9 HWY 70 Road bore w/ 18" I.D. steel casing 164 LF
10 Fire hydrant & gate valve assembly 3 EA
11 Water main tap, service saddle, corp stop 5 EA
12 Curb stop & riser 5 EA
13 1" PE water service line 1,000 LF
14 Water meter & box combination 4 EA
Schedule B: Fence Canyon Water Main
15 Connection to existing water main 1 EA
16 4" PVC water main & fittings 5,445 EA
17 4" Gate valve & box 4 EA
18 Flush hydrant & gate valve assembly 1 EA
19 Water main tap, service saddle, corp stop 5 EA
20 Curb stop & riser 5 EA
21 1" PE water service line 750 LF
22 Water meter & box combination 5 EA
Page 1 of 2 of Offer Schedule
23 Booster pump enclosure 1 LS
24 Electrical system 1 LS
25 Booster pump system 1 LS
Schedule C: Miscellaneous
26 Mobilization/demobilization 1 LS
27 Rock excavation 200 YD
Preparation of Storm Water Pollution Prevention Plan (SWPPP)
1 LS
29 Implementation of SWPPP 1 LS
Construction Subtotal =
NMGRT (Otero County) =
Total Bid =
TOTAL OFFER IN WRITING:
SUBCONTRACTORS:
Page 2 of 2 of Offer Schedule