1309208-event.pdf
PDF 267 KB Posted
- Attached to
- Orchard Diversion Pipeline
- Solicitation number
- JUS-LimtSol-2025-0280
- Issued by
- Broadwater County, Montana
About this file
The document is a limited solicitation from the State of Montana Natural Resource Damage Program (NRDP) for the 2025 Orchard Diversion Pipe System Installation project in Carbon County, Montana. The solicitation seeks a construction contractor to remove and replace an existing pipeline near Bridger, MT, with work including mobilization/demobilization, procurement of materials, excavation, removal of existing pipe, and installation of a new pipe system. The project is scheduled for release on 4/22/2025, with bids opening at 12:30 PM MDT and closing on 5/1/2025 at 5:00 PM MDT. A non-mandatory pre-bid conference and project walk-through will be held on 4/28/2025 at 1:00 PM at the project site, with the desired completion date of June 30, 2025.
The solicitation will evaluate bids based on project cost, with the lowest bid from responsive and responsible bidders selected. The project uses US Dollars and covers multiple commodity codes including agricultural services, building and construction services, engineering services, and water-related services. Bidders must submit prices for two line items: mobilization/demobilization and earthwork/procurement/installation of the pipe system, both as lump sum items. The contact for the solicitation is Erin Ricci, who can be reached at Erin.Ricci@mt.gov or +1 406-444-5667. Detailed project specifications and requirements are available in the attached draft contract and supporting documents.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
22 April 2025
Orchard Diversion Pipeline Mobilization/demobilization, excavation/earthwork, and procurement/installation of the Orchard Diversion Pipe System near Bridger, MT.
22 April 2025
Released 4/22/2025 12:00 PM MDT Type Limited Solicitation Open 4/22/2025 12:30 PM MDT Number JUS-LimtSol-2025-0280 Close 5/1/2025 5:00 PM MDT Currency US Dollar
Sealed Until 5/1/2025 5:00 PM MDT
Contacts Erin Ricci Erin.Ricci@mt.gov
Phone +1 406-444-5667
Commodity Codes Commodity Code Description 0103 Agricultural - Services 0515 Building & Construction - Services 1504 Engineering - Services 5303 Water - Irrigation Systems & Pumps 5307 Water - Services
22 April 202522 April 202522 April 202522 April 202522 April 202522 April 202522 April 202522 April 202522 April 2025 mailto:Erin.Ricci@mt.gov
2025 Orchard Diversion Pipe System Installation Carbon County, Montana
The State of Montana Natural Resource Damage Program (NRDP), is conducting a limited solicitation for construction contractors. The draft Contract, found under Buyer Attachments, contains a Scope of Work with a detailed description of the project. All responses must comply with the instructions and procedures contained herein.
NRDP seeks a Contractor to provide all labor, equipment, and materials to execute the work associated with removal and replacement of an existing pipeline near Bridger, Montana, as shown in Appendix A of the draft Contract. Work will include mobilization/demobilization, procurement of materials, excavation and removal of existing pipe, and installation of new pipe system as described in draft Contract. Requested services and deliverables are contained herein.
Additional detail is included within the draft Contract and Scope of Work. Within the eMACS bid items, submit prices for each bid item. Prices for all bid items must include all labor, supplies, and incidentals.
Project Schedule: Contractor must provide a detailed schedule, including start date and completion date. It is desired that the pipeline replacement be completed by June 30, 2025.
Pre-Bid Walkthrough
A Non-Mandatory pre-bid conference and Project walk-through will be held at the Project Site at 1:00 P.M.
Mountain Time on April 28, 2025. All prospective bidders are encouraged to attend. There will NOT be access to the project site during bidding except for the pre-bid conference. Persons with disabilities seeking accommodations may contact NRDP to make a request, 406-444-0205.
Submittal:
A bid that does not include all bid items will not be considered.
Responses to this limited solicitation will be evaluated by the project cost. The lowest bid from the responsive and responsible bidders received will be selected.
The Contractor will be required to enter into an agreement substantially similar to the draft Contract.
Description
Required to View Event
Prerequisites Required to Enter Bid
22 April 2025
1. Review and Accept the Q&A Board Information
2. Review and accept the Single Point of Contact information.
3. Bidder has reviewed all attachments in the Buyer Attachments section of eMACS.
4. Please review and accept the prevailing wage requirements.
22 April 202522 April 202522 April 202522 April 202522 April 202522 April 202522 April 2025
Buyer Attachments
1. 2025 Orchard Diversion Pipe System Installation Draft Contract and Scope of Work .pdf
2. C-01 - Pipe Replacement-TT-BS-22x34hz rev2.pdf
3. Information+Required_2025 Orchard Diversion Pipe System.docx
22 April 202522 April 202522 April 202522 April 202522 April 202522 April 2025 https://bids01.jaggaer.com/apps/Router/PublicEventDownload?file=U291cmNpbmdldmVudC8xMzA5MjA4LTE4MDY5MDc4MzcyMDI1IE9yY2hhcmQgRGl2ZXJzaW9uIFBpcGUgU3lzdGVtIEluc3RhbGxhdGlvbiBEcmFmdCBDb250cmFjdCBhbmQgU2NvcGUgb2YgV29yayAucGRm&auth=MDpBRVMyI0NQNVp4a2IvSnkxZDNIUm81TGpka2h4M0V4bkpBZDlVSkVFUnk5WnZrK2l5eGZjOVRGNkRHUlU9 https://bids01.jaggaer.com/apps/Router/PublicEventDownload?file=U291cmNpbmdldmVudC8xMzA5MjA4LTE4MDY5MDkzNjZDLTAxIC0gUGlwZSBSZXBsYWNlbWVudC1UVC1CUy0yMngzNGh6IHJldjIucGRm&auth=MDpBRVMyI0NQNVp4a2IvSnkxZDNIUm81TGpka2h4M0V4bkpBZDlVSkVFUnk5WnZrK2l5eGZjOVRGNkRHUlU9 https://bids01.jaggaer.com/apps/Router/PublicEventDownload?file=U291cmNpbmdldmVudC8xMzA5MjA4LTE4MDY5MDk5NTBJbmZvcm1hdGlvbitSZXF1aXJlZF8yMDI1IE9yY2hhcmQgRGl2ZXJzaW9uIFBpcGUgU3lzdGVtLmRvY3g%3D&auth=MDpBRVMyI0NQNVp4a2IvSnkxZDNIUm81TGpka2h4M0V4bkpBZDlVSkVFUnk5WnZrK2l5eGZjOVRGNkRHUlU9
Questions Required Questions
There are no Questions added to this event.
22 April 202522 April 202522 April 202522 April 202522 April 2025
Product Line Items Product Line Items
There are no Items added to this event.
22 April 202522 April 202522 April 202522 April 2025
Service Line Items Service Line Items
1.
# Item Name, Commodity Code, Description Allow
Alternates Qty. UOM Requested Service Delivery
S1 Bid Item 1, Mobilization/Demobilization 1 LS - Lump Sum
See Scope of Work, Attachment A to draft Contract
S2 Bid Item 2,Earthwork and Procurement/Installation of Pipe System 1 LS - Lump Sum
See Scope of Work, Attachment A to draft Contract
22 April 202522 April 202522 April 2025
File details come from the government source that posted it. Updated .