J. 1 NOAA SHIP THOMAS JEFFERSON DRYDOCKING AND REPAIRS_REV-2
View the file
Other files
| File | Type | Posted |
|---|---|---|
| MOA2-04(18)_TJFY19DD_Rev3_2018-11-28.pdf | ||
| Amendment_0004.pdf | ||
| Amendment_0003.pdf | ||
| RFP_1305M218RNMAN0027_REV_3.pdf | ||
| TJ-184-002B_VSAT_Radome_Installation.pdf | ||
| References.zip | ZIP file | |
| RFP_1305M218RNMAN0027_REV_2.pdf | ||
| Amendment_0002.pdf | ||
| RFP_1305M218RNMAN0027_REV_1.pdf | ||
| Amendment_0001.pdf | ||
| J._1_NOAA_SHIP_THOMAS_JEFFERSON_DRYDOCKING_AND_REPAIRS_REV-1.pdf | ||
| Thomas_Jefferson_-_HVAC_System_Design_-_9.1.2015.pdf | ||
| Miscellaneous_supporting_information.zip | ZIP file | |
| Manuals.zip | ZIP file | |
| RFP_Package.zip | ZIP file | |
| Drawings.zip | ZIP file | |
| STANDARD_SPECS.zip | ZIP file |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NOAA Ship Thomas Jefferson
Dry Docking and Repairs_REV 2
MOA2-04(18)
DATE: September 25, 2018
Revised: October 30, 2018
Written by:
Reviewed by:
Marine Engineering Branch - MOA2 Marine Operation Center, Atlantic
439 West York Street Norfolk, VA 23510
Record of Changes
Change Date: October 10, 2018 (Changes are highlighted with a single vertical line in the right margin.)
• All – Changed the word “provided” to “provides” within the Abstract of all Work Items.
(This change is not marked.)
• Item 302 – added paragraph 3.2.7 b. to provide information on the existing coating system for the transducer faces.
• Item 309 – Revised paragraph 3.9.4 a. 2. to insert text “Reference (aj) was developed in Diamond System Builder which is a proprietary program of Mitsubishi.” Access to the program is through the OEM authorized representative required in paragraph 3.9.4 a. 8.
• Item 309 – Revised paragraph 3.9.4 i. 2. to replace the word “Design” to read “Diamond.”
• Item 313 – added new paragraph 3.13.7 a. to provide information on the existing coating system for the underwater hull.
• Item 318 – Modified requirements for the written test procedure.
• Item 319 – Modified requirements for the written test procedure.
• Item 507 – Changed paragraph 5.7.7 c. 3. to reflect correct information on the anti-fouling coating for the underwater hull.
Change Date: October 30, 2018 (Changes are highlighted with a double vertical line in the right margin.)
• Item 400 – Revised paragraph to remove estimated hours and material costed which are identified in Schedule B.
• Item 508 – Revised paragraph 5.8.4 b. 2. to allow the contractor to choose which bulkhead to make watertight.
MOA2-04(18)
October 30, 2018 i
Table of Contents
1. SCOPE
2. GENERAL
3. BASIC ITEMS
3.1 ITEM NO. 301: Temporary Services
3.2 ITEM NO. 302: Dry Docking and Routine Dry Dock Work
3.3 ITEM NO. 303: Unshipping and Shipping Rudder
3.4 ITEM NO. 304: Propeller Shaft Inspection and Repairs
3.5 ITEM NO. 305: Propeller Inspections and Repairs
3.6 ITEM NO. 306: ABS Ballast Tank Inspections
3.7 ITEM NO. 307: Ballast Tank Preservation
3.8 ITEM NO. 308: Sea Valve Overhauls
3.9 ITEM NO. 309: HVAC System Upgrades
3.10 ITEM NO. 310: Cathodic Protection: Inspect & Repair
3.11 ITEM NO. 311: Cathodic Protection: Anode Shield Replacement .. 55
3.12 ITEM NO. 312: Elinca System: Inspect & Repair
3.13 ITEM NO. 313: Underwater Body Coating - Maintenance
3.14 ITEM NO. 314: Clean/Degrease Engine Room Bilge
3.15 ITEM NO. 315: Structural Replacements/Repairs
3.16 ITEM NO. 316: Reduction Gear and Clutch Servicing
3.17 ITEM NO. 317: Piping Repairs
3.18 ITEM NO. 318: Dock Trials
3.19 ITEM NO. 319: Sea Trials
4. OPTIONAL ITEM 400: ADDITIONAL ITEM REQUESTS
5. OPTIONAL ITEMS
5.1 ITEM NO. 501: ADCP Transducer Installation
5.2 ITEM NO. 502: Potable Water System Renewals
5.3 ITEM NO. 503: Grey and Black Water Piping Replacement
5.4 ITEM NO. 504: Stateroom Upgrades
5.5 ITEM NO. 505: Plot Room Upgrade
5.6 ITEM NO. 506: Bridge Deck & Pilothouse Top Deck Preservation . 97
5.7 ITEM NO. 507: Bow Sonar Dome Removal
5.8 ITEM NO. 508: Permanent Ballast Installation
5.9 ITEM NO. 509: Fog Bell Installation
ii
5.10 ITEM NO. 510: Clean/Degrease Steering Gear Room Bilge
5.11 ITEM NO. 511: SSDG Generator and Breaker OHs
REFERENCES
LIST OF ATTACHMENTS
1 | P a g e
1. SCOPE
1.1 These Detail Specifications contain the requirements for
intermediate dry-docking, HVAC upgrade and general repairs to the NOAA Ship Thomas Jefferson (formerly USNS Littlehales T-AGS 52).
2. GENERAL
2.1 References
2.1.1 NOAA Standard Specification 000-1H, “General
Requirements for Ship Repair Contract Work on NOAA Ships”
2.1.2 NOAA Standard Specification AMC-631-2D, “Coating
Systems for Steel Surfaces”
2.1.3 NAVSEA Standard Item 009-32, “Cleaning and Painting
Requirements: Accomplish”
2.1.4 NOAA Ship Thomas Jefferson drawing TJ-085-002F, “Booklet of General Plans”
2.1.5 ABS Steel Vessels Under 90 Meters (295 Feet) in Length
2.2 Requirements
2.2.1 Reference 2.1.1 form a part of these Detail
Specifications. All provisions and requirements contained therein are applicable to all work items, including all additional work items which are authorized by the Contracting Officer.
a. Provide an electronic copy, in Adobe Portable Document Format (PDF), and two hard copies of all Condition Reports.
b. Include in the Safety Plan detailed procedures for the following:
1. Confined and Enclosed Spaces and Other Dangerous Atmospheres – All confined spaces must be considered to have a hazardous atmosphere until demonstrated to be safe via testing by the Competent Person. Confined spaces may contain high concentrations of harmful gases and other environmental conditions that can cause injury, illness, or death. Include in this section the procedures for personnel to enter and work within confined spaces.
