This is a Statement of Work (SOW) for the National Oceanic and Atmospheric Administration (NOAA) National Weather Service Forecast Office in Pittsburgh, PA under RFQ 1305M327Q0061. The SOW outlines three separate projects at the facility in Moon Township, PA: (1) Generator sound barrier wall repair comprising approximately 600 square feet of masonry wall rehabilitation including top course removal and replacement, surface preparation, mortar repairs, and repainting both sides with tan-colored breathable acrylic masonry paint; (2) Window film installation of VS20 spectrally-selective architectural film on 19 rectangular glass panels, 2 triangular panels, and 1 door to improve energy efficiency; and (3) Interior repainting of approximately 7,000 combined square feet of walls and metal doors across 19 work areas on two levels, including removal of carpet wall covering on 280 square feet requiring full surface preparation.

The contractor must provide all labor, tools, supplies, materials, transportation, and supervision required for performance. All work must comply with specific surface preparation, priming, and paint application standards including SSPC PA Guide 10, NFPA 70E, and 29 CFR 1910 safety requirements. The contractor is responsible for submitting Safety Data Sheets, product specifications, and color samples for Government approval prior to work commencement, and must provide before and after photographs. The period of performance is 180 calendar days after notice to proceed, with standard working hours of 8:00 AM to 5:00 PM Monday through Friday, though work outside these hours may be required with advance written approval. The place of performance is the National Weather Service Forecast Office, 192 Shafer Road, Moon Township, PA 15108. A Post Award Conference must be held within 10 business days of award, and a final project plan must be submitted within 10 business days after that conference. The Technical Point of Contact is Jeremy Cordie (jeremy.cordie@noaa.gov, 937-479-8753) and the Local Point of Contact is Tom Plecha (thomas.plecha@noaa.gov, 412-262-1591).

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

National Oceanic and Atmospheric Administration (NOAA) Statement of Work (SOW)

National Weather Service Forecast Office (WFO), Pittsburgh, PA (PBZ) Projects

RFQ 1305M327Q0061

1.0 GENERAL

The National Weather Service (NWS) Eastern Region has a requirement for the following projects at the National Weather Service Forecast Office (WFO), Pittsburgh, PA (PBZ):

A. Generator sound barrier wall repair to reduce, block, and absorb noise pollution caused by the backup generator (Moon Township, PA);

B. Window film installation to boost energy efficiency (Moon Township, PA); and C. Repaint existing interior painted walls and doors (Moon Township, PA).

The contractor shall provide the labor, tools, supplies, materials, transportation, services, and supervision required to perform all work outlined in this SOW. The Contractor is to perform a visual inspection of current site conditions prior to the start of any work. The Contractor shall sign off on every specified task in the SOW and provide signed typewritten copies of all reports, and site photos to the Technical Point of Contact (TPOC) and Contracting Officer (CO), as outlined in Section 9.0. If there are discrepancies in this document, the Contactor shall ask for a clarification from the TPOC prior to bid. If no clarification is requested, the CO’s judgement shall rule.

The TPOC is to be contacted and briefed prior to starting work. The Contractor is not to make any modifications to equipment owned by the Government under this contract.

2.0 TASKS / REQUIREMENTS

2.1 TASK ONE. Generator sound barrier wall repair.

Approximately six hundred (600) sq ft of sound barrier wall requires re-habilitation which includes surface preparation, removal / replacement of the top course with new block, and re-painting of both sides of the structure. Approximate wall dimensions: 27 ft overall length,10 ft height.

2.1.1 Specific Requirements

A. MASONRY WALL SELECT DEMOLITION

1. The Contractor shall remove the entire top course of the damaged block wall.

B. MASONRY WALL REPAIR

1. The Contractor shall install a new row of solid brick with mortar. Top course shall have a slight taper outward for water runoff.

