cedar_creek_specs_final.pdf

PDF 291 KB Posted

Attached to
Cedar Creek Dam Diversion Channel Lining Federal contract opportunity
Solicitation number
12SPEC18Q0029
Issued by
Department of Agriculture National Resources Conservation Service Headquarters

About this file

Specs

View the file

Other files for this federal contract opportunity

Other files attached to Cedar Creek Dam Diversion Channel Lining, newest first.
File Type Posted
Clearing_Grubbing.pdf PDF
cedar_creek_site_showing_minutes.pdf PDF
Amendment_0003_Docs.pdf PDF
Amendment_0003.pdf PDF
Amendment_0002.pdf PDF
Amendment_1.pdf PDF
12SPEC18Q0029_1442.pdf PDF
CEDAR_CREEK_FINAL_APPROVED_DRAWINGS.PDF PDF
Wage_Rates.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Spec No. Title No. Pages

5 Pollution Control 4

6 Seeding, Sprigging, and Mulching 4

7 Construction Surveys 4

8 Mobilization and Demobilization 2

11 Removal of Water 3

21 Excavation 5

23 Earthfill 7

400 Geocomposite Liner 3

Spec. No. Title No. Pages

592 Geotextile 3

600 Geocomposite Liner 1

Cedar Creek Diversion Channel Lining

City of Columbia Falls

Summary of Material Specifications

Summary of Construction Specifications

NRCS-NEH-642 5-1 January 2014

Construction Specification 5—Pollution Control

1. Scope The work consists of installing measures or performing work to control erosion and minimize the production of sediment and other pollutants to water and air from construction activities.

The following BioPreferred® product categories are applicable to this specification:

mulch and compost materials erosion control materials fertilizers dust suppressants agricultural spray adjuvants

2. Material Silt fence shall conform to the requirement of Materials Specification 592, Geotextile. All other material furnished shall meet the requirements of the material specifications listed in section 8 of this specification.

3. Erosion and sediment control measures and works The measures and works shall include, but are not limited to, the following:

Staging of earthwork activities—The excavation and moving of soil materials shall be scheduled to minimize the size of areas disturbed and unprotected from erosion for the shortest reasonable time.

Seeding—Seeding to protect disturbed areas shall occur as soon as reasonably possible following completion of that earthwork activity.

Mulching—Mulching to provide temporary protection of the soil surface from erosion.

Diversions—Diversions to divert water from work areas and to collect water from work areas for treatment and safe disposition. They are temporary and shall be removed and the area restored to its near original condition when the diversions are no longer required or when permanent measures are installed.

Stream crossings—Culverts or bridges where equipment must cross streams. They are temporary and shall be removed and the area restored to its near original condition when the crossings are no longer required or when permanent measures are installed.

Sediment basins—Sediment basins collect, settle, and eliminate sediment from eroding areas from impacting properties and streams below the construction site(s). These basins are temporary and shall be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.

Sediment filters—Straw bale filters or geotextile silt fences trap sediment from areas of limited runoff. Sediment filters shall be properly anchored to prevent erosion under or around them. Silt fences shall be installed and maintained in accordance with ASTM D6462. These filters are temporary and shall be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.

Waterways—Waterways for the safe disposal of runoff from fields, diversions, and other structures or measures. These works are temporary and shall be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.

Other—Additional protection measures as specified in section 8 of this specification or required by Federal, State, or Local government.

4. Chemical pollution The contractor shall provide watertight tanks or barrels or construct a sump sealed with plastic sheets to collect and temporarily contain chemical pollutants, such as drained lubricating or transmission fluids, grease, soaps, concrete mixer

NRCS-NEH-642 5-2 January 2014 washwater, or asphalt, produced as a by-product of the construction activities. Pollutants shall be disposed of in accordance with appropriate State and Federal regulations. At the completion of the construction work, tanks, barrels, and sumps shall be removed and the area restored to its original condition as specified in section 8 of this specification. Sump removal shall be conducted without causing pollution.

Sanitary facilities, such as chemical toilets, or septic tanks shall not be located next to live streams, wells, or springs. They shall be located at a distance sufficient to prevent contamination of any water source. At the completion of construction activities, facilities shall be disposed of without causing pollution as specified in section 8 of this specification.

5. Air pollution The burning of brush or slash and the disposal of other materials shall adhere to State and Local regulations.

Fire prevention measures shall be taken to prevent the start or spreading of wildfires that may result from project activities. Firebreaks or guards shall be constructed and maintained at locations shown on the drawings.

All public access or haul roads used by the contractor during construction of the project shall be sprinkled or otherwise treated to fully suppress dust. All dust control methods shall ensure safe construction operations at all times. If chemical dust suppressants are applied, the material shall be a commercially available product specifically designed for dust suppression and the application shall follow manufacturer's requirements and recommendations. A copy of the product data sheet and manufacturer's recommended application procedures shall be provided to the engineer 5 working days before the first application.

6. Maintenance, removal, and restoration All pollution control measures and temporary works shall be adequately maintained in a functional condition for the duration of the construction period. All temporary measures shall be removed and the site restored to near original condition.

