This is a Statement of Work (SOW) for janitorial services at the National Weather Service Forecast Office in Negaunee, Michigan. The contractor must provide all personnel, supplies, equipment, and materials necessary to clean the 4,287 square foot facility, which operates 24/7 and houses 20 employees. The facility contains 50% uncarpeted flooring and 50% carpeted area, with 20 windows requiring cleaning.

The contractor must perform daily cleaning (Sunday, Monday, Thursday, Friday) including floor sweeping/vacuuming with HEPA filters, waste removal, restroom disinfection, and dusting. Weekly tasks include damp mopping, office surface cleaning, window washing, and microwave/sink cleaning. Monthly duties include buffing electronics shop floors, spot cleaning walls and doors, and Venetian blind cleaning. Quarterly work (January, April, July, October) encompasses clock washing, exterior window cleaning, air grill cleaning, light fixture maintenance, and specialized floor treatments—including resilient floor buffing and ceramic tile deep cleaning with specific prohibitions against wax, oil, or coatings on anti-static access floors. Semiannual carpet cleaning (April, October) must use low-moisture processes, explicitly prohibiting hot water extraction and spin-bonnet methods. Annual ceramic tile floor cleaning occurs in April. The contractor must provide quarterly on-site visits by authorized staff, designate a representative for government contact, bill monthly in arrears, and ensure uninterrupted service except on federal holidays. All employees must be fully vaccinated and sign security logs. The base year performance period runs January 1, 2027 through December 31, 2027, with four optional years extending through December 31, 2031. The Technical Point of Contact is Ryan Metzger at (906) 475-5782 x642.

View the file

Other files

File Type Posted
Sol_1305M327Q0040.pdf PDF
WD_2015-4871_Rev_34.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work National Weather Service

Janitorial Services for the Marquette Weather Forecast Office

Place of Performance:

National Weather Service Forecast Office 112 Air Park Drive South Negaunee, MI 49866 Marquette County

Scope of Work The contractor shall provide all personnel, supplies except those identified to be provided by the Government, tools, equipment, materials and supervision for the duties required to clean the Weather Forecast Office as described in this Statement of Work. This facility is in operation 24/7. The equipment, materials and supplies shall be appropriate for the work being performed, be of good commercial quality, and properly stored in the area designated by the Government Technical Point of Contact (TPOC).

Additional Information Cleanable Square Footage: 4,287 Uncarpeted Flooring: 50% Carpeted Area: 50% Number of Employees: 20 Number of Windows: 20

Description of Work The contractor shall:

1. Be responsible for satisfactorily managing and performing programs for cleaning as specified,

2. Provide an individual, other than the person performing the regular cleaning service, to perform quarterly spot checks of work performed (unless owned and operated by one individual), and

3. Be responsible for furnishing all supplies (for example, liquid soap, urinal deodorizer blocks, cleaning solutions, paper hand towels, toilet paper, and trash bags.

SCHEDULE OF WORK

A. DAILY: (Sunday/Monday/Thursday/Friday)

1. Sweep or dust mop all uncarpeted floors including hallways and foyers using chemically treated absorbent tools. All sweeping of floors shall be done by the dustless method using either the laundered or the disposable types of treated cloths, as appropriate.

2. Vacuum all carpeted floors with a commercial grade vacuum that has a High Efficiency Particulate Air (HEPA) filter.

3. Vacuum or clean indoor and outdoor entrance mats.

4. Empty all waste receptacles and recycle containers. Remove all refuse to proper outside containers. Replace plastic liners when soiled or torn. In case of leakage, damp wipe receptacle to remove all residue.

5. Wet mop restroom floors with disinfectant solution. Clean and disinfect counter tops, sinks, mirrors, fixtures, toilets, and urinals. Spot clean toilet enclosures, baseboards, pipes, sills, and walls. Provide and replace, as necessary, deodorant devices for the men’s restroom urinal. Fill restroom soap, towel, and toilet tissue dispensers. A sufficient quantity of paper towels and toilet paper shall be readily available in each restroom.