C. MASONRY WALL PREPARATION AND CLEANING

1. The Contractor shall prepare surfaces as follows:

a. GENERAL PREPARATION:

i. Clean surfaces to remove grease, oil and other deterrents to paint adhesion.

b. MASONRY SURFACE PREPARATION:

i. Prepare all concrete surfaces for new paint application by using a scraper, power washer, stiff brush, chemicals or other means recommended by the paint manufacturer to remove dirt, loose or peeling paint, mildew, chalky residue and efflorescence. Patch any cracks or holes with hydraulic cement as per manufacturer’s recommendations.

ii. Power wash and clean sound barrier wall to include removing loose/chipping paint.

iii. Contractor shall allow the wall to dry completely.

D. MASONRY WALL MORTAR REPAIRS

1. The Contractor shall:

a. Patch all holes and deteriorated mortar joints with an acrylic concrete patch, and gaps wider than 1/16" shall be sealed using an elastomeric masonry caulk, including, the base of the wall at the foundation.

b. Fill and repair large cracks with masonry caulk or equivalent.

c. All product selections must accept paint.

E. EXTERIOR CONCRETE COATINGS

1. The Contractor shall apply paints as follows:

a. PRIMING: Contractor shall apply one (1) full coat of a premium, alkali-resistant acrylic masonry primer to the entire block wall.

b. PAINTING: Contractor shall:

i. Apply finish coats of breathable, 100% acrylic exterior masonry paint. Paint shall be applied via rollers, brushes and/or sprayer and back-rolled to achieve uniform coverage and fill the porous block profile. Apply a minimum of two (2) coats of paint to ensure uniform coverage.

ii. After the second coat, carefully inspect the entire surface for pinholes. Spot coat these areas with an additional coat until the surface is uniform in appearance.

iii. Paint shall be a match existing color; tan. Submit for approval the color selection prior to the purchase of paint and the start of work.

2.1.2 Additional Information

A. Paint Products: deliver materials to the work site in manufacturer’s sealed container(s) labeled to show the name of manufacturer, product type, batch number, instructions for use, and safety precautions.

2.1.3 Submittals

A. The Contractor shall prepare and submit all products planned for use during the course of this contract. Submittals shall be sent directly to the TPOC via electronic mail. The actual product selection must be highlighted and clearly shown on each submittal. The Contractor shall not proceed with work or procure any products or materials until the submittal(s) are reviewed by the Government. Any work or activity undertaken prior to review shall be at the Contractor’s own risk.

Should the CO subsequently determine the work or activity does not comply with the contract, the Contractor shall be responsible for all costs and time required to comply with the CO’s determination. CO shall have the right to order the Contractor to cease execution of work for which submittals have not been reviewed. The Government shall not be liable for any cost or delay incurred by the Contractor attributable to the proper exercise of this right.

B. The contractor shall confirm all paint colors prior to any application in the field. After painters' materials have been approved and before work is started, the contractor shall submit a sample showing each type of finish and color.

C. Review of submittals will be general and shall not be construed as permitting any departure from the contract requirements.

1305M327Q0061 SOW Page 2 of 12

D. The Contractor shall identify in writing, all deviations or changes in re-submitted submittal(s). In the absence of such written notice, review of a submission shall not include or apply to such deviations or changes.

E. The Contractor shall provide a Safety Data Sheet (SDS) to the TPOC for all products and chemicals planned for use by their workers while on-site. The SDS will be reviewed and filed by the TPOC in the project file.

2.1.4 Applicable Documents

A. The following documents provide specifications, standards, or guidelines that must be complied with in order to meet the requirements of this contract:

1. NFPA 70E, Standard for Electrical Safety in the Workplace (National Fire Protection Association 2021)

2. 29 CFR 1910, Occupational Safety and Health Standards (Occupational Safety and Health Administration 1970)

3. Exterior Water-Borne Acrylic Latex Paint

a. coating products shall be ready-mixed

b. exterior acrylic for application directly to properly prepared, previously painted

c. vertical concrete and masonry walls

i. product selection must be manufacturer compatible and made to be used with the primer selection.

d. penetrating, alkali-resistant masonry conditioning primer/sealer for application over weathered, chalky, and bare concrete surfaces prior to a body coat