2 | P a g e
2. Control of hazardous energy (lockout/tagout (tags-plus)) – All machines, equipment, and pressurized systems are to be isolated from their energy source and at a minimum tagged out in addition to locking out (if the equipment can be fitted with a locking device) before any servicing or repair work is performed where the unexpected start up or release of energy could cause injury or death. In addition, lockout/tagout shall be used whenever personnel are required to remove a guard or other safety device or required to place any part of personnel’s body in a danger zone of any machine, equipment, or system. Include in this section the procedures for lockout/tagout for servicing of machinery, equipment, and systems when the energization or startup of machinery, equipment, or systems, or the release of hazardous energy, could endanger personnel.
3. Hotwork Operations – Include in this section the procedures used for preparing for hotwork including Marine Chemists and Competent Persons requirements, notifications of hotwork operations, fire prevention during hotwork operations and fire prevention after completion of hotwork operations.
4. Fall Protection – The ship is equip with systems to protect personnel from falls during normal operations.
Include in this section temporary safe guards, systems, equipment, restraints and/or procedures used to protect personnel from falls during accomplishment of work required by these Detail Specifications.
c. Definition of terms as related to drawings:
1. As-built drawing – A drawing that reflects the as-constructed conditions of the system. As-built drawings include current and previous undocumented changes to the system.
2. Develop ACAD “As-Built” drawing – Covert the drawing from the provided format and create in an ACAD format.
2.2.2 Maintain a Quality Assurance (QA) Test and Inspection
Plan applicable to all work items, including all additional work items which are authorized by the Contracting Officer. The form shall include the following minimum information for each work item and additional work item:
a. Specification item and paragraph number
b. Component/Equipment name
c. Test or Inspection description
3 | P a g e
d. Acceptance Criteria
e. QA Inspection Report
2.2.3 Maintain a separate Test Schedule.
2.2.4 Develop, in consultation with the local attending ABS
Surveyor, a written survey schedule that lists the items to be inspected and the scheduled dates and times of the inspections.
2.2.5 Unless otherwise stated in these work items, prepare
and coat all new steel, disturbed, or otherwise required painted surfaces in accordance with reference 2.1.2. If no paint system is identified in the item, apply the appropriate coating system to the area being coated as identified by paragraph 5.2 of this reference except that the topcoat color shall match the surrounding area. Reference 2.1.2 may be amended with reference
2.1.3 when approved by the COR.
a. All Coating contractors to have current and active QP1 certification.
b. Maintain environmental records for days when coating systems are applied. Obtain environmental readings prior to application of any coating and at maximum of 1 hour intervals during application of the coating.
2.2.6 Weight Report: Weigh all materials and items removed, installed, or relocated on the ship. Provide a summary report to the COR indicating the total weight in pounds of the item and a breakdown of their locations by space, deck, frame, distance from centerline, and height off of the deck. A sample form is attached to these specifications.
2.2.7 The Contractor may reduce the ship's draft by
offloading liquid loads and/or ballasting in order to provide the required clearances under the keel during transit to and from the contractor's facility. Oil Tanks shall not be ballasted. After all other work has been completed, reload and trim the ship to the as-found conditions. In the event fuel is offloaded, the fuel shall be metered off and on the ship through a filter de-watering system. Store removed fuel in clean storage facilities. The minimum draft for transit which will be permitted is 12 feet - 6 inches.
2.2.8 The cleanliness of the ship at the time of redelivery
to NOAA shall be equal to or better than the cleanliness of the ship at the time of delivery to the contractor.
4 | P a g e
2.2.9 NOAA Ship Thomas Jefferson is ABS Classed. All
fabrication and materials are to be in accordance with reference
2.1.5. so as to retain her ABS Class.
2.3 Deliverables
2.3.1 General - Condition Reports (see requirement in
reference 2.1.1)
2.3.2 General - Progress Reports (see requirement in
reference 2.1.1)
2.3.3 General - List of Contractor’s Supervisors (see
requirement in reference 2.1.1)
2.3.4 General - Safety Plan (see requirement in reference
2.1.1)
2.3.5 General - Gas Free Certifications (see requirement in
reference 2.1.1)
2.3.6 General - Hot Work Notices (see requirement in
reference 2.1.1)
2.3.7 General - Hazardous Material List and MSDS (see
requirement in reference 2.1.1)
2.3.8 General - Quality Assurance (QA) Test and Inspection
Plan
2.3.9 General - Test Schedule
2.3.10 General - ABS Approved Welding Procedure and Welder
Certification – Provide a copy of ABS approved welding procedures and welder certificates prior to starting any work.
Maintain a list of currently qualified welders throughout the contract performance period.
2.3.11 General - ABS Survey Schedule - Submit the ABS survey
schedule to the COR within 48 hours after the start of the contract performance period. The ABS survey schedule shall list all initial inspections required by the ABS Surveyor.
2.3.12 General - QP1 certification(s)
2.3.13 General - Coating Environmental Reports
2.3.14 General - Weight Report
5 | P a g e
2.4 Notes
2.4.1 Hazardous Materials:
a. NOAA Ship Thomas Jefferson was constructed between 1988 and 1991. There was no asbestos used during the construction and any asbestos requirements contained in the referenced Standard Specifications do not apply.
b. Several items in this specification require gas freeing of tanks, in order to accomplish the required work.
Prospective bidders should be careful not to duplicate the costs of gas freeing where tank(s) are required to be gas freed to perform work in more than one item.
c. The contractor is responsible for the control, handling, and disposal of any hazardous materials generated during accomplishment of this contract.
2.4.2 Reference 2.1.4 was used in the identification, location, and naming of spaces within these Detail Specifications. Even though reference 2.1.4 has been modified since construction, differences still exist.
2.4.3 Ship’s force may schedule work items to be
accomplished by ship’s force concurrent with these Detail Specifications. Ship’s force work items will be scheduled and coordinated with the contractor to not interfere with the work required in these Detail Specifications.
2.4.4 Ship Safety Procedures. NOAA Ship Thomas Jefferson has
her own safety procedures to include Confined Space Entry Program, Lockout/Tagout, Hotwork Operations, and Marine Operations Fall Protection Program. Ship’s force will continue to use the ship’s safety procedures during accomplishment of ship’s force work items.
2.4.5 The following general characteristics of the ship are
provided for information:
ABS Class Number...9105067 Delivery Date..01 Dec 1991 Length Overall.........208 feet Beam (Molded)...........45 feet Propulsion.............Diesel, single screw Cruising Speed..........12 knots Electric Service.......345 KW, 225/450 volts AC Officer size Crew size
6 | P a g e
E ABS Class Notations....✠A1, , ✠AMS, ✠ACCU
2.4.6 Except as otherwise stated in this specification, NOAA
plans to deliver the ship to the contractor's facility with the following maximum drafts and displacement (approximately 62% liquid loading):
Forward Draft............14 feet - 0 inches Aft Draft................14 feet - 6 inches Displacement..........≈2200 long tons
End of Section
7 | P a g e
3. BASIC ITEMS
3.1 ITEM NO. 301: Temporary Services
3.1.1 Abstract – This item covers the requirements for
providing temporary service during repair of the ship’s tunnel thruster (bow thruster).