6. Wet mop break room floors with disinfectant solution. Clean and disinfect counter tops, sink, and table. Spot clean walls above counter tops and behind waste receptacles as needed. Fill break room soap and towel dispensers.

7. Clean and disinfect the drinking fountain.

8. Dust all horizontal surfaces that are readily accessible and visibly require dusting. All dusting shall be done by the damp or treated cloth method.

B. WEEKLY:

1. Damp mop all uncarpeted floors using a detergent solution. Remove all oil, tar, and stubborn dirt using an all-purpose spray cleaner.

2. Vacuum, dust, or damp wipe, as appropriate, all office desktops, chairs, phones, file cabinets, fabric partitions, window sills, and ledges. Method and material used must not leave a film, streaks, or stains. Care should be taken around computer equipment and accessories.

3. Wash glass entrance doors and windows and all interior glass. Method and material used must not leave a film, streaks, or stains.

4. Clean and scour the break room sink, interior and exterior of the microwave, and the counter top under the microwave.

5. Clean and scour store room sink and counter top.

C. MONTHLY:

1. Buff and spot polish traffic areas in the electronics shop to prevent finish from wearing through to the tile surface.

2. Spot clean doors, walls, painted surfaces, and ledges to remove fingerprints, marks, and smudges utilizing an all-purpose spray cleaner.

3. Remove spots and stains from carpeted areas using a good general purpose carpet spot remover.

4. Thoroughly clean and dust all Venetian blinds.

D. QUARTERLY: (January, April, July, and October)

1. Wash off all clocks.

2. Wash all exterior windows. Methods and materials used must not leave streaks or stains.

3. Clean the return air grills in the Operations Area and Equipment Room.

4. Remove all bugs and/or debris from ceiling light fixtures.

5. Resilient Floor (Electronics Shop): After damp mopping or light scrubbing, a dilute floor polish

(7% to 8% solids) or spray-buffing compound shall be sprayed on the floor. Before the liquid can dry, it shall be buffed with a floor machine of 170 to 1,100 rpm equipped with a buffing pad or brush. A thin, protective, glossy film remains after buffing the liquid dry. This procedure allows the base coat of polish to be protected, reducing the need for stripping. Severe traffic areas may require extra coats of polish.

6. Access Floor (Equipment and Operations Area): Damp mop complete floor. Mop should be damp but not wet to ensure that no water seeps down through floor seams. To remove marks or stains, use an all-purpose spray cleaner. Under no circumstances will wax, oil, or other coatings be applied to this floor as the anti-static properties of this floor will be lost.

7. Ceramic Tile Floors: Remove spots and stains from ceramic tile floor located in the entrance ways, bathrooms, and break room using an all-purpose spray cleaner.

E. SEMIANNUAL: (April and October)

1. Vacuum/clean chairs.

2. Vacuum all accessible carpeted walls.

3. Clean interior walls in the breakroom.

4. All carpeted areas shall be cleaned using a low moisture cleaning process. Vacuum thoroughly before doing the cleaning process.

● DO NOT use hot water extraction or so-called “Steam Cleaning”.

● DO NOT use the Spin-Bonnet method.

F. ANNUAL: (April)

1. All ceramic tile floors shall be cleaned using the following procedure:

• Sweep or vacuum as required removing loose dust and dirt.

• Remove foot marks and small spills with damp mop or sponge.

• A cleaning solution shall be mixed according to the manufacturer’s directions. Use a double bucket or two standard buckets; one containing fresh cleaning solution, the other to receive dirty cleaning solution removed from the floor.

• Apply cleaning solution to the floor and agitate with either floor machine or scrubbing brush attachment, or long handled scrubbing brush. Be especially careful to loosen all dirt in grout joints. Work small areas at a time to keep dirty cleaning solution from drying on the floor.

• Remove all dirty cleaning solutions from the floor with a wet mop or auto scrubber.

• Let the floor dry before allowing traffic.

• Note: No sealers or waxes shall be used on this floor.