4. Safety Methods Used During Paint Application: Comply with the requirements of SSPC (STANDARD by Society for Protective Coatings) PA Guide 10

a. Surface Preparation:

i. clean surfaces to remove grease, oil and other deterrents to paint adhesion in accordance with SSPC-SP 1 Solvent Cleaning

ii. remove loose mill scale, rust, and paint, by hand or power tool cleaning, as defined in SSPC-SP 2 Hand Tool Cleaning and SSPC-SP 3 Power Tool Cleaning

iii. Prepare masonry walls before coating as defined in SSPC-SP13.

iv. Fill all cracks/voids in block joints with a suitable exterior-grade sealant or patching compound.

v. Rake out and fill damaged mortar joints (repointing) to ensure a solid surface.

b. Toxic Materials: to protect personnel from overexposure to toxic materials, conform to the most stringent guidance of:

i. applicable manufacturer’s Safety Data Sheets (SDS) or local regulation

ii. 29 CFR 1910.1000

iii. ACGHI-BKLT and ACGHI-DOC, threshold limit values

iv. Appendix A, photos of existing conditions

2.1.5 Material Requirements

A. General requirements for materials not previously detailed:

1. DRYLOK® Extreme Concrete & Masonry Waterproofer

2. Sherwin-Williams Exterior Acrylic Latex Paint

3. Manufacturers’ product names are intended to describe the standard of quality, performance, functionality or other characteristics needed to meet the requirements and are not intended to limit or restrict competition.

2.1.6 Painting Requirements

1305M327Q0061 SOW Page 3 of 12

A. Preparation

1. Perform cleaning procedures and surfaces in strict accordance with the paint manufacturer’s instructions.

2. Properly prepare all surfaces to receive touch-up of prime coat, body and top coats. The final surface shall be smooth and void of any paint ridges.

a. Wipe down all surfaces and surrounding areas before painting is started

b. Prior to paint, all surfaces are to be completely dry, clean and smooth

B. Atmospheric and Surface Conditions

1. Application shall only be completed on dry and frost-free surfaces. Do not apply coating when air or substrate conditions are:

a. less than 3 degrees C (5 degrees F) above dew point

b. less than 10 degrees C (50 degrees F) or over 35 degrees C (95 degrees F), unless specifically pre-approved by the TPOC and the product manufacturer.

c. when the relative humidity exceeds 85 percent; or to damp or wet surfaces; unless otherwise permitted by the paint manufacturer’s printed instructions.

d. Do not apply exterior painting when it is windy and dusty.

2. Under no circumstances are application conditions to exceed manufacturer recommendations

C. Paint Products

1. finish coats must be compatible with selection of prime paints

2. thoroughly mix painting materials to ensure uniformity of color, complete dispersion of pigment and uniform composition

3. do not thin unless necessary for application and when finish paint is used for body coat (use materials and quantities for thinning as specified in manufacturer's printed instructions)

4. remove paint skins, then strain paint through commercial paint strainer to remove lumps and other particles

5. follow manufacturer’s instructions and guidelines

D. Applications

1. Apply coatings by brush, roller, or spray

a. After surface preparation, prime all surfaces before application of body and finish coats, except as otherwise specified.

2. Unless otherwise specified, apply paint in two (2) coats to painted surfaces; body, and finish.

When two (2) coats of the same paint type are applied to a painted surface, the first coat applied is the body and the second coat is the finish.

a. body coat must be smooth before applying succeeding coat(s)

b. apply each coat evenly and cover the substrate completely

c. allow not less than 48 hours between application of succeeding coats, except as allowed by manufacturer's instructions, and approved by TPOC

3. When stains, dirt, discolorations or undercoats show through a finish coat, additional coats of paint shall be applied by the Contractor at no additional cost to the Government until the finish coat is of a uniform color and appearance. This may require some additional surface preparation by the Contractor prior to applying another coat. The finish coat shall be smooth and uniform upon completion of all work.

1305M327Q0061 SOW Page 4 of 12

a. All coats are to be dry to manufacturer’s recommendations before applying succeeding coats.