7. Measurement and payment Method 1—For items of work for which specific unit prices are established in the contract, each item is measured to the nearest unit applicable. Payment for each item is made at the contract unit price for that item. For water or chemical suppressant items used for dust control for which items of work are established in section 8 of this specification, measurement for payment will not include water or chemical suppressants that are used inappropriately or excessive to need. Such payment will constitute full compensation for the completion of the work.

Method 2—For items of work for which lump sum prices are established in the contract, payment is made as the work proceeds and supported by invoices presented by the contractor that reflect actual costs. If the total of all progress payments is less than the lump sum contract price for this item, the balance remaining for this item will be included in the final contract payment. Payment of the lump sum contract price will constitute full compensation for completion of the work.

Method 3—For items of work for which lump sum prices are established in the contract, payment will be prorated and provided in equal amounts on each monthly progress payment estimate. The number of months used for prorating shall be the number estimated to complete the work as outlined in the contractor's approved construction schedule. The final month's prorate amount will be provided with the final contract payment. Payment as described will constitute full compensation for completion of the work.

All Methods—The following provisions apply to all methods of measurement and payment. Compensation for any item of work described in the contract, but not listed in the bid schedule is included in the payment for the item of work to which it is made subsidiary. Such items, and the items to which they are made subsidiary, are identified in section 8 of this specification.

NRCS-Montana Cedar Creek Diversion Channel Lining 5-3 June 2018

8. ITEMS OF WORK AND CONSTRUCTION DETAILS

Items of work to be performed in conformance with this specification and construction details are:

a. Bid Item 3, Pollution Control

1. This item shall consist of all work required by the contractor to prevent water and air pollution during construction and to obtain Montana Pollutant Discharge Elimination System permits.

2. In section 3, EROSION AND SEDIMENT CONTROL MEASURES AND WORKS, a Notice of Intent (NOI) Package shall be developed by the contractor and submitted to the Montana Department of Environmental Quality (MT DEQ). The NOI Package shall include a completed NOI form, Storm Water Pollution Prevention Plan (SWPPP), and application fee. Prior to submittal to MT DEQ, the draft SWPPP shall be presented to the landowner for review and approval. A copy of the MT DEQ’s standard response letter indicating the NOI package has been received shall be submitted to the Contracting Officer prior to initiation of construction.

3. In section 3, EROSION AND SEDIMENT CONTROL MEASURES AND WORKS, the contractor shall be responsible for administration of and compliance with the approved SWPPP and permit. The measures and works shall be those required by construction operations in accordance with the approved SWPPP. The contractor shall be responsible for submitting a Notice of Termination (NOT) upon project completion when the required conditions have been met.

4. In section 3, EROSION AND SEDIMENT CONTROL MEASURES AND WORKS, the contractor shall be responsible for determining the necessity for and, if necessary, obtaining a General Permit for Construction Dewatering. This permit is authorized under the Montana Pollutant Discharge Elimination System and serviced by MT DEQ.

5. In section 3, EROSION AND SEDIMENT CONTROL MEASURES AND WORKS, all disturbed areas, including staging, temporary roads, stockpile, and borrow areas, shall be reclaimed through seedbed preparation and seeding according to Construction Specification 6, Seeding, Sprigging, and Mulching.

Payment for such work is included in Bid Item 4.

6. In section 4, CHEMICAL POLLUTION, construction equipment shall be kept in good working order, and free of oil, hydraulic fluid, and diesel fuel leaks. Sanitary facilities shall be in temporary staging areas designated on the construction drawings. Following construction, the contractor shall remove all chemical pollutants and sanitary facilities from the site in a manner that assures pollution will not occur.

7. In section 6, MAINTENANCE, REMOVAL, AND RESTORATION, the contractor shall spray or otherwise control weed growth at the construction site. Weed removal shall be performed in a manner that does not damage adjacent vegetation. Approval for chemical applications shall be obtained from the landowner. The contractor shall obtain all required permits and comply with all Local, State, and Federal laws pertaining to herbicide application.

8. In section 6, MAINTENANCE, REMOVAL, AND RESTORATION, the project site shall be cleaned up, and all refuse, remaining stockpiles, and un-used materials, removed from the project site. Site cleanup shall be approved by the engineer prior to demobilization of equipment required for this item.

9. In section 7, MEASUREMENT AND PAYMENT, Method 3 shall apply.

b. Bid Item 9, Additive Pollution Control

1. This item shall consist of all work required by the contractor to prevent water and air pollution during construction and to obtain Montana Pollutant Discharge Elimination System permits within the additive lined reach, Stations 33+60 to 37+60.

Cedar Creek Diversion Channel Lining 5-4 June 2018

2. Construction details of Bid Item 3 shall also apply to Bid Item 9.

NRCS-NEH-642 6-1 January 2014

Construction Specification 6—Seeding, Sprigging, and Mulching

1. Scope The work consists of preparing the area for treatment; furnishing and placing seed, sprigs, mulch, fertilizer, inoculant, lime, and other soil amendments; and anchoring mulch in designated areas as specified.