G. ADDITIONAL WORK OUTSIDE THE STATEMENT OF WORK

Additional work not covered in the Statement of Work (SOW) may be requested on an as needed basis with a modification to the purchase order. The contractor shall be compensated for the additional work at an hourly rate plus materials if applicable, to be included in the purchase order.

Materials shall be itemized on the invoice and not exceed published price listings.

TERMS OF STATEMENT OF WORK

A. The contractor shall bill on a monthly basis in arrears for the service provided.

B. The contractor shall designate a representative, and provide contact numbers, for the TPOC to communicate with about the quality of work, progress, and technical details of the project.

Neither the local representative nor the TPOC has the authority to modify the contract in any manner which might affect the cost. Only the Contracting Officer has the authority to modify the contract in any way.

C. Quarterly on site visits are required by a staff member of the prime contract who has the authority to address contractual and performance issues. These site visits shall be scheduled in advance and be on a date and time agreeable to both parties.

D. The contractor shall be responsible for the scheduling and coordination of work on the site.

Services performed under this contract shall be performed during hours approved by the MIC.

E. Services shall be performed in accordance with the Statement of Work without interruption even if the regularly scheduled employee fails to show due to illness, injury, vacation, no show, etc.

F. If any of the services do not conform to the contract requirements, the Government may require the contractor to perform the services again in conformity with the contract requirements, at no increase in contract amount. If the defects in services are not corrected by performance, the government may (1) require the contractor to take necessary action to ensure that future performance conforms to contract requirements, and (2) reduce the contract price to reflect the reduced value of the services performed.

G. If the contractor fails to expeditiously take the necessary action to ensure that performance is in conformity with contract requirements, the Government may take corrective action.

H. All work shall be done as required above except on Federal holidays, of which work shall be accomplished the following day or as agreed upon by the contractor and MIC. A list of Federal holidays may be found at www.opm.gov.

I. Any cleaning missed due to severe weather operations shall be made up the following day.

J. The Government reserves the right to inspect for quality control.

K. The contractor and/or employee shall sign in and out on the security log sheet located in the janitor’s closet whenever entering or exiting the property.

L. Contractors and/or employees must be fully vaccinated.

SAFETY AND ENVIRONMENTAL REQUIREMENTS

1. The Contractor and Sub-Contractors shall comply with all applicable Federal, State, and Local law and regulations pertaining to safety and environmental requirements.

2. The Contractor shall provide and maintain work environments and procedures which will safeguard the public and Government personnel, property, materials, supplies and equipment exposed to Contractor operations and activities.

Observance of Legal Holidays and Site Closure Information The Contractor shall observe the following Federal holidays, and any other day off work designated by Federal Statute, by Executive Order, or by Presidential proclamation:

New Year’s Day Labor Day

Martin Luther King Jr.’s Birthday Columbus Day

President’s Day Veteran’s Day

Memorial Day Thanksgiving Day

Independence Day Christmas Day

Juneteenth Day

When any holiday falls on a Saturday, the preceding Friday is observed. When any holiday falls on a Sunday, the following Monday is observed. All personnel assigned to this contract shall limit their observation of holidays to those set forth above.

In each instance, the Contractor agrees to continue to provide sufficient personnel to perform requirements of any critical tasks already in operation or scheduled, and shall be guided by the instructions issued by the Contracting Officer or the TPOC. In the event of a site dismissal or closure due to weather, emergency or other circumstances, the contractor is instructed to contact the TPOC or alternate for guidance.

Period of Performance Base Year: 01/01/2027 - 12/31/2027 Option Year 1: 01/01/2028 - 12/31/2028 Option Year 2: 01/01/2029 - 12/31/2029 Option Year 3: 01/01/2030 - 12/31/2030 Option Year 4: 01/01/2031 - 12/31/2031

GOVERNMENT POINT OF CONTACTS:

Site Visit Point of Contact: Jerry Hill, (906) 475-5782 x221, jerry.hill@noaa.gov Technical Point of Contact: Ryan Metzger, (906) 475-5782 x642, ryan.metzger@noaa.gov Invoice Approver in IPP: Ryan Metzger, (906) 475-5782 x642, ryan.metzger@noaa.gov