3.1.2 References
(a) NOAA Standard Specification 000-2D, “Temporary Services at Contractor Facilities”
3.1.3 Government-Furnished Material
a. None
3.1.4 Requirements
a. Provide all temporary services required in accordance with reference (a) for the entire performance period.
b. The following additional information and requirements apply:
1. Electric: Provide and maintain 400 amps, 60 hz, 460 volts ac, 3 phase electrical shore power services. Estimated demand load is 250 amps average when the ship is habitable. The ship’s two receptacles are for NATO (Joy type) plugs rated at 400 amps each. Ship’s force will identify which of the ship’s receptacles to connect to for this availability at the time of hookup.
2. Telephone Service: Provide five phone lines and three phones; one each to the three dockside offices and two phone lines to the ship’s phone system.
3. Steam: Not required.
4. Toilet Facilities: Required during uninhabitable period.
5. Parking Spaces: Provide parking spaces for eight vehicles. Provide the follow labels for the parking spaces:
a) One each: “NOAA - COR”
b) One each: “NOAA - CO”
8 | P a g e
c) One each: “NOAA - CME”
d) Five each: “NOAA”
6. Dockside Office Space: Three office spaces plus a common space for the crew. The common space to include a full size refrigerator, tables with chairs, and power receptacles for a microwave and coffee pots.
7. Security Services: Required.
8. Air: Provide 32 CFM (minimum), 125 psi dry, filtered compressed air connected to the ship's service airline on the Main Deck.
9. Internet Service: Required. Provide the proper number of connections necessary to satisfy the ship's wet berth and dry dock locations, as well as the ship’s and COR's dockside office spaces. All necessary cabling, DSL or cable modem(s), or fiber translators shall be provided for an RJ-45 network connection to the ship and the dockside office(s) routers.
Provide a minimum of one Internet Protocol (IP) address with Directory Name Server (DNS) service for each ship and dockside office(s) locations. The ship will provide the necessary routers and switches.
10. ABS Surveyor: Schedule the services of an ABS Surveyor as required by ABS for performing inspections of all new installations, modifications, and tank inspections. NOAA will pay for all normal ABS surveys and surveys associated with the work required by these specifications. The contractor shall provide a credit for any additional ABS charges associated with rescheduling of surveys and rework surveys which are directly under the control of the contractor.
11. Additional Crane Services: Provide 30 hours of crane service for loading /offloading ship’s supplies and equipment.
12. 48 hours prior to completion of the contract repair period, remove temporary deck covering.
a) Wash all none carpeted decks that were covered with temporary deck covering including each decks’ passageway and the Ship's Mess.
b) Steam clean all carpets that were covered with temporary deck covering.
9 | P a g e
3.1.5 Quality Assurance
a. No additional requirements
3.1.6 Deliverables
a. Safe Drinking Water Report (see requirements of reference (a))
3.1.7 Notes
a. None
End of Item
10 | P a g e
3.2 ITEM NO. 302: Dry Docking and Routine Dry Dock Work
3.2.1 Abstract - This item provides the ship specific
requirements for routine work to be accomplished while the ship is hauled.
3.2.2 References
(a) NOAA Standard Specification 997-1B, “Drydocking & Routine Drydock Work”
(b) NOAA Ship Thomas Jefferson drawing 161-6634743, “Shaft Strut”
(c) NOAA Ship Thomas Jefferson drawing 562-6634741, “Rudder Arrangement and Details”
(d) NOAA Ship Thomas Jefferson drawing 243-6634740, “Propeller Shafting, Arrangement and Details”
(e) NOAA Ship Thomas Jefferson drawing 801-6634640, “Hull Lines”
(f) NOAA Ship Thomas Jefferson drawing 801-6634641, “Table of Offsets”
(g) NOAA Ship Thomas Jefferson drawing TJ-568-004D, “NOAA Ship Thomas Jefferson Bow Thruster Installation”
(h) NOAA Ship Thomas Jefferson drawing 245-6634744, “Propeller Diagram”
(i) NOAA Ship Thomas Jefferson drawing TJ-079-03, Revision C Trim & Stability Booklet
3.2.3 Government Furnished Material
a. One box: HSS-GF0-HPMP-1 High Performance Marine packing (Estimated value $1,500)
3.2.4 Requirements
a. Provide dry-docking and routine dry-dock work in accordance with GENERAL Section reference 2.1.4 and reference (a).
11 | P a g e
b. The following additional requirements apply:
1. The ship shall be hauled within 72 hours of arrival at the contractor facility.
2. The minimum acceptable forward and after drafts and corresponding displacement tons permitted to dry-dock the ship consistent with safe stability and structural integrity are as follows:
a) Fwd = 10 feet - 3 inches
b) Aft = 10 feet - 9 inches
c) Displacement ≈ 1440 LT
3. Haul the ship in position 3 at a minimum keel block height of 5 feet.
4. After positioning and before hauling the ship, conduct a diver’s inspection of the underwater keel blocks positions relative to the dome to verify that the keel blocks will not come in contact with the centerline multi-beam dome.
5. Record inspection results on the attached NOAA DOCKING REPORT S0700/SWB997 in lieu of Docking Report form 2410.
6. Additional requirements for the propeller:
a) CLEANING AND POLISHING: Clean and polish forward and after surface of the propeller blade tips between 0.7 and 1.0 radius lines and the leading edges of the propeller blades over 0.2 of the blade width to a finish equal to the “B” specimen of the Rubert Comparator having a roughness average (RA) of 76.8 micro-inch. The remainder of the propeller blades shall be polished to a finish equal to the “C” specimen of the Rupert Comparator having an RA of 188.0 micro-inch.
b) Take the following data on the propeller:
1) Pitch of each blade at 0.7 radius, and
0.9 radius.
2) Stamping on hub for propeller diameter.
12 | P a g e
3) Stamping on hub for manufacturer and propeller number.
4) Stamping on hub for ABS number.
5) Stamping on hub for weight.
7. Additional requirements for the bow thruster propeller:
a) CLEANING AND POLISHING: Clean and polish to a finish equal to the “C” specimen of the Rupert Comparator having an RA of 188.0 micro-inch.
8. Install GFM packing for the tailshaft and rudder post instead of "TFE-impregnated square flax packing", as required in reference (a), para 3.8.
3.2.5 Quality Assurance
a. No additional requirements.
3.2.6 Deliverables
a. Docking Report S0700/SWB997
b. Propeller Inspection Data
3.2.7 Notes
a. References (b) through (i) are listed as sources for obtaining information.
b. Intersleek 1100SR with a final coat FXA992-Blue is an approved coating system for the transducer faces.
