This is a Questions and Answers document for NOAA's janitorial services solicitation 1305M327Q0049 in Rapid City, South Dakota. The document clarifies key contracting requirements and operational procedures for prospective quoters responding to this requirement for janitorial services on a base year plus four option years basis.

The Q&A addresses critical compliance and performance expectations, including confirmation that the previous contract award to Eco Friendly Cleaning Specialist, LLC totaled $74,051.87 for the base plus four option years. Regarding subcontracting, NOAA permits the use of subcontractors for routine daily and weekly cleaning tasks provided the prime contractor maintains full oversight, responsibility for all performance, management, and quality assurance, and that subcontractor experience may be credited toward the relevant experience evaluation factor. All required security investigations and background checks must be favorably completed prior to the contract start date of January 1, 2027; if not completed, contractors may be escorted around the facility during the adjudication period. Site visits are highly recommended and can be arranged individually with the designated points of contact; subcontractor representatives are permitted to attend on the prime contractor's behalf. Additional clarifications address the on-site supervisor's authority to act as the local representative with full firm oversight, and confirm that the independent Government estimate is not available to quoters. This is a template document providing guidance rather than specifying detailed service requirements or pricing terms.

View the file

Other files

File Type Posted
1305M327Q0049_Questions_and_Answers_0003.docx DOCX document
Sol_1305M327Q0049_Amd_0003.pdf PDF
Attachment_2_UNR_WFO_Floor_Plan_layout_0003.pdf PDF
Sol_1305M327Q0049_Amd_0002.pdf PDF
Sol_1305M327Q0049_Amd_0001.pdf PDF
Sol_1305M327Q0049.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1305M327Q0049 Questions and Answers

1. Previous award: The solicitation states the previous contract (1305M322PNWWR0102) was awarded to Eco Friendly Cleaning Specialist, LLC for a base year and four option years totaling $74,051.87. Could you confirm the previous award amount, the awardee, and the period of performance? I can confirm the previous award information listed is accurate, with the period of performance being a base year plus four option years. SAM.gov has all the information you're looking for on this previous contract as well.

2. Subcontracting — "meaningful portion": Section 6 states the quoter "must perform a meaningful portion of the primary and vital contract requirements and may not act merely as a pass-through." Could you clarify what portion or percentage of the work NOAA considers a meaningful portion? Specifically, may a subcontractor perform the routine daily and weekly cleaning tasks while the prime contractor provides management, supervision, quality control, and site oversight? See 3’s answer.

3. Subcontractor past performance: If a quoter relies on a proposed subcontractor's experience to meet the Experience evaluation factor, is that sufficient, or must the prime contractor itself demonstrate similar past work? 2 & 3 Subcontracting is permissible; however, the prime contractor remains responsible for all contract performance, management, and quality assurance. As long as your firm maintains full oversight, a subcontractor may perform the routine cleaning tasks and their experience may be considered toward the relevant experience evaluation factor.

4. Site visit: The solicitation states a site visit is highly recommended and names Mr. Hintz and Mr. Fox to schedule a visit. Is there a scheduled group site-visit date and time, or should each quoter arrange an individual visit? May a subcontractor representative attend the site visit on the prime contractor's behalf? Please reach out to the contacts listed in the solicitation directly to arrange an individual site visit. A representative from your subcontractor is welcome to attend on your behalf.

5. Background investigations: Must all personnel security investigations be favorably completed before the January 1, 2027 start date, or may work begin while a NACI adjudication is pending? All required security investigations must be favorably completed prior to the start of work. If this is not completed in time, the contractor may be escorted around the facility until the background checks are complete.

6. Estimated value: Is there an estimated value or independent Government estimate available for this requirement that you can share? The independent Government estimate is not public information and will not be shared.

7. Would it be okay for the cleaning company’s supervisor to also be my local representative and handle any issues that come up at the location? The supervisor on-site may act as your local representative, provided your firm maintains full oversight and responsibility for the performance and compliance of the contract.