The following BioPreferred® product categories are applicable to this specification:

mulch and compost materials erosion control materials fertilizers agricultural spray adjuvants

2. Material Seed—All seed shall conform to the current rules and regulations of the State where it is being used and shall be from the latest crop available. It shall meet or exceed the standard for purity and germination listed in section 7.

Seed shall be labeled in accordance with the state laws and the U.S. Department of Agriculture rules and regulations under the Federal Seed Act in effect on the date of invitations for bids. Bag tag figures are evidence of purity and germination.

No seed will be accepted with a test date of more than 9 months before the delivery date to the site.

Seed that has become wet, moldy, or otherwise damaged in transit or storage will not be accepted. The percent of noxious weed seed allowable shall be as defined in the current State laws relating to agricultural seeds. Each type of seed shall be delivered in separate sealed containers and fully tagged unless exception is granted in writing by the contracting officer.

Fertilizer—Unless otherwise specified, the fertilizer shall be a commercial grade fertilizer. It shall meet the standard for grade and quality specified by State law. Where fertilizer is furnished from bulk storage, the contractor shall furnish a supplier's certification of analysis and weight. When required by the contract, a representative sample of the fertilizer shall be furnished to the contracting officer for chemical analysis.

Inoculants—The inoculant for treating legume seeds shall be a pure culture of nitrogen-fixing bacteria prepared specifically for the species and shall not be used later than the date indicated on the container or as otherwise specified. A mixing medium, as recommended by the manufacturer, shall be used to bond the inoculant to the seed. Two times the amount of the inoculant recommended by the manufacturer shall be used except four times the amount shall be used when seed is applied using a hydraulic seeder. Seed shall be sown within 24 hours of treatment and shall not remain in the hydraulic seeder longer than 4 hours.

Lime and other soil amendments—Lime shall consist of standard ground agriculture limestone, or approved equivalent.

Standard ground agriculture limestone is defined as ground limestone meeting current requirements of the State Department of Agriculture. Other soil amendments shall meet quality criteria and application requirements specified in section 7.

Mulch tackifiers—Asphalt emulsion tackifiers shall conform to the requirements of ASTM D 977, Specification for Emulsified Asphalt. The emulsified asphalt may be rapid setting, medium setting, or slow setting. Nonasphaltic tackifiers required because of environmental considerations shall be as specified in section 7.

Straw mulch material—Straw mulch shall consist of wheat, barley, oat or rye straw, hay, grass cut from native grasses, or other plants as specified in section 7. The mulch material shall be air-dry, reasonably light in color, and shall not be musty, moldy, caked, or otherwise of low quality. The use of mulch that contains noxious weeds is not permitted. The contractor shall provide a method satisfactory to the contracting officer for determining weight of mulch furnished.

Other mulch materials—Mulching materials, such as wood cellulose fiber mulch, mulch tackifiers, synthetic fiber mulch, netting, and mesh, are other mulching materials that may be required for specialized locations and conditions. These materials, when specified, must be accompanied by the manufacturer's recommendations for methods of application.

NRCS-NEH-642 6-2 January 2014

3. Seeding mixtures, sod, sprigs, and dates of planting The application rate per acre for seed mixtures, sprigs, or sod and date of seeding or planting shall be as shown on the plans or as specified in section 7.

4. Seedbed preparation and treatment Areas to be treated shall be dressed to a smooth, firm surface. On sites where equipment can operate on slopes safely, the seedbed shall be adequately loosened (4 to 6 inches deep) and smoothed. Depending on soil and moisture conditions, disking or cultipacking, or both, may be necessary to properly prepare a seedbed. Where equipment cannot operate safely, the seedbed shall be prepared by hand methods by scarifying to provide a roughened soil surface so that broadcast seed will remain in place.

If seeding is to be accomplished immediately following construction operations, seedbed preparation may not be required except on a compacted, polished, or freshly cut soil surface.

Rocks larger than 6 inches in diameter, trash, weeds, and other debris that will interfere with seeding or maintenance operations shall be removed or disposed of as specified in section 7.

Seedbed preparation shall be discontinued when soil moisture conditions are not suitable for the preparation of a satisfactory seedbed as determined by the contracting officer's technical representative (COTR).

5. Seeding, sprigging, fertilizing, mulching, and stabilizing All seeding or sprigging operations shall be performed in such a manner that the seed or sprigs are applied in the specified quantities uniformly in the designated areas. The method and rate of seed application shall be as specified in section 7.

Unless otherwise specified, seeding or sprigging shall be accomplished within 2 days after final grading is completed and approved.

Fertilizer, lime, and other soil amendments shall be applied as specified in section 7. When specified, the fertilizer and soil amendments shall be thoroughly incorporated into the soil immediately following surface application.