13 | P a g e
3.3 ITEM NO. 303: Unshipping and Shipping Rudder
3.3.1 Abstract - This item provides the requirements for
unshipping the rudder, inspecting the bearing surfaces and shipping the rudder on the ship.
3.3.2 References
(a) NOAA Ship Thomas Jefferson drawing TJ-562-001A, “Rudder Arrangement and Details”
3.3.3 Government-Furnished Material
a. None
3.3.4 Requirements
a. Remove the rudder nut keeper and remove the rudder nut from stock flange.
b. Unship the rudder and rudder stock to the shop.
c. Perform the following additional work on the rudder and rudder stock.
1. Prepare and preserve the rudder in accordance with Basic Item “Underwater Body Coating.”
2. Clean the rudder stock and perform a complete dimensional inspection of the bearing surfaces.
d. Replace the rudder’s four Aluminum 15 pound anodes.
New anodes to have a faired or tapered shape to minimize turbulence.
e. Install the rudder in its original location after completion of all work requiring the rudder removal using a new rudder nut keeper.
3.3.5 Quality Assurance
a. Perform an operational test of the rudder prior to hauling and after floating the ship.
b. Take and record rudder trunk bearing clearances prior to unshipping the rudder.
c. Take and record the rudder stock bearing surfaces after unshipping the rudder.
14 | P a g e
d. Take and record rudder bearing ID after unshipping the rudder.
3.3.6 Deliverables
a. Rudder - Operational test prior to hauling
b. Rudder - trunk bearing clearances
c. Rudder - stock bearing surface readings
d. Rudder - bearing ID measurements
e. Rudder - Operational test after floating
3.3.7 Notes
a. The rudder is a one piece ship welded straight blade type rudder. A ten foot access below the rudder is required for removal of the rudder or the rudder must be cut in half, removed and rewelded to the satisfaction of the attending ABS surveyor.
15 | P a g e
3.4 ITEM NO. 304: Propeller Shaft Inspection and Repairs
3.4.1 Abstract - This item provides the requirements for
pulling, servicing and installing the ship’s propeller shaft.
3.4.2 References
(a) NOAA Standard Specification AMC-240-1, "Propulsion Shafts and Propellers"
(b) NOAA Ship Thomas Jefferson drawing 243-6634740, “Propeller Shafting, Arrangement and Details”
(c) NOAA Ship Thomas Jefferson drawing 161-6634743, “Shaft Strut”
(d) NOAA Ship Thomas Jefferson drawing 243-6634745, “Shaft Brake Arrangement & Details”
(e) NOAA Ship Thomas Jefferson drawing 245-6634744, “Propeller Diagram”
(f) NOAA Standard Specification MOC-631-3B, “Underwater Body Ablative Coating System”
3.4.3 Government-Furnished Material
a. None
3.4.4 Requirements
a. General:
1. Touch up damaged areas of the underwater body preservation system in accordance with reference (f).
b. Perform the following work on the propeller shaft in accordance with reference (a):
1. Remove from the ship to an inside shop facility.
2. Perform the “In-shop Inspection of Propulsion Shaft” outlined in reference (a).
3. Using a micrometer, measure the shaft bearing area diameters at four locations along the length of bearing area. Compare the shaft bearing area dimensions to those of the respective bearings.
16 | P a g e
4. Clad weld repair and machine the shaft in way of the ground strap.
5. Machine, clad weld repair, and machine the stainless steel journal in way of the stern tube and strut bearings.
a) Machining shall not reduce the shaft diameter below 9.176 inches.
b) Use stainless steel 309L for the first pass if the machining approaches the 9.176 inch minimum diameter.
c) Use stainless steel 308L for each successive pass.
c. Replace the shaft covering with a 100% solids, two component, liquid polymer that cures to a hard ceramic-like material.
d. While the propeller shaft is drawn from the ship perform the following:
1. Measure the inside diameters of each strut and stern tube bearing. Use a micrometer and measure at four locations throughout the bearing lengths. Compare these inside diameter measurements with the diameter measurements obtained from the shafts’ corresponding bearing areas.
2. Clean the void space between the forward and aft bearings of all mud, dirt, loose rust, scale, and foreign matter to an SSPC-SP1 condition. Coat the entire interior surface of the void thoroughly and evenly with two coats of an approved Surface Tolerant Epoxy.
3. Renew the zinc located within the shaft void space.
4. Clean the void space in the propeller hub to remove all traces of preservative.
5. Clean and dress the threads on the propeller nut and the propeller shaft.
6. Match mark the stuffing box and remove the stuffing box from the ship to the shop.
17 | P a g e
7. Clean the stuffing box of all growth, debris, grease, and foreign material to an SSPC-SP1 condition.
8. Inspect the stuffing box and “Air-seal” ring for damage and excessive wear that may affect its performance.
9. Install the stuffing box in its original position using a new gasket and monel fasteners. Apply an anti-seize lubricant to fastener threads prior to installing and tightening.
e. After completion of all other associated work, install the propulsion shaft and propeller in their original positions.
f. Prior to final make-up of the propeller, tightly pack the area of the shaft in way of the end of the liner and the propeller hub with an ABS approved corrosion preventive compound. Pack the propeller hub stuffing box with approved filler and install using a new rubber ring. Install and repack the gland and securely lock the nuts in place, using monel or CRES wire.
g. CRITICAL NOTE: Piecing of rubber ring will not be permitted. Ring shall be installed as one-piece.
h. Renew the propeller nut keepers.
i. Clean the fairwater cap to remove all traces of preservative and cement. Properly install the fairwater cap with a new rubber ring. Replace any missing or defective fasteners as original and perform drilling and/or tapping as required. For estimating purposes, assume 15% of fasteners require replacement. Cement recesses to provide a smooth contour consistent with the shape of the fairwater cap.
j. Fill the void in the propeller hub and the fairwater cap with a corrosion preventive compound as specified in the latest revision of COMSCINST 4750.2, Appendix H, and reinstall plugs.
k. Reinstall rope guards and shaft fairwaters.
l. Replace all missing, broken or defective studs or bolts. For estimating purposes, assume 15%.
3.4.5 Quality Assurance
a. No additional requirements.
18 | P a g e
3.4.6 Deliverables
a. Propeller Shaft - In-shop Inspection Report
b. Propeller Shaft - Bearing areas dimensions
c. Strut and Stern Bearing dimensions
3.4.7 Notes
a. None
19 | P a g e
3.5 ITEM NO. 305: Propeller Inspections and Repairs
3.5.1 Abstract - This item provides the requirements for
removal, inspection, repairs and installation of the ship’s propeller.