4. Protection, Clean Up, and Touch-Up

a. The Contractor shall protect in-progress or completed work at all times. The

Contractor shall also protect adjacent work areas, infrastructure and equipment.

b. Upon completion, clean paint from all hardware and other surfaces or items not required to be painted from any paint drops or smears

c. Before final inspection, all touch-up or refinished areas MUST produce solid even color and a smooth texture finish, free from defects in workmanship

2.1.7 Quality Control

A. Examine the areas and conditions where painting and finishing are applied and correct any observed deficiencies immediately that are detrimental to the proper and timely completion of work. Do not proceed with the work until unsatisfactory conditions are corrected to permit proper installation of the work.

B. It is the contractor’s responsibility to inform the Government of any failed preparations, paint coatings, or work deficiencies. Any re-work must be brought to the attention of the Local Point of Contact (LPOC) and TPOC.

C. The contractor shall re-paint individual areas which are not approved, as determined by the TPOC, until approval is received and work is deemed acceptable.

D. The Contractor shall be held wholly responsible for the finished appearance and satisfactory completion of painting work.

E. Inspections will be performed by the LPOC. Final acceptance will be by the TPOC.

2.2 TASK TWO. Window film installation.

The scope of service includes installation of type VS20 film on nineteen (19) rectangular glass panels, two

(2) triangle glass panels, and one (1) door. The building will remain completely operational with staff during this work. Ingress/egress to facility and pedestrian walkways must be maintained for use. All employees, visitors, building interiors and Government equipment must be fully protected at all times during this construction work.

2.2.1 Specific Requirements

A. PRE-INSPECTION AND MEASUREMENTS

1. The contractor shall measure and verify all glass panel sizes in the field prior to ordering or cutting any window film and/or starting any work.

B. GLASS PREPARATION

1. The contractor shall temporarily remove existing window treatments and clean glass surfaces.

C. WINDOW FILM INSTALLATION

1. SPECIFICATION

a. The Contractor shall use film type VS20 spectrally-selective architectural window film. It shall be specifically engineered to reject high levels of solar heat while maintaining maximum visible light transmission and optical clarity. Overall window area is approximately 38 feet x 8.5 feet (includes frames). The overall door is approximately 27” x 68”.

1305M327Q0061 SOW Page 5 of 12

b. The contractor shall install nine (9) rectangular films on top glass window panels.

The approximate size is 36" x 45" each, not all are identical in measurement.

c. The contractor shall install ten (10) rectangular films on bottom glass window panels. The approximate size is 36" x 72" each, not all are identical in measurement.

d. The contractor shall install two (2) triangular films on corner/side glass window panels. The approximate size is 27" x 36" each.

e. The contractor shall install one (1) rectangular film on glass door panels. The approximate size is 27" x 68" each.

D. WINDOW TREATMENT RE-INSTALLATION

1. The contractor shall reinstall window treatments as they were before work began.

2.2.2 Additional Information

A. The Project Manager shall provide a field report to the TPOC and LPOC via electronic mail. This report shall include a summary of all Contractor work, photos, product specification datasheets, use and care guidelines, product warranty, and any Contractor concerns or recommendations.

2.2.3 Submittals

A. The Contractor shall provide a Data Sheet (DS) to the TPOC and LPOC for all products planned for use by their workers while on-site. The DS will be reviewed and filed by the TPOC and LPOC in the project file.

B. The Contractor shall discuss in advance with the TPOC and LPOC preferences for each location.

2.3 TASK THREE. Repaint existing interior painted walls and doors.

The scope of Task three is to repaint existing interior painted walls and doors at the Weather Forecast Office (WFO). The maintenance work includes: preparing surfaces for the re-coating of primer and/or paint on walls, and metal surfaces. This work areas include offices, rooms, and corridors.

Upper Level: Approximately thirteen (13) work areas. The approximate combined wall area is 4,600 sq ft.

Approximately ten (10) metal doors with jambs (both sides) on this level will require painting. Additional door jambs with wood doors will require paint on the jambs only.

Lower Level: Approximately six (6) work areas. The approximate combined wall area is 2,400 sq ft.

Approximately 280 sq ft. will require the removal of carpet wall covering. These areas will involve removal of glue, full spackle, sand and surface preparation to the area, then a final dust wipe down prior to paint.