The rate, amount, and kind of mulching or mesh shall be as specified in section 7. Mulches shall be applied uniformly to the designated areas. They shall be applied to areas seeded not later than 2 working days after seeding has been performed. Straw mulch material shall be stabilized within 24 hours of application using a mulch crimper or equivalent anchoring tool or by a suitable tackifier. When the mulch crimper or equivalent anchoring tool is used, it shall have straight blades and be the type manufactured expressly for and capable of firmly punching the mulch into the soil. Where the equipment can be safely operated, it shall be operated on the contour. Hand methods shall be used where equipment cannot safely operate to perform the work required.

The tackifier shall be applied uniformly over the mulch material at the specified rate, or it shall be injected into the mulch material as it is being applied. Mesh or netting stabilizing materials shall be applied smoothly, but loosely on the designated areas. The edges of these materials shall be buried or securely anchored using spikes or staples as specified in section 7.

The contractor shall maintain the mesh or netting areas until all work under the contract has been completed and accepted.

Maintenance shall consist of the repair of areas damaged by water erosion, wind, fire, or other causes. Such areas shall be repaired to reestablish the intended condition and to the design lines and grades required by the contract. The areas shall be refertilized, reseeded, and remulched before the new application of the mesh or netting.

6. Measurement and payment Method 1—For items of work for which specific unit prices are established in the contract, each area treated is measured as specified in section 7 and the area calculated to the nearest 0.1 acre. Payment for treatment is made at the contract unit price for the designated treatment, which will constitute full compensation for completion of the work.

When specified as an item of work, mesh or netting is measured to the nearest square yard of surface area covered and accepted. Payment is made at the contract unit price and will constitute full compensation for completion of the work.

NRCS-NEH-642 6-3 January 2014

Method 2—For items of work for which specific lump sum prices are established in the contract, the quantity of work will not be measured for payment. Payment for this item is made at the contract lump sum price for the item and will constitute full compensation for the completion of the work.

Method 3—For items of work for which lump sum prices are established in the contract, payment is made as the work proceeds. Progress payments will be determined as specified in section 7. Payment of the lump sum contract price will constitute full compensation for completion of the work.

All Methods—The following provisions apply to all methods of measurement and payment. Compensation for any item of work described in the contract, but not listed in the bid schedule is included in the payment for the item of work to which it is made subsidiary. Such items and the item(s) to which they are made subsidiary are identified in section 7.

Cedar Creek Diversion Channel Lining 6-4 June 2018

7. ITEMS OF WORK AND CONSTRUCTION DETAILS

Items of work to be performed in conformance with this specification and construction details are:

a. Bid Item 4, Seeding, Sprigging, and Mulching

1. This item shall consist of preparing the areas to be seeded and furnishing and applying the fertilizer and seed to all areas disturbed by construction activities.

2. In Section 4, SEEDBED PREPARATION AND TREATMENT, stripped material shall be spread in disturbed areas in accordance with Construction Specification 23, Earthfill. The spread material shall then be prepared in accordance with this section.

3. In Section 5, SEEDING, SPRIGGING, FERTILIZATING, MULCHING, AND STABILIZING, the following seed mixture and seeding rates of Pure Live Seed (PLS) by method shall be used:

Seed Species and Cultivar Percent of Mix

Drilled Rate

PLS

(lbs/acre)

Broadcast Rate

PLS

(lbs/acre)

Bluebunch wheatgrass - Goldar 30% 4.2 8.4

Rough fescue - Common 20% 2.4 4.8

Slender wheatgrass – Pryor/Primar/Copperhead/Revenue

30% 4.2 8.4

Western wheatgrass – Rosana/Rodan 20% 4.0 8.0

TOTALS 100% 14.8 29.6

Only certified seed of the above-named varieties shall be used. The seeding shall be completed immediately after construction, except that the seeding cannot be completed between September 15 and October 15. The preferred seeding period is October 15 through May 15.

A commercial 16-20-00-15 fertilizer shall be applied at the rate of 200 pounds per acre. It shall be spread uniformly and worked into the soil immediately. When disking is to be done, the fertilizer shall be placed prior to the disking operations.

Seed may be planted with a suitable grass seed drill or broadcast. Mulching is not required.

4. Seeding, Sprigging, and Mulching quantity is 3 acres.

5. In section 6, MEASUREMENT AND PAYMENT, Method 1 will apply. Such payment will constitute full compensation for related Subsidiary Item, Earthfill, Stripped Material, Construction Specification 23.

NRCS-NEH-642 7-1 January 2009

Construction Specification 7—Construction Surveys

1. Scope The work consists of performing all surveys, measurements, and computations required by this specification.

2. Equipment and material Equipment for construction surveys shall be of a quality and condition to provide the required accuracy. The equipment shall be maintained in good working order and in proper adjustment at all times. Records of repairs, calibration tests, accuracy checks, and adjustments shall be maintained and be available for inspection by the engineer. Equipment shall be checked, tested, and adjusted as necessary in conformance with manufacturer's recommendations.

Material is field notebooks, stakes, templates, platforms, equipment, spikes, steel pins, tools, and all other items necessary to perform the work specified.