3.5.2 References
(a) SPURS drawing -002, “NOAA Thomas Jefferson SPURS Prop Mounted MV-19_15”
(b) NOAA Ship Thomas Jefferson drawing no. 161-6634743, “Shaft Strut”
(c) NOAA Ship Thomas Jefferson drawing no. 245-6634744, “Propeller Diagram”
3.5.3 Government-Furnished Material
a. None
3.5.4 Requirements
a. Fair and straighten all minor indents or distortions in both leading and trailing edges of the propeller.
b. Grind smooth all leading and trailing edges.
c. Dress or ground out minor cracks.
d. Perform the following additional work on the propeller and the strut:
1. Replace the Spurs model MV 19/15 Line & Net Cutters. Upgrade the system to include a filler plate between the rotary blade assemblies on the propeller and a stationary blade assembly mounting plate on the strut.
2. Perform modifications to the propeller and strut in accordance with reference (a) and the manufacturer’s off-site and on-site guidance. The manufacturer’s representative must be on-site during installation of the propeller to ensure proper clearances between the stationary and rotating blades
a) Modify the forward face of the propeller for installation of a riding surface for the stationary cutter head to prevent wearing of the propeller.
20 | P a g e
b) Install the new Spurs filler plate and rotary Blade assembly on the propeller.
c) Modify the strut to provide a mounting surface for the stationary blade assembly that allows for replacement of the stationary cutter assembly by divers without the need for welding.
d) Install the new stationary blade assembly on the strut.
e. After cleaning and all other work, balance the propeller. Provide a certification for the balancing.
f. Drawings:
1. Develop ACAD “As-Built” drawing of references (b) and (c) to incorporate appropriate sections of reference (a) with input from NOAA. Submit the drawings to the COR for review and acceptance.
2. Provide four full size hard copies of accepted drawings on bond paper.
3. All drawings provided shall be in AutoCAD Version 2012 and PDF with electronic copies provided on CD-ROM.
3.5.5 Quality Assurance
a. Take the following data on the installed propeller:
1. Pitch of each blade at 0.7 radius, and 0.9 radius.
2. Stamping on hub for propeller diameter.
3. Stamping on hub for manufacturer, propeller number, and A.B.S. number.
4. Stamping on hub for weight.
b. Measure and record the Line & Net Cutters clearance between the new rotary and stationary blade assemblies.
21 | P a g e
3.5.6 Deliverables
a. Propeller inspection report
b. Propeller data
c. Line & Net Cutters clearances
d. ACAD drawing TJ-161-6634743
e. ACAD drawing TJ-245-6634744
3.5.7 Notes
a. Coordinate work on this item with Basic Item “Dry Docking and Routine Dry Dock Work” and “Propeller Shaft Inspection and Repairs.”
b. Existing stationary blade assembly of the Spurs Line and Net Cutter has failed.
c. Spurs Line and Net Cutter contact information:
Spurs Marine 201 SW 33rd Street Ft. Lauderdale, FL 33315 Attn: Donald Govan 800-824-5372 954-463-2707 E-mail: spurs@spursmarine.com Website: www.spursmarine.com
22 | P a g e
3.6 ITEM NO. 306: ABS Ballast Tank Inspections
3.6.1 Abstract - This item contains the requirements for
opening, inspecting and closing the ship’s Ballast tanks
3.6.2 References
(a) NOAA Ship Thomas Jefferson drawing no. 085-6980295, "Tank Capacity and Deadweight Scale”
3.6.3 Government-Furnished Material
a. None
3.6.4 Requirements
a. Prior to drydocking the ship, prepare a Liquid Transfer/Removal Plan outlining a comprehensive procedure for transfer and removal of all liquids in the tanks to be inspected. Included shall be the quantities and location of liquids to be transferred between tanks and the quantities and location of liquids to be removed, stored, disposed of and returned. If transfer of liquids while the ship is drydocked is planned, the dockmaster shall approve the Plan. A copy of the Plan shall be submitted to the COR at least 3 work days prior to drydocking the ship.
b. Open, ventilate, and clean the ballast tanks specified in Table 306-1 safe for entry of workers. Post a gas-free certificate, issued by a Marine Chemist certified by the National Fire Protection Association, at the brow. Provide a copy of each gas-free certificate to the COR.
Table 306-1: Ballast Tanks
LOCATION CAPACITY
GALLONS
Low Suction LOCATION CAPACITY
GALLONS
Low Suction
4-0-0 17,547 41 4-8-1 11,044 95 4-8-2 11,044 224 4-22-0 6,407 770 4-22-1 4,081 292 4-22-2 4,081 281 3-51-0 23,583 1,295 4-59-0 5,884 770 4-75-0 11,786 1,295
c. Except as otherwise specified, NOAA will pump down tanks to the low suction level of the installed ship's piping system. The contractor shall pump out and properly dispose of all remaining water, sludge, and other tank contents.
23 | P a g e
d. High pressure water wash tanks including sides, overhead, bottom and all internals to remove slime and light scale. Light scraping may be necessary but take care not to damage coatings. Pump out, remove, and properly dispose of all residual water and debris.
e. Rig sufficient lighting in each opened tank to allow a thorough inspection.
f. After all tanks have been inspected by the ABS Surveyor and when accepted by the COR, close each opened tank using new gaskets. Renew all missing and broken fasteners and chase all manhole cover threads. Estimate 10% missing or broken fasteners. Notify the COR at least four hours in advance of closing each tank. Immediately prior to closing each tank, the COR or a member of the ship's engineering force will inspect the tanks interior to verify that rags or other residual debris has not been left.
g. Refill ballast tanks with municipal water and carefully top off the tanks. Some of the ballast tanks have common vents. DO NOT OVERFILL TANKS.
3.6.5 Quality Assurance
a. Perform a 2.0 psig air test on each tank after closing. Hold the pressure and check manhole covers for leaks using a soapy water solution.
b. During the filling process, recheck manhole covers and vents for leaks.
3.6.6 Deliverables
3.6.7 Ballast Tank Inspection – Air Test results
3.6.8 Notes
a. Notify the COR and ABS 24 hours before tank inspection.
b. Reference (a) is listed as a source for obtaining information.
c. Coordinate work on this item with Basic Item “Salt Water Ballast Tank Preservation”
24 | P a g e
3.7 ITEM NO. 307: Ballast Tank Preservation
3.7.1 Abstract – This item contains the requirements for
cleaning, preparation and coating of identified tanks.
3.7.2 References
(a) NOAA Ship Thomas Jefferson drawing no. 085-6980295, "Tank Capacity and Deadweight Scale”
(b) NOAA Ship Thomas Jefferson drawing no. TJ-568-004D, “Bow Thruster Installation”
(c) NOAA Ship Thomas Jefferson drawing no. 101-6634860, “Structural Module 1”
(d) NOAA Ship Thomas Jefferson drawing no. 101-6634861.
