1305M323RNRMJ0021 Solicitation Questions.pdf

PDF 101 KB Posted

Attached to
Construct Tower Foundation and Tower Installation Project Mauna Loa Observatory Federal contract opportunity
Solicitation number
1305M323RNRMJ0021
Issued by
Department of Commerce National Oceanic and Atmospheric Administration

About this file

This document contains questions and answers regarding solicitation number 1305M323RNRMJ0021 from the Department of Commerce National Oceanic and Atmospheric Administration to construct a tower foundation and install a tower at the Mauna Loa Observatory. The questions seek additional drawings of the replacement tower to allow for coordination and foundation design based on tower loads and site soil conditions. Responses indicate additional drawings will be provided in a solicitation amendment.

View the file

Other files for this federal contract opportunity

Other files attached to Construct Tower Foundation and Tower Installation Project Mauna Loa Observatory, newest first.
File Type Posted
SF30 1305M323RNRMJ00210003.pdf PDF
SF30 1305M323RNRMJ00210002.pdf PDF
ATTACHMENT 8 Tower Shop Drawings.pdf PDF
ATTACHMENT 6 Geotech Repot MLO Army Monopole.pdf PDF
SF30 1305M323RNRMJ00210001.pdf PDF
ATTACHMENT 5 Erection Drawings Combined.pdf PDF
ATTACHMENT 7 MLO GEOTechnical Engineering Report Dec1994.pdf PDF
ATTACHMENT 4 CONSTRUCTION WAGE RATE REQUIREMENTS HI20230001.pdf PDF
ATTACHMENT 2 DRAWINGS.pdf PDF
1305M323RNRMJ0021 SF1442.pdf PDF
ATTACHMENT 3 BANNED CONSTRUCTION MATERIALS LIST.pdf PDF
ATTACHMENT 1 STATEMENT OF WORK.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Item No. Question Government Response

Please the replacement tower shop drawings for coordination purposes.

See solicitation amendment for additional drawings.

Attachment 01 SOW, Page 2, CLIN No.1, Number 1:

Furnish stamped and sealed (Professional Engineer

Certified) tower foundation design requirements to allow the furnished tower to be installed on site.

The tower and foundations installer will be responsible for engineering the new foundations plan based on the tower manufacturers engineered shop drawings and the soils condition found in these reports. They shall take no other liberties with these reports aka recommendations made within these reports. They shall run their own calculations when designing the foundations plan based on the loads found in the manufacturers engineering shop drawings. See solicitation amendment for additional drawings.

Attachment 02 Drawings: In order to properly propose this effort we will need a complete set of drawings that show the Tower Assembly. There doesn't appear to be a copy of the Tower Drawings within the

SAM.Gov Posting.

See solicitation amednment for additional drawings.

In the SOW on page 2, contract line item 1, c. “New tower design has a footprint of 8’ per side ( see attached tower drawings)”. There were no tower drawings included in the solicitation just some drawing for something called “The Tower Building”.

Could you please send the mentioned tower drawings?

See solicitation amednment for additional drawings.

1305M323RNRMJ0021 Construct Tower Foundation and Tower Installation Project at the Mauna Loa