3. Quality of work All work shall follow recognized professional practice and the standards of the industry unless otherwise specified in section 9 of this specification. The work shall be performed to the accuracy and detail appropriate for the type of job.

notes, sketches, and other data shall be complete, recorded neatly, legible, reproducible and organized to facilitate ease in review and allow reproduction of copies for job documentation. Survey equipment that requires little or no manual recording of field data shall have survey information documented as outlined in section 9 of this specification.

All computations shall be mathematically correct and shall include information to identify the bid item, date, and who performed, checked, and approved the computations. Computations shall be legible, complete, and clearly document the source of all information used including assumptions and measurements collected.

If a computer program is used to perform the computations, the contractor shall provide the engineer with the software identification, vendor's name, version number, and other pertinent data before beginning survey activities. Computer generated computations shall show all input data including values assigned and assumptions made.

The elevations of permanent and temporary bench marks shall be determined and recorded to the nearest 0.01 foot.

Differential leveling and transit traverses shall be of such precision that the error of vertical closure in feet shall not exceed plus or minus 0.1 times the square root of the traverse distance in miles. Linear measurements shall be accurate to within 1 foot in 5,000 feet, unless otherwise specified in section 9 of this specification. The angular error of closure for transit traverses shall not exceed 1 minute times the square root of the number of angles turned.

The minimum requirements for placing slope stakes shall be at 100-foot stations for tangents, as little as 25 feet for sharp curves, breaks in the original ground surface and at any other intermediate stations necessary to ensure accurate location for construction layout and measurement. Slope stakes and cross sections shall be perpendicular to the centerline.

Significant breaks in grade shall be determined for cross sections. Distances shall be measured horizontally and recorded to the nearest 0.1 foot. Side shots for interim construction stakes may be taken with a hand level.

Unless otherwise specified in section 9 of this specification, measurements for stationing and establishing the location of structures shall be made to the nearest 0.1 foot.

Elevations for concrete work, pipes, and mechanical equipment shall be determined and recorded to the nearest 0.01 foot.

Elevations for earth work shall be determined and recorded to the nearest 0.1 foot.

4. Primary control The baselines and bench marks for primary control, necessary to establish lines and grades needed for construction, are shown on the drawings and have been located on the job site.

These baselines and bench marks shall be used as the origin of all surveys, layouts, and measurements to establish construction lines and grades. The contractor shall take all necessary precautions to prevent the loss or damage of primary control points. Any stakes or control points lost or damaged by construction activity will be reestablished by the contractor or at contractor expense.

NRCS-NEH-642 7-2 January 2009

5. Construction surveys Before work starts that requires contractor performed surveys, the contractor shall submit in writing for the engineer's review: the name, qualifications, and experience of the individuals to be assigned to the survey tasks.

Method 1—Contractor performed surveys shall include:

• checking and any supplemental or interim staking

• performing quantity surveys, measurements, and computations for progress payment

• other surveys as described in section 9 of this specification

Method 2—Contractor performed surveys shall consist of all work necessary for:

• establishing line and grade for all work

• setting slope stakes for all work

• checking and any supplemental or interim staking

• establishing final grade stakes

• performing quantity surveys, measurements, and computations for progress payment

• other surveys as described in section 9 of this specification

Method 3—Contractor performed surveys shall consist of all work necessary for:

• establishing line and grade for all work

• setting slope stakes for all work

• checking and any supplemental or interim staking

• establishing final grade stakes

• performing quantity surveys, measurements, and computations for progress payments

• performing original (initial) and final surveys for determinations of final quantities

• other surveys as described in section 9 of this specification

6. Staking The construction staking required for the item shall be completed before work on any item starts. Construction staking shall be completed as follows or as otherwise specified in section 9 of this specification:

Clearing and grubbing—The boundary of the area(s) to be cleared and grubbed shall be staked or flagged at a maximum interval of 200 feet, closer if needed, to clearly mark the limits of work. When contractor staking is the basis for determining the area for final payment, all boundary stakes will be reviewed by the engineer before start of this work item.

Excavation and fill—Slope stakes shall be placed at the intersection of the specified slopes and ground line. Slope stakes and the reference stakes for slopes shall be marked with the stationing, required cut or fill, slope ratio, and horizontal distance from the centerline or other control line. The minimum requirements for placing slope stakes is outlined in section 3, Quality of work.

Structures—Centerline and offset reference line stakes for location, alignment, and elevation shall be placed for all structures.

7. Records All survey data shall be recorded in fully identified standard hard-bound engineering survey field notebooks with consecutively numbered pages. All field notes and printed data shall include the purpose or description of the work, the date the work was performed, weather data, sketches, and the personnel who performed and checked the work.

Electronically generated survey data and computations shall be bound, page numbered, and cross referenced in a bound field notebook containing the index for all survey activities. All work shall follow recognized professional practice.

The construction survey records shall be available at all times during the progress of the work for examination and use by the engineer and when requested, copies shall be made available. The original field notebooks and other records shall be provided to and become the property of the owner before final payment and acceptance of all work.