Approximately two (2) metal doors with jambs (both sides) will require painting on this level. Additional door jambs with wood doors will require paint on the jambs only.

The building will remain completely operational with staff during this work. Ingress/egress to facility and pedestrian walkways must be maintained for use. All employees, visitors, building interiors and Government equipment must be fully protected at all times during this construction work.

2.3.1 Specific Requirements

A. Areas

1305M327Q0061 SOW Page 6 of 12

1. Upper Floor

a. All offices, rooms, corridors, stairwells, metal doors and jambs (both sides) and all other metal door jambs. All walls are 8 ft in height.

b. Note: The restroom and wood doors require NO painting.

i. Meteorologist in Charge (MIC): 14’ 2” x 12’ 6”

ii. Warning Coordination Meteorologist (WCM): 14’ 5” x 10’

iii. Waiting Area: 14’ 4”

iv. Reception Area: 8’ 10” x 10’

v. Storage Area: 10’ 5” x 10’

vi. Electronics Systems Analyst (ESA): 16’ x 13’ 6”

vii. Electronics Technicians (ELTECH): 16’ 8” x 13’ 10”

viii. Senior Service Hydrologist (SSH): 8’ x 13’ 10”

ix. Information Technology Officer (ITO): 11’ 7” x 13’ 10”

x. Stairwell: 16’ x 18’

xi. Stairwell: 8’ x 14’

xii. Multi-Purpose Room: 20’ 6” x 13’ 8”

xiii. Corridor: 72’ x 4’

2. Lower Floor

a. All corridors, rooms, offices, two (2) metal doors and jambs (both sides) and all other metal door jambs. All walls are 8 ft in height.

b. Note: The restroom, Equipment Room, Communications Room, Ready Room and wood doors require NO painting.

i. Locker Area: 16’ x 27’

ii. Science Operations Officer (SOO): 13’ x 8’

iii. Operations Area: 30’ x 35’

iv. Hydro Area: 10’ x 10’

v. HMT Desk – 15’ x 14’

vi. Corridor: 26’ x 4’

A. Surface Preparation

a. Perform cleaning procedures and surface preparations in strict accordance with the paint manufacturer’s instructions.

b. Properly prepare all surfaces to receive touch-up of prime coat, body and top coats.

Wipe down all surfaces and surrounding areas before painting is started. All surfaces are to be completely dry, clean and smooth.

c. Remove all oil, dust, grease, dirt, loose paint and other foreign material to ensure adequate adhesion.

d. Avoid dust and chemicals from surface preparation in other areas to contaminate wet paint on new freshly painted surfaces

e. Fill cracks and nail holes with patching paste-spackle and sand to achieve a level 4 finish.

f. The office space adjacent to the Operations Area will require the removal of carpet wall covering. These areas will involve glue removal, a complete spackle and sanding surface preparation.

g. Remove hardware and hardware accessories, plates, light fixtures, and items in place that are not to be painted, or provide protection such as taping, prior to surface preparation and painting. Note: If taping includes windows, door jams, etc, the contractor is responsible for any residue left behind on surfaces after removal of the tape.

h. The final surfaces shall be smooth and void of any paint ridges.

1305M327Q0061 SOW Page 7 of 12

i. Notify the TPOC of problems anticipated for any minor preparatory work required, such as but not limited to, filing nail holes, cleaning surfaces to be painted, and priming any requisite areas.

C. Primer and Top Coat Applications

1. The contractor shall:

a. Mix and prepare the paint according to the manufacturer’s directions.

b. Apply coatings by brush or roller only.

c. Prime & Paint coatings shall not be over dirt, rust, scale, grease, moisture or scuffed surfaces, or conditions detrimental to formation of a durable primer & paint film.

d. Use a high-quality semi-gloss latex paint for the metal doors and door jambs.

e. Use a high-quality egg-shell latex base paint for the following areas: Operations, hallways, vestibules, ceilings, and management’s offices.

f. Provide finish coats that are compatible with the primers used.

g. Do not apply succeeding coats until the previous coat has cured. Follow manufacturer’s recommended time frames for re-coat.

h. Apply additional coats when undercoats or other conditions show through the final coat, until paint film is of uniform finish, color and appearance.

i. Eliminate cloudiness, spotting, laps, brush marks, runs, sags, or other surface imperfections.

j. Clean up any spills immediately to avoid damages to the building.