“Structural Module 2”
3.7.3 Government-Furnished Material
a. None
3.7.4 Requirements
a. Powerwash the tank surfaces to remove ingested salts from the surfaces.
b. Prepare and preserve the entire interior of Ballast Tanks 4-8-1, 4-8-2, 4-22-1, 4-22-2 and 4-75-0 in accordance with GENERAL Section reference 2.1.2. Upgrade the preservation system to a high solids, edge retentive paint system for a service life of 10 - 12 years.
c. Perform the following additional work in Ballast Tanks 4-8-1 and 4-8-2:
1. Open the manholes accesses into the lower section of the Bow Thruster Trunk (4-12-0), prepare and preserve the manhole covers the same as the tank interior, prepare and preserve the lower section of the Bow Thruster Trunk the same as the tank interior, and close the manhole accesses using new stainless steel fasteners with an anti-seize lubricant.
2. Mechanically rout out the flood pipe connecting the forward and aft sections of the tanks.
3. Remove disused brackets and standoffs.
25 | P a g e
3.7.5 Quality Assurance
a. Perform surface chloride checks of cleaned surfaces to ensure acceptable low concentrations.
3.7.6 Deliverables
a. Ballast Tank Preservation - chloride test
3.7.7 Notes
a. References (a) through (d) are provided as source for obtaining information.
b. Coordinate work on this item with Optional Item “Permanent Ballast Installation” if awarded.
26 | P a g e
3.8 ITEM NO. 308: Sea Valve Overhauls
3.8.1 Abstract - This item provides the requirements for
removal, overhaul and installation of the sea valves on the ship.
3.8.2 References
(a) NOAA Standard Specification AMC-505-1B, “Valve Overhaul and Test”
(b) NOAA Ship Thomas Jefferson drawing 163-6634821, “Seachest Details”
(c) NOAA Ship Thomas Jefferson drawing 524-6634839, “Seachest Cross-Over Piping”
3.8.3 Government-Furnished Material
a. None
3.8.4 Requirements
a. Remove, overhaul, test and reinstall the valves listed in Table 307-1 in accordance with reference (a). The term “overhaul” used in reference (a) shall be redefined for this work item to be the same as “rebuild” is defined in NOAA Standard Specification AMC-000-1F. In lieu of overhaul, the contractor may renew any valves equal to or smaller than 3 inches.
b. Perform the following work on the two 12 inch simplex sea chest strainers:
c. Remove to the shop.
d. Thoroughly clean the interior housing to remove all growth and other foreign matter.
e. Rework all mating and sealing surfaces to reestablish their mating and sealing capabilities.
f. Conduct a visual inspection of the housing for evidence of damage or deterioration.
g. Prepare and preserve the interior and exterior surfaces in accordance with GENERAL Section reference 2.1.2.
Apply paint system STL-11 to the prepared surfaces.
27 | P a g e
h. Reassemble the strainer using a new gasket and fasteners.
i. Install on the ship in its original location using new fasteners.
j. After reassembly and prior to the shop hydro test of all steel valves and spool pieces, apply the first coat of paint system STL-11.
k. Prior to installing on the ship, apply the second coat of paint system STL-11 on the valves and spool pieces. Top coat color shall be same as found.
l. Apply an anti-seize lubricant to fastener threads prior to installing and tightening.
m. Power tool clean and preserve the tank top and exposed areas around the two simplex sea chest strainers in accordance with reference 2.1.2. Apply paint system STL-11.
Table 307-1: Sea Valves
NO. Service Location Space/Frm
Size/type
1 SSVS Discharge Scientic Stores/22s
2" swing check, screwed
2 SSVS Discharge Scientic Stores/22s
2" gate, flanged
3 Velocimeter primary seawater supply
Transducer Void/33-34s
1" gate, flanged
4 Salinometer secondary seawater supply
Transducer Void/32-33s
1½” gate, flanged
5 Velocimeter primary seawater supply
Transducer Void/33-34s
2" gate, flanged
6 Salinometer secondary seawater supply
Transducer Void/32-33s
2" ball, flanged
7 Main Engine OVBD Engine Room/64p
6" butterfly (lug)
8 Bilge Emergency Suction
Engine Room/65p
4" Angle, flanged
9 Sewage OVBD Engine Room/54p
3" swing check, flanged
28 | P a g e
NO. Service Location Space/Frm
Size/type
10 Sewage OVBD Engine Room/54p
3" gate, flanged
11 Sewage OVBD Engine Room/57s
3" swing check, flanged
12 Sewage OVBD Engine Room/57s
3" gate, flanged
13 Grey Water OVBD Engine Room/61s
3" gate, flanged
14 Grey Water OVBD Engine Room/61s
3" swing check, flanged
15 A.C. Condensers OVBD Engine Room/59s
6" butterfly (lug)
16 Auxiliary SW OVBD Engine Room/61s
4" butterfly (lug)
17 Auxiliary SW OVBD Engine Room/66s
4" swing check, flanged
18 RO units OVBD Engine Room/66s
1½” bronze gate, flanged
19 Reefer condenser OVBD Engine Room/63p
1¼” gate, flanged
20 Auxiliary SW OVBD Engine Room/66s
4" butterfly (wafer)
21 Bilge/ballast OVBD Engine Room/68p
4" swing check, flanged
22 Bilge/ballast OVBD Engine Room/68p
4" butterfly (lug)
23 OWS OVBD Engine Room/70p
Upgrade to 1¼” globe, flanged
24 OWS OVBD Engine Room/70p
1¼” swing check, flanged
25 SSDG OVBD Engine Room/73p
4" butterfly, wafer
26 RO Distilling Units Suction
Engine Room/71s
1¼” bronze globe, flanged
29 | P a g e
NO. Service Location Space/Frm
Size/type
27 Main Sea Chest Engine Room/71p
12” butterfly (lug)
28 Main Sea Chest Engine Room/71p
12" butterfly (wafer)
29 Main Sea Chest Engine Room/71s
12” butterfly (lug)
30 Main Sea Chest Engine Room/71s
12" butterfly (wafer)
Main Sea Chest: Vent Engine Room/71p
2" globe, screwed
32 Main Sea Chest: Vent Engine Room/71s
2" globe, screwed
33 Fire Pump Sea Chest ballast tank 4-75-0/82p
5" butterfly (lug)
34 Fire Pump Sea Chest:
Vent
Machine Shop/82p
1½” gate, screwed
35 Fire Pump Sea Chest:
Vent
Machine Shop/82p
1½” swing check, screwed
36 Fire Pump Sea Chest:
Blow down
Machine Shop/82p
1” swing check, screwed
37 Fire Pump Sea Chest:
Blow down
Machine Shop/82p
1" Ball, screwed
38 Grey Water Drain Machine Shop/83p
3" Check, flanged
39 Grey Water Drain Machine Shop/83p gate, flanged
40 Fire Pump bypass Machine Shop/83p
1" Check, flanged
41 Fire Pump bypass Machine Shop/83p
1" globe, welded
3.8.5 Quality Assurance
a. After completion of all work and prior to preservation, perform a hydrostatic pressure test two simplex strainers at a pressure of 60 psi. Hold the pressure for 10 minutes.