NRCS-NEH-642 7-3 January 2009

Complete documentation of computations and supporting data for progress payments shall be submitted to the engineer with each invoice for payment as specified in section 9 of the specification. When the contractor is required to conduct initial and final surveys as outlined in section 5, Construction Surveys, notes shall be provided as soon as possible after completion to the engineer for the purpose of determining final payment quantities.

8. Payment Method 1—For items of work for which lump sum prices are established in the contract, payment is made as the work proceeds, after presentation of correct and accurate invoices by the contractor showing related costs and evidence of the charges of suppliers, subcontractors, and others for supplies furnished and work performed. Invoices for the total amount of the contract price will not be accepted until all surveys are complete and required documentation has been determined complete. If the total of such payments is less than the lump sum contract price for this item, the unpaid balance will be included in the final contract payment. Payment of the lump sum contract price will constitute full compensation for completion of all work under the bid item.

Method 2—For items of work for which lump sum prices are established in the contract, payment is made as the work proceeds with progress payment amounts determined as a percentage of the total work planned as projected from the contractor's approved construction schedule. Payment of the lump sum contract price will constitute full compensation for completion of all work under this bid item.

All Methods—Payment will not be provided under this item for the purchase price of materials or equipment having a residual value.

Compensation for any item of work described in the contract, but not listed in the bid schedule will be included in the payment for the item of work to which it is made subsidiary. Such items and the item to which they are made subsidiary are identified in section 9 of this specification.

Cedar Creek Diversion Channel Lining 7-4 June 2018

9. ITEMS OF WORK AND CONSTRUCTION DETAILS

Items of work to be performed in accordance with this specification and construction details are:

a. Bid Item 1, Construction Surveys

1. This item shall consist of all contractor performed surveying.

2. In section 5, CONSTRUCTION SURVEYS, Method 1 shall apply. The NRCS shall perform initial staking once prior to construction in accordance with this specification and shall provide a list of the coordinates establishing such staking to the contractor. At contractor’s request, the NRCS will provide TIN surfaces depicting finished liner grade and finished cover soil grade in Autodesk Civil3D 2016 format. These surfaces will be provided as a courtesy and shall not override the NRCS staking, staking coordinates, construction drawings, or specifications as representation of required work within the contract or establishment of quantities. The NRCS shall perform quantity surveys, measurements, and computations for final payment.

3. The contractor shall request initial stakeout by NRCS a minimum of 10 business days prior to construction.

4. In section 8, MEASUREMENT AND PAYMENT, Method 2 shall apply.

b. Bid Item 8, Additive Construction Surveys

1. This item shall consist of all contractor performed surveying within the additive lined reach, Stations 33+60 to 37+60.

2. Construction details of Bid Item 1 shall also apply to Bid Item 8.

NRCS-NEH-642 8-1 May 2001

Construction Specification 8—Mobilization and Demobilization

1. Scope The work consists of the mobilization and demobilization of the contractor's forces and equipment necessary for performing the work required under the contract. It does not include mobilization and demobilization for specific items of work for which payment is provided elsewhere in the contract. Mobilization will not be considered as work in fulfilling the contract requirements for commencement of work.

2. Equipment and material Mobilization shall include all activities and associated costs for transportation of contractor's personnel, equipment, and operating supplies to the site; establishment of offices, buildings, and other necessary general facilities for the contractor's operations at the site; premiums paid for performance and payment bonds including coinsurance and reinsurance agreements as applicable; and other items specified in section 4 of this specification.

Demobilization shall include all activities and costs for transportation of personnel, equipment, and supplies not required or included in the contract from the site; including the disassembly, removal, and site cleanup of offices, buildings, and other facilities assembled on the site specifically for this contract.

This work includes mobilization and demobilization required by the contract at the time of award. If additional mobilization and demobilization activities and costs are required during the performance of the contract as a result of changed, deleted, or added items of work for which the contractor is entitled to an adjustment in contract price, compensation for such costs will be included in the price adjustment for the item or items of work changed or added.

3. Payment Payment will be made as the work proceeds, after presentation of paid invoices or documentation of direct costs by the contractor showing specific mobilization and demobilization costs and supporting evidence of the charges of suppliers, subcontractors, and others. When the total of such payments is less than the lump sum contract price, the balance remaining will be included in the final contract payment. Payment of the lump sum contract price for mobilization and demobilization will constitute full compensation for completion of the work.

Payment will not be made under this item for the purchase costs of materials having a residual value, the purchase costs of materials to be incorporated in the project, or the purchase costs of operating supplies.

Cedar Creek Diversion Channel Lining 8-2 June 2018

4. ITEMS OF WORK AND CONSTRUCTION DETAILS

Items of work to be performed in conformance with this specification and construction details are:

a. Bid Item 2, Mobilization and Demobilization

1. This item shall consist of the mobilization and demobilization of the contractor’s forces and equipment to perform the work required in the contract.

2. The contractor shall thoroughly clean all equipment prior to the mobilization to the project to ensure that the equipment is free of weed seeds.

3. After construction is complete, the contractor shall restore all access roads to a condition equal to that which existed prior to construction.