D. Painting Application Completion

a. Visually inspect all painted surfaces for color steadfastness.

b. Clean any paint that has splattered by washing, scraping or other approved methods, using care not to scratch or damage adjacent finished surfaces.

c. Remove temporary protective wrappings taking care not to damage any existing surface or newly painted surface.

d. Remove any tape residue, where applicable.

e. At the completion of all field work, the Contractor shall remove from the area all trash, rubbish, protective coverings and debris caused by its operations, leaving the job site clean.

2.3.2 Additional Information

A. The Contractor can temporarily move the office furniture off the wall to allow for a minimum of 48” of working space around all wall surfaces. Contractor shall carefully move all free-standing office furniture, filing cabinets, and rolling chairs to the center of the room or to a designated on-site staging/storage area. After final paint inspection and acceptance, the contractor shall move the office furniture back to their original positions.

B. Contractor shall provide one (1) full unopened gallon of paint for each color used in the repainting of the building’s interior for future touch ups.

C. The contractor shall provide detailed photos of each area: BOTH before and after pictures. Pre and Post photos MUST be taken from the same positioning.

a. Pre-existing Conditions (prior to the start of work): A minimum of four (4) photos per room shall be taken.

b. Post Completion Photos: A minimum of four (4) photos per room shall be taken.

1305M327Q0061 SOW Page 8 of 12

D. The Project Manager shall meet with the TPOC at 50% completion to review the results of Contractor performance, exchange information and resolve emergent technical problems and issues.

This meeting may take place via teleconference.

E. The Contractor shall issue to the TPOC a verbal report summarizing all work that was performed before planning to de-mobilize from the site. The contractor shall also note site conditions and verify no environmental concerns are present at the site.

2.3.3 Submittals

A. The Contractor shall provide a Safety Data Sheet (SDS) to the TPOC for all products and chemicals planned for use by their workers while on-site. The SDS will be reviewed and filed by the TPOC in the project file.

B. The Contractor shall discuss in advance with the TPOC and LPOC the preference of color for each location. Sample color chips shall be submitted to the TPOC and LPOC for a color selection, up to a maximum of three (3) colors per area (e.g. Operations/Corridors, Offices, Doors/Jambs).

2.3.4 Material Requirements

A. General requirements for materials not previously detailed:

a. Sherwin-Williams Pro Interior Acrylic Coating Paint or equal

b. Sherwin-Williams PrepRite ProBlock Primer or equal

B. Manufacturers’ product names are intended to describe the standard of quality, performance, functionality or other characteristics needed to meet the requirements and are not intended to limit or restrict competition.

3.0 CONTRACTOR PERSONNEL

3.0.1 The Contractor shall provide qualified personnel to perform all requirements specified in this SOW. All work shall be performed and completed in a workmanship-like manner and in accordance with the latest proven practices of the trade by thoroughly skilled and experienced workers. Contractor personnel shall follow the written product guidance for all products applied on-site, including environmental conditions, etc.

The Contractor shall provide a Project Manager who shall be responsible for all Contractor work performed under this SOW. The Project Manager shall be a single point of contact for the Contracting Officer (CO) and the Technical Point of Contact (TPOC). The Project Manager and all designated alternates shall be able to read, write, speak and understand English. Additionally, the Contractor shall not replace the Project Manager without prior approval from the CO.

3.0.2 Contractor employees visiting Government facilities shall maintain a REAL ID and identification that, at a minimum, displays the Contractor name and the employee’s name. Visiting Contractor employees shall comply with all Government escort rules and requirements. All Contractor employees shall identify themselves as Contractor employees when their status is not readily apparent and shall display all identification and visitor badges in plain view above the waist at all times. Contractors shall sign in and out at the Weather Forecast Office upon arrival and departure daily.