30 | P a g e
3.8.6 Deliverables
a. Sea Valve – Bluing Seat Check
b. Sea Valve – Hydrostatic test results
c. Strainer – Hydrostatic test results
3.8.7 Notes
a. This is a habitability item.
b. References (b) and (c) are listed as sources for obtaining information.
c. Strainer Data:
Manufacturer: Core Industries Inc. Mueller Steam Model/Type: 12" 155M, SPLX STR, 125# FLG’D Clamp
31 | P a g e
3.9 ITEM NO. 309: HVAC System Upgrades
3.9.1 Abstract - This item provides the requirements for
removal of the ship’s existing HVAC system and installation of an upgraded modular design, City Multi® HVAC system throughout the ship.
3.9.2 References
(a) NOAA Ship Thomas Jefferson drawing 185-3275005-2, “Foundation Incidental HVAC Upgrade Main Deck”
(b) NOAA Ship Thomas Jefferson drawing 185-3275005-3, “Foundations Incidental HVAC Upgr 01 Lvl and Above”
(c) NOAA Ship Thomas Jefferson drawing 185-3275005-4, “Foundation Incidental HVAC Upgr Second Deck and Below”
(d) NOAA Ship Thomas Jefferson drawing 185-3275005-5, “Miscellaneous Electrical Foundations Incidental HVAC Upgrade”
(e) NOAA Ship Thomas Jefferson drawing 185-3275005-6, “Pump Foundations Incidental HVAC Upgrade”
(f) NOAA Ship Thomas Jefferson drawing 321-3274004-2, “HVAC Elec Power Mods Incdt to HVAC Mods”
(g) NOAA Ship Thomas Jefferson drawing 321-3274004-3, “HVAC Elec Control Mods Incdt to HVAC Mods”
(h) NOAA Ship Thomas Jefferson drawing 321-3274004-4, “Power System Mods Incidental Aux Seawater Clg Pumps Replace A/C Seawater Clg Pumps Instl”
(i) NOAA Ship Thomas Jefferson drawing 331-3275004-1, “Misc Electrical Modifications”
(j) NOAA Ship Thomas Jefferson drawing 512-3275003-7, “HVAC Mods 01 Lvl & Abv”
(k) NOAA Ship Thomas Jefferson drawing 512-3275003-8, “HVAC Mods Main Deck”
(l) NOAA Ship Thomas Jefferson drawing 512-3275003-9, “HVAC Mods 2nd Deck & Below”
(m) NOAA Ship Thomas Jefferson drawing 514-3275003-2, “Chilled Water Piping System Modifications”
32 | P a g e
(n) NOAA Ship Thomas Jefferson drawing 514-3275003-3, “Cooling Water Piping Installation”
(o) NOAA Ship Thomas Jefferson drawing 514-3275003-6, “A/C Piping Installation Second Deck and Below”
(p) NOAA Ship Thomas Jefferson drawing 514-3275003-11, “A/C Piping Installation Main Deck”
(q) NOAA Ship Thomas Jefferson drawing 514-3275003-12, “A/C Piping Installation Fcsle Deck & Abv”
(r) NOAA Ship Thomas Jefferson drawing 524-3275003-1, “Sea Water Cooling Piping Mods HVAC Upgrade”
(s) NOAA Ship Thomas Jefferson drawing 528-3275003-4, “Condensate Drain Piping Removal”
(t) NOAA Ship Thomas Jefferson drawing 528-3275003-5, “Condensate Drain Piping Installation 2nd DK & Blw”
(u) NOAA Ship Thomas Jefferson drawing 528-3275003-13, “Condensate Drain Piping Installation Main Deck”
(v) NOAA Ship Thomas Jefferson drawing 528-3275003-14, “Condensate Drain Piping Installation Fcsle DK & Above”
(w) NOAA Ship Thomas Jefferson drawing 621-3275005-1, “Metal Joiner Bulkheads & Door Incidental HVAC Upgrade”
(x) NOAA Standard Specification MOC-300-3, “General Requirements for Electrical/Electronic Items”
(y) NOAA Standard Specification AMC-635-2, “Thermal Insulation for Compartments”
(z) NOAA Standard Specification AMC-635-1, “Thermal Insulation of Piping”
(aa) NOAA Ship Thomas Jefferson drawing 637-6634934, “Ceiling Layout Lower Deck and Flat”
(ab) NOAA Ship Thomas Jefferson drawing 637-6634935, “Ceiling Layout Main Deck”
(ac) NOAA Ship Thomas Jefferson drawing 637-6634936, “Ceiling Layout Fcsle Deck”
(ad) NOAA Ship Thomas Jefferson drawing 637-6634937, 33 | P a g e
“Ceiling Layout Upper Deck”
(ae) NOAA Ship Thomas Jefferson drawing 637-6634938, “Ceiling Layout Bridge Deck”
(af) NOAA Ship Thomas Jefferson drawing 507-6643858. “HVAC Label Plate List”
(ag) NOAA Ship Thomas Jefferson drawing 985-6634639, “Fire Control Plan”
(ah) NOAA Standard Specification AMC-300-1, “Overhaul of Electrical Rotating Machinery”
(ai) NOAA Ship Thomas Jefferson manual TJ-503-08, “Chill Water Pump”
(aj) NOAA Ship Thomas Jefferson Diamond System Builder drawing “Thomas Jefferson DSB HVAC System Design”
(ak) NOAA Ship Thomas Jefferson manual, “Consilium Salwico CS4000 Operations Manual”
3.9.3 Government-Furnished Material
a. Two each - Air Handling Unit, Model: PKFY-P30NHMU-ER2 (est cost $1,900 each)
b. One each - Air Handling Unit, Model: PKFY-P12NHMU-ER2 (est cost $1,500 each)
c. Eight each - Air Handling Unit, Model: PLFY-P08NCMU- ER4 (est cost $1,920 each)
d. Twenty Two each - Air Handling Unit, Model: PLFY- P12NCMU-ER4 (est cost $2,010 each)
e. Twenty five each - Air Handling Unit, Model: PLFY- P15NCMU-ER4 (est cost @2,100 each)
f. Two each - Air Handling Unit, Model: PLFY-P24NCMU-ER4 (est cost $2,800 each)
g. Three each - Air Handling Unit, Model: PLFY-P36NBMU- ER4 (est cost $3,800 each)
h. Four each - BC Controller, Model: CMB-P1016NU-GA (est cost $13,500 each)
34 | P a g e
i. One each - BC Controller, Sub, Model: CMB-P104NU-GB (est cost $16,000 each)
j. Forty Seven each - Controller/Thermostat Model: PAR- 31MAA-J (est cost $30 each)
k. Seven each - Joint Kit CMY-Y102SS-G2 (est cost $1,200 each)
l. One each - Joint Kit CMY-Y102S-G2 (est cost $1,000 each)
m. Two each – Plate Heat Exchanger Model: AMDX-20 (est cost $4,000 each)
n. Two each - SIEMENS MCC 5 HP, MCC 5 HP_1 (est cost $12,000 each)
o. Two each - SIEMENS MCC 15 HP, MCC 15 HP_1 (est cost $16,000)
p. Two each - PUMP, CENTRIFUGAL, 3 X 2-1/2 X 7, W/254JM 15 HP MOTOR (est cost $19,000 each)
q. Two each - PUMP, CENTRIFUGAL, 1-1/2 X 1-1/4 X 7, W/184JM 5 HP MOTOR (est cost $17,000 each)
r. Four each – Water Cooled Condensing Unit Model Number:
PQRY-P240YSHMU-A, 460V/3PH/60 HZ with Twinning CMY-QlOOVBK (est cost $35,000 each)
s. Two each – PUMP, CENTRIFUGAL, 1½X2-8, W/215JM 10 HP MOTOR (est cost $5,500 each)
3.9.4 Requirements
a. General:
1. The contractor shall design and make all necessary arrangements (temporary accesses, install padeyes and lifting gear, rigging path, etc.) to safely install the HVAC modifications and auxiliary fixtures, using References (a) through (w) as guidance.