4. In section 3, PAYMENT, payment is inclusive of mobilization between work sites along the channel.

Payment for this bid item is by lump sum. Fifty (50) percent of the lump sum may be paid upon observable evidence, such as delivery of heavy equipment to the site, that mobilization has commenced, with the remaining balance paid as part of final project payment. Submittal of invoices related to this bid item is not required.

NRCS-NEH-642 11-1 May 2001

Construction Specification 11—Removal of Water

1. Scope The work consists of the removal of surface water and ground water as necessary to perform the construction required by the contract in accordance with the specifications. It shall include: (1) constructing, installing, building, and maintaining all necessary temporary water containment facilities, channels, and diversions; (2) furnishing, installing, and operating all necessary pumps, piping, and other facilities and equipment; and (3) removing all such temporary works and equipment after their intended function is no longer required.

2. Diverting surface water The contractor shall install, maintain, and operate all cofferdams, channels, flumes, sumps, and all other temporary diversion and protective works needed to divert streamflow and other surface water through or around the construction site. Control of surface water shall be continuous during the period that damage to construction work could occur. Unless otherwise specified and/or approved, the diversion outlet shall be into the same drainageway that the water would have reached before being diverted.

The contractor shall furnish the contracting officer, in writing, a proposed plan for diverting surface water before beginning any construction activities for which a diversion is required, unless waived in section 8 of this specification.

Acceptance of this plan or the waiving of the plan requirement will not relieve the contractor of the responsibilities related to this activity during the process of completing the work as specified.

3. Dewatering the construction site Foundations, cutoff trenches, and all other parts of the construction site shall be dewatered and kept free of standing water and muddy conditions as necessary for the proper execution of the work. The contractor shall furnish, install, operate, and maintain all drains, sumps, pumps, casings, well points, and all other equipment required to properly dewater the site as specified. Dewatering systems that cause a loss of soil fines from the foundation areas will not be permitted.

The contractor shall furnish the contracting officer, in writing, a proposed plan for dewatering before commencing with any construction activity for which dewatering may be required, unless waived in section 8 of this specification.

Acceptance of this plan or the waiving of the plan requirement will not relieve the contractor of the responsibilities for completing the specified work.

4. Dewatering borrow areas The contractor shall maintain all borrow areas free of surface water or otherwise provide for timely and effective removal of surface and subsurface water that accumulates within the borrow area, unless waived in section 8 of this specification.

Borrow material shall be processed as necessary to achieve proper and uniform moisture content at the time of placement.

If pumping to dewater borrow areas is included as a bid item of work in the bid schedule, each pump discharge pipe shall be equipped with a water meter. The meter shall be such that the measured quantity of water is accurate within 3 percent of the true quantity. The contractor shall provide necessary support to perform accuracy tests of the water meter when requested by the contracting officer.

5. Erosion and pollution control Removal of water from the construction site, including the borrow areas, shall be accomplished so that erosion and the transporting of sediment and other pollutants are minimized. Dewatering activities shall be accomplished in a manner that the water table water quality is not altered. Pollution control activities shall not conflict with the requirements of Construction Specification 5, Pollution Control, if it is a part of this contract.

6. Removal of temporary works When temporary works are no longer needed, the contractor shall remove and return the area to a condition similar to that which existed before construction. Areas where temporary works were located shall be graded for sightly appearance with no obstruction to natural surface waterflows or the proper functioning and access to the works of improvement installed. The contractor shall exercise extreme care during the removal stages to minimize the loss of soil sediment and debris that was trapped during construction.

NRCS-NEH-642 11-2 May 2001

Pipes, casings, and any other material used to dewater the site shall be removed from temporary wells. The wells shall be filled to ground level with clean gravel or other suitable material approved by the contracting officer. The contractor shall exercise extreme care to prevent pollution of the ground water by these actions.

7. Measurement and payment Method 1—Items of work listed in the bid schedule for removal of water, diverting surface water, and dewatering construction sites and borrow areas are paid for at the contract lump sum prices. Such payment will constitute full compensation for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work.

Method 2—Items of work listed in the bid schedule for removal of water, diverting surface water, dewatering construction sites, and dewatering borrow areas are paid for at the contract lump sum prices. Such payment will constitute full compensation for furnishing, installing, operating, and maintaining the necessary trenches, drains, sumps, pumps, and piping and for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work. The exception is that additional payment for pumping to dewater borrow areas and the removal of water will be made as described in the following paragraph.

If pumping to dewater borrow areas is a contract bid item, payment is made at the contract unit price, which shall be the price per 1,000 gallons shown in the bid schedule. Such payment will constitute full compensation for pumping only.

Compensation for equipment and preparation and for other costs associated with pumping is included in the lump sum payment for removal of water or the lump sum payment for dewatering the borrow areas. Payment is made only for pumping that is necessary to dewater borrow areas that cannot be effectively drained by gravity or that must have the water table lowered to be usable as a suitable borrow source. Pumping for other purposes will not be included for payment under this item.