3.0.3 Contractor employees shall comply with all applicable Government regulations, policies and procedures (e.g., fire, safety, sanitation, environmental protection, security, “off limits” areas, etc.) when visiting or working at Government facilities. The Contractor shall ensure Contractor employees present a professional appearance at all times and that their conduct shall not reflect discredit on the United States or the Department of Commerce. The Project Manager shall ensure Contractor employees understand and abide by Department of Commerce established rules, regulations and policies concerning safety and security.

1305M327Q0061 SOW Page 9 of 12

3.0.4 The Government may, at its sole discretion (in coordination with the Contracting Officer where practical), direct the Contractor to remove any Contractor employee from NOAA facilities for misconduct or security reasons. Removal does not relieve the Contractor of the responsibility to continue providing the services required under the contract. The Contracting Officer will provide the Contractor with a written explanation to support any request to remove an employee.

3.1 PROJECT MANAGER

3.1.1 The Contractor shall provide a Project Manager who shall be responsible for all Contractor work performed under this SOW. The Project Manager shall be a single point of contact for the Contracting Officer and the COR. The name of the Project Manager, and the name(s) of any alternate(s) who shall act for the Contractor in the absence of the Project Manager, shall be provided to the Government as part of the Contractor's proposal. The Project Manager is further designated as Key by the Government. During any absence of the Project Manager, only one alternate shall have full authority to act for the Contractor on all matters relating to work performed under this contract. The Project Manager and all designated alternates shall be able to read, write, speak and understand English. Additionally, the Contractor shall not replace the Project Manager without prior approval from the Contracting Officer.

3.1.2 The Project Manager shall be available to the COR via telephone between the hours of 08:00 AM and 5:00 PM EST, Monday through Friday, and shall respond to a request for discussion or resolution of technical problems within 24 hours of notification.

3.1.3 The Project Manager shall ensure all sites are cleaned up and debris is disposed of at the end of each work day, in accordance with all applicable Federal, State, and local laws and regulations for disposal.

4.0 APPLICABLE DOCUMENTS

A. Task One. Generator sound barrier wall repair.

1. Appendix A: site photos

2. NFPA 70E, Standard for Electrical Safety in the Workplace (National Fire Protection

Association 2021)

3. 29 CFR 1910, Occupational Safety and Health Standards (Occupational Safety and Health

Administration 1970)

4. SSPC (STANDARD by Society for Protective Coatings) PA Guide 10

5. 29 CFR 1910.1000

6. Appendix A, photos of existing conditions

B. Task Two. Window film installation.

1. Appendix B: photos of existing glass panels

2. 29 CFR 1910, Occupational Safety and Health Standards (Occupational Safety and Health

Administration 1970)

3. NFPA 241, Standard for Safeguarding Construction, Alteration, and Demolition Operations

(National Fire Protection Agency 2022) C. Task Three. Repaint existing interior painted walls and doors.

1. Appendix C: sketch and photos of existing conditions

2. 29 CFR 1910, Occupational Safety and Health Standards (Occupational Safety and Health

Administration 1970)

3. 29 CFR 1926, Occupational Safety and Health Standards (Occupational Safety and Health

Administration 1970)

1305M327Q0061 SOW Page 10 of 12

4. Safety Methods Used During Paint Application: Comply with the requirements of SSPC (STANDARD by Society for Protective Coatings) PA Guide 10

5. Drywall Finishing https://www.usg.com/content/dam/USG_Marketing_Communications/canada/product_prom otional_materials/finished_assets/cgc-construction-handbook-ch05-finishing-drywall-system s-can-en.pdf

6. Sherwin-Williams Paint Data Sheets:

https://www.sherwin-williams.com/home-builders/specifications/sustainability

7. 29 CFR 1910.1000

8. ACGHI-BKLT and ACGHI-DOC, threshold limit values

D. All Tasks.

a. Manufacturer’s instructions for proper application of each product.

5.0 SAFETY

A. Air Quality

1. The contractor shall use, on the job site, only chemicals and products which are effective to fulfill the requirements described herein, have the least adverse impact on the environment, do not exceed the volatile organic chemical (VOC) limitations rule(s) published by the U.S.