2. Reference (aj) was developed in Diamond System Builder which is a proprietary program of Mitsubishi. The contractor shall update reference (aj) prior to any installation and throughout the installation of the GFM Mitsubishi City Multi® system. Set equipment M-Net addresses to allow for future
35 | P a g e expansion using all ports of the Main BC and Sub BC controllers.
3. Perform all electrical work in accordance with reference (x).
4. Use USCG and ABS approved fire rated, watertight conduits for fire rated, watertight penetrations.
5. Repair all compartment insulation in accordance with reference (y).
6. Repair all damaged piping insulation in accordance with reference (z).
7. Minor deviations from the drawings are authorized if appearance, function and strength are not impaired.
8. Obtain the services of an Original Equipment Manufacture’s (OEM’s) authorized representative of the GFM to provide on-site and off-site support during installation of the new Mitsubishi City Multi® HVAC system.
9. Perform all installations of the GFM Mitsubishi City Multi® in accordance with the OEM’s installation requirements.
10. Provide the services of an OEM’s authorized representative to commission the final installation and provide onsite training for the operation and preventive maintenance of the installed Mitsubishi City Multi® HVAC system to ship’s force.
11. Develop and provide for approval a test plan to verify the proper operation of the new HVAC system. The test plan is to include:
a) Calculations for Total Connected Volume for each of the BC Controllers per ASHRAE Standard 15-2013
b) Calculated and actual quantity of refrigerant for each of the BC Controllers
c) OEM inspections and commissioning requirements
d) ABS inspections for maintaining watertight and firetight integrity.
36 | P a g e
12. Servicing technicians for the firefighting equipment and fire detection system must be current factory trained and authorized by the OEM. Provide a copy of Authorized Distributor Letter from OEM.
13. Servicing technicians for the firefighting equipment and fire detection system must be covered by a current ABS certificate for Fire Extinguishing Systems Inspection/Maintenance Firms. Provide a copy of the ABS Fire Extinguishing Systems Inspection/Maintenance Certificate.
b. This work item affects the following spaces:
1. Pilot House 03-27-0
2. Radio Room 03-33-2
3. Chart Room 03-36-0
4. Aft Radio Room 03-39-2
5. Locker 02-24-0
6. Captain’s Office 02-24-1
7. XO/Ships Office 02-24-2
8. Passage 02-26-0
9. CG Locker 02-31-1
10. XO Stateroom 02-31-2
11. Stair Passage 02-33-1
12. Captain’s Stateroom 02-37-3
13. Stateroom 02-40-2
14. Passage 01-17-0
15. Chief Engineer’s Office 01-19-1
16. Operation Officers Office 01-19-2
17. Operations Officers Stateroom 01-23-2
18. Chief Engineer’s Stateroom 01-25-1
19. 1st Asst Engineers Stateroom 01-29-2
37 | P a g e
20. Fan Room 01-30-3
21. Stateroom 01-34-1
22. T/SH 01-34-2
23. Stateroom 01-34-4
24. Stateroom 01-39-1
25. Stateroom 01-39-2
26. Stateroom 01-43-4
27. Passage 1-8-0
28. GSM Store 1-8-1
29. CG Locker 1-8-2
30. Ship’s Store 1-8-3
31. Fan room 1-8-4
32. Mess Deck 1-16-1
33. Galley 1-16-2
34. Dry Store 1-25-2
35. Chief Steward’s Office 1-25-4
36. Lounge 1-30-1
37. SSFC UPS Space 1-32-2
38. Plot Room|Server Room 1-32-4
39. Survey Control Center 1-37-2 (future)
40. Hospital 1-42-1
41. Dive Locker 1-77-0
42. Passage 2-8-0
43. GSM Store 2-8-1
44. Ship Store 2-8-2
38 | P a g e
45. Scientific Store 2-22-2
46. Scientific Store 2-22-3
47. Crew Stateroom 2-25-1
48. Crew Stateroom 2-30-1
49. Crew Stateroom 2-34-1
50. Crew Stateroom 2-34-2
51. Crew Stateroom 2-39-1
52. Crew Stateroom 2-39-2
53. Crew Stateroom 2-43-1
54. Crew Stateroom 2-43-2
55. Crew Stateroom 2-47-1
56. Crew Stateroom 2-47-2
57. Crew Stateroom 2-51-1
58. Crew Stateroom 2-51-2
59. MCS 2-63-1
60. Exercise Room 3-22-0
c. Structural:
1. Removals:
a) Remove and scrap foundations for AHU R01-33- 1, AHU R1-11-2, AHU R1-60-2, AHU R2-32-2 and AHU R2-69-1 using references (j), (k) and
(l) for guidance.
b) Remove and scrap Auxiliary Pump No. 1 and No. 2 foundations using reference (e) for guidance.
2. Installations:
a) Fabricate and install new foundations for four water cooled A/C condensers using references (a) and (b) for guidance.
39 | P a g e
b) Fabricate and install foundations for sixty-three air handling units, five BC controllers and one supply fan using references (a), (b) and (c) for guidance.
c) Fabricate and install two new pump foundations for aux. seawater pumps using reference (e) for guidance.
d) Fabricate and install two new pump foundations for A/C seawater pumps using reference (e) for guidance.
e) Design, fabricate and install two new pump foundations for A/C Fresh Water Cooling Pumps.
f) Fabricate and install a new power panel and transformer foundation using references (d) and (f) for guidance.
3. After removals, power tool prepare and preserve the decks in Fan Room (1-8-4), Fan Room (01-30-3), exposed deck under AHU R2-32-2, exposed deck under AHU R2-69-1, exposed tank top under Auxiliary Pump No.