All Methods—The following provisions apply to all methods of measurement and payment. Compensation for any item of work described in the contract, but not listed in the bid schedule is included in the payment for the contract line item to which it is made subsidiary. Such items and the items to which they are made subsidiary are identified in section 8 of this

Cedar Creek Diversion Channel Lining 11-3 June 2018

8. ITEMS OF WORK AND CONSTRUCTION DETAILS

Items of work to be performed in conformance with this specification and construction details are:

a. Subsidiary Item, Removal of Water

1. This item shall consist of the removal of surface and subsurface water as required for construction of the permanent works under stable and dry conditions.

2. In section 2, DIVERTING SURFACE WATER, work within this contract shall not commence if the dam outlet works are discharging water to the channel or if such flow is anticipated to occur within the duration of construction. A surface water diversion plan shall not be required, but measures taken to divert any surface water, such as stormwater, are subject to review and approval by the engineer.

3. In section 3, DEWATERING THE CONSTRUCTION SITE, a plan for dewatering the construction site shall not be required. Measures taken to dewater the construction site are subject to review and approval by the engineer.

4. Dewatering facilities, if required, shall remove and maintain water a minimum of (1) foot below the lower construction limits in a manner that assures the soil matrix is dry and stable. The foundation condition shall be approved by the Engineer prior to any placement of liner or earthfill. All earthwork for dewatering shall be in conformance with OSHA Safety Standards.

5. In section 5, EROSION AND POLLUTION CONTROL, pollution control for diverting and dewatering measures and works, established during their construction, operation, and removal, shall not conflict with the requirements of Construction Specification 5, Pollution Control and the approved SWPPP.

6. In section 7, MEASUREMENT AND PAYMENT, no separate payment will be made for removal of water.

Compensation for removal of water will be included in the payment for Bid Item 5, Excavation, Construction Specification 21. Within the additive lined reach, Stations 33+60 to 37+60, compensation for removal of water will be included in the payment for Bid Item 10, Additive Excavation, Construction Specification 21.

NRCS-NEH-642 21-1 May 2001

Construction Specification 21—Excavation

1. Scope The work shall consist of the excavation required by the drawings and specifications and disposal of the excavated materials.

2. Classification Excavation is classified as common excavation, rock excavation, or unclassified excavation in accordance with the following definitions.

Common excavation is defined as the excavation of all materials that can be excavated, transported, and unloaded using heavy ripping equipment and wheel tractor-scrapers with pusher tractors or that can be excavated and dumped into place or loaded onto hauling equipment by excavators having a rated capacity of one cubic yard or larger and equipped with attachments (shovel, bucket, backhoe, dragline, or clam shell) appropriate to the material type, character, and nature of the materials.

Rock excavation is defined as the excavation of all hard, compacted, or cemented materials that require blasting or the use of ripping and excavating equipment larger than defined for common excavation. The excavation and removal of isolated boulders or rock fragments larger than 1 cubic yard encountered in materials otherwise conforming to the definition of common excavation shall be classified as rock excavation. The presence of isolated boulders or rock fragments larger than 1 cubic yard is not in itself sufficient cause to change the classification of the surrounding material.

For the purpose of these classifications, the following definitions shall apply:

Heavy ripping equipment is a rear-mounted, heavy duty, single-tooth, ripping attachment mounted on a track type tractor having a power rating of at least 250 flywheel horsepower unless otherwise specified in section 10.

Wheel tractor-scraper is a self-loading (not elevating) and unloading scraper having a struck bowl capacity of at least 12 cubic yards.

Pusher tractor is a track type tractor having a power rating of at least 250 flywheel horsepower equipped with appropriate attachments.

Unclassified excavation is defined as the excavation of all materials encountered, including rock materials, regardless of their nature or the manner in which they are removed.

3. Blasting The transportation, handling, storage, and use of dynamite and other explosives shall be directed and supervised by a person(s) of proven experience and ability who is authorized and qualified to conduct blasting operations.

Blasting shall be done in a manner as to prevent damage to the work or unnecessary fracturing of the underlying rock materials and shall conform to any special requirements in section 10 of this specification. When specified in section 10, the contractor shall furnish the engineer, in writing, a blasting plan before blasting operations begin.

4. Use of excavated material Method 1—To the extent they are needed, all suitable material from the specified excavations shall be used in the construction of required permanent earthfill or rockfill. The suitability of material for specific purposes is determined by the engineer. The contractor shall not waste or otherwise dispose of suitable excavated material.

Method 2—Suitable material from the specified excavations may be used in the construction of required earthfill or rockfill. The suitability of material for specific purposes is determined by the engineer.

5. Disposal of waste materials Method 1—All surplus or unsuitable excavated materials are designated as waste and shall be disposed of at the locations shown on the drawings.

NRCS-NEH-642 21-2 May 2001

Method 2—All surplus or unsuitable excavated materials are designated as waste and shall be disposed of by the contractor at sites of his own choosing away from the site of the work. The disposal shall be in an environmentally acceptable manner that does not violate local rules and regulations.

6. Excavation limits Excavations shall…