Environmental Protection Agency (EPA), and comply with all regulatory requirements.

B. Spill Contingency Plan

1. Neither domestic drains nor storm drains on the WFO PBZ grounds shall be used to dispose of paint, thinners, fluids, solvents, concentrated cleaning agents or other hazardous materials.

C. The Contractor shall protect any adjacent work areas, infrastructure and equipment affected by work within this SOW. The Contractor shall immediately clean primer and paint from all hardware and other surfaces or items not required to be painted from any paint drops or smears. The Contractor shall protect work from debris, paint droppings, and spattering by use of masking, drop cloths, removal of items or by other approved methods.

6.0 OTHER APPLICABLE CONDITIONS

The Contractor shall attend a Post Award Conference with the Contracting Officer and the COR no later than 10 business days after the date of award. The purpose of the Post Award Conference is to discuss technical and contracting objectives of this contract and review the Contractor's draft project plan. The Post Award Conference will be held either at the place of performance facility or via teleconference.

7.0 PERIOD OF PERFORMANCE

A. The period of performance for this contract is a total of one hundred and eighty (180) calendar days after notice to proceed (NTP) from the Contracting Officer.

B. The Contractor shall provide a draft Project Plan at the Post Award Conference for Government review and comment. The Contractor shall provide a final Project Plan to the TPOC and CO not later than 10 business days after the Post Award Conference.

8.0 PLACE OF PERFORMANCE AND HOURS OF OPERATION

A. The place of performance is:

1305M327Q0061 SOW Page 11 of 12 https://www.usg.com/content/dam/USG_Marketing_Communications/canada/product_promotional_materials/finished_assets/cgc-construction-handbook-ch05-finishing-drywall-systems-can-en.pdf https://www.usg.com/content/dam/USG_Marketing_Communications/canada/product_promotional_materials/finished_assets/cgc-construction-handbook-ch05-finishing-drywall-systems-can-en.pdf https://www.usg.com/content/dam/USG_Marketing_Communications/canada/product_promotional_materials/finished_assets/cgc-construction-handbook-ch05-finishing-drywall-systems-can-en.pdf https://www.sherwin-williams.com/home-builders/specifications/sustainability

National Weather Service Forecast Office 192 Shafer Road Moon Township, PA 15108

B. Contractor employees shall generally perform all work between the hours of 8:00 AM and 5:00 PM local time, Monday through Friday (except Federal holidays). However, there may be occasions when Contractor employees shall be required to work other than normal business hours, including weekends and holidays, to fulfill requirements under this SOW. Working outside of regular business hours must be approved in advance, in writing, to the TPOC and CO.

9.0 GOVERNMENT FURNISHED RESOURCES

A. The Government will not furnish any resources to the Contractor in support of this contract, other than access to the facilities. The Contractor shall furnish all materials, equipment, and services necessary to fulfill the requirements of this contract.

10.0 CONTRACTOR FURNISHED PROPERTY

A. The Contractor shall furnish all facilities, materials, equipment and services necessary to fulfill the requirements of this contract, except for the Government Furnished Resources specified in SOW 2.0 and SOW 6.0.

11.0 GOVERNMENT ACCEPTANCE PERIOD

A. The CO will review deliverables prior to acceptance and provide the Contractor with notification via electronic mail that provides documented reasons for non-acceptance.

B. The CO will have the right to reject or require correction of any deficiencies found in the deliverables that are contrary to the information contained in the Contractor’s accepted quote. In the event of a rejected deliverable, the Contractor will be notified in writing by the CO of the specific reasons for rejection.

C. The CO will review deliverables and make comments. The Contractor shall have seven (7) business days to make corrections and redeliver.

12.0 POINTS OF CONTACT

Technical Point of Contact (TPOC) Name: Jeremy Cordie Email: jeremy.cordie@noaa.gov Phone: 937-479-8753

Local Point of Contact (LPOC) Name: Tom Plecha Email: thomas.plecha@noaa.gov Phone: 412-262-1591

1305M327Q0061 SOW Page 12 of 12 mailto:jeremy.cordie@noaa.gov mailto:thomas.plecha@noaa.gov