ABSTRACT OF OFFERS - CONSTRUCTION
2. Date Issued: 5/3/2018 3. Date Open:
6/4/2018
Page No.
4. Issuing Office Name and Title of Certifying Official Typed/Signature/Date
USDA-NRCS 100
USDA, Suite 206, Stillwater, OK 74074
Sharla K. Goforth, Contract Specialist
5. Project Title Offers
Mary's Creek 9 Rehab, TN
6. Number of Amendments Issued: B. Bid Security: Yes B. Bid Security:Yes B. Bid Security: Yes
Amendments
Acknow-ledged
Yes Amendment s Acknow-ledged Yes
Amendments Acknow-ledged
NA
7A.
Item No.
7B. Description of Offered Item 7C Est Quanti ty E. Unit Price
F. Est.
Amount
E. Unit Price
F. Est. Amount E. Unit Price F. Est. Amount
1 Clearing and Grubbing 3.6 $5,000.00 $18,000.00 $8,000.00 $28,800.00 $10,000.00 $36,000.00
Structure Removal - Existing Slide Gate Assembly & Concrete - By Others
XXX
3 Structure Removal - Existing Dock 1 $1,000.00 $1,000.00 $25,000.00 $25,000.00
4 Pollution Control - Silt Fence 2000 $3.25 $6,500.00 $5.00 $10,000.00 $5.00 $10,000.00
5 Pollution Control - Erosion Control Rock 150 $37.50 $5,625.00 $100.00 $15,000.00 $100.00 $15,000.00
6 Temporary Seeding 3.5 $1,000.00 $3,500.00 $3,500.00 $12,250.00 $3,000.00 $10,500.00
7 Mulching 15.2 $1,000.00 $15,200.00 $1,500.00 $22,800.00 $5,000.00 $76,000.00
8 Permanent Seeding 10.4 $1,000.00 $10,400.00 $6,500.00 $67,600.00 $5,000.00 $52,000.00
9 Sodding 15645 $5.00 $78,225.00 $8.00 $125,160.00 $6.00 $93,870.00
10 Construction Surveys 1 $20,000.00 $20,000.00 $10,000.00 $10,000.00 $30,000.00 $30,000.00
11 Mobilzation & Demobilization 1 $25,000.00 $25,000.00 $67,000.00 $67,000.00 $50,000.00 $50,000.00
12 Water for Construction 1000 $10.00 $10,000.00 $10.00 $10,000.00 $100.00 $100,000.00
13 Removal of Water 1 $1,000.00 $1,000.00 $35,000.00 $35,000.00 $20,000.00 $20,000.00
14 Excavation, Common 7452 $5.00 $37,260.00 $8.00 $59,616.00 $25.00 $186,300.00
15 Excavation, Common, All Drains 5895 $10.00 $58,950.00 $12.00 $70,740.00 $25.00 $147,375.00
Excavation, Common, Riser Base Installation & Impact Basin
790 $10.00 $7,900.00 $10.00 $7,900.00 $50.00 $39,500.00
Earthfill, Class A, Embankment, Spillway and Impact Basin
9829 $5.00 $49,145.00 $8.00 $78,632.00 $35.00 $344,015.00
18 Drainfill, Coarse 477 $37.50 $17,887.50 $60.00 $28,620.00 $75.00 $35,775.00
19 Drainfill, Fine 4322 $37.50 $162,075.00 $75.00 $324,150.00 $75.00 $324,150.00
20 Salvaging and Spreading Topsoil 51343 $1.00 $51,343.00 $1.00 $51,343.00 $3.00 $154,029.00
Concrete, Class 4000 - Riser Base & Pipe Bedding
13.2 $650.00 $8,580.00 $2,500.00 $33,000.00 $750.00 $9,900.00
22 Concrete, Class 4000 - Impact Basin 35.7 $650.00 $23,205.00 $2,500.00 $89,250.00 $1,500.00 $53,550.00
23 Steel Reinforcement - Riser Base 2473 $1.25 $3,091.25 $1.00 $2,473.00 $3.00 $7,419.00
24 Steel Reinforcement - Impact Basin 4713 $1.25 $5,891.25 $1.00 $4,713.00 $3.00 $14,139.00
25 Concrete Pressure Pipe 25 $100.00 $2,500.00 $2,500.00 $62,500.00 $500.00 $12,500.00
26 Tile Drains, Perforated Pipe 200 $12.00 $2,400.00 $12.00 $2,400.00 $50.00 $10,000.00
27 Tile Drains, Non-perforated pipe 259 $12.00 $3,108.00 $8.00 $2,072.00 $50.00 $12,950.00
28 Corrugated Aluminum Pipe Drop 1 $1,500.00 $1,500.00 $25,000.00 $25,000.00 $10,000.00 $10,000.00
29 Rock Riprap, Impact Basin 210 $37.50 $7,875.00 $85.00 $17,850.00 $100.00 $21,000.00
30 Rock Riprap, Wave Protection XXX
31 Slide Gate Assembly XXX
32 Metalwork - Riser Inlets 1 $3,500.00 $3,500.00 $25,000.00 $25,000.00 $15,000.00 $15,000.00
33 Metalwork - Impact Basin Cover 1 $3,500.00 $3,500.00 $22,500.00 $22,500.00 $10,000.00 $10,000.00
34 Chain Link Fence 34.4 $25.00 $860.00 $70.00 $2,408.00 $100.00 $3,440.00
35 Quality Control 1 $3,500.00 $3,500.00 $70,000.00 $70,000.00 $70,000.00 $70,000.00
Mineral Aggregate Fill, Riser Base (#57 Stone)
10 $47.50 $475.00 $100.00 $1,000.00 $100.00 $1,000.00
37 Construction Access Roads 1 $5,000.00 $5,000.00 $35,000.00 $35,000.00 $20,000.00 $20,000.00
Grand Total $653,996.00 $1,444,777.00 $1,995,412.00
3721 N. Carnation Street
1. Solicitation Number:
12SPEC18B0011
I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.
Tinin Contracting Co., Inc.
1149 Ross Creek Rd.
Franklin Park, IL 60131Fort Necessity, LA 71243
824 Chester Rd Clifton, TN 38425
ECW Recoveries LLC Kovilic Construction