This document is a justification addendum for a sole source contract modification. The United States Department of Agriculture Rural Development is modifying an existing contract with an unnamed vendor to extend financial and restructuring advisory services for loans made by the Federal Financing Bank and guaranteed by the Rural Utilities Service to Brazos Electric Power Cooperative. The bankruptcy case involving Brazos Electric has not progressed as quickly as anticipated, requiring an additional year of services through April 2023. The contract modification increases the period of performance and award amount by $1,700,000, bringing the total value to $4,999,775. The contractor provides expertise evaluating loan collateral assets and analyzing Brazos Electric's financials to maximize recovery for the Rural Utilities Service loan of approximately $1.8 billion.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM
United States Department of Agriculture Justification for Other than Full and Open Competition
Federal Acquisition Regulation (FAR) Part 6.3
1. Identification of the agency and the contracting activity.
Agency: United States Department of Agriculture (USDA), Rural Development, Rural Utilities Service, Electrical Program
Contracting Activity: United States Department of Agriculture, Rural Development, Procurement Management Office, Regional Acquisition Division.
2. The nature and/or description of the action being approved.
USDA/RD awarded a sole source contract (12RADA21C0001) on April 7, 2021, in accordance with 41 U.S.C. 3304(a)(2), as implemented by FAR 6.302-2, titled “Unusual and compelling urgency.”
USDA/RD has a critical and immediate need to extend this contract to secure loans made by the Federal Financing Bank (FFB) and guaranteed by the Rural Utilities Service (RUS) (hereinafter RUS/FFB loans) to Brazos Electric Power Cooperative, Inc.
The litigation of this bankruptcy case has not progressed as anticipated, and it is the opinion of the USDA’s legal counsel that an additional six months to a year of services will be required for resolution in the case. This justification amends the previous justification, and a modification will be issued to increase the period of performance of the non-severable services for an additional year through April 6, 2023 and increase the award amount by $1,700,000.00.
3. A description of the supplies or services required to meet the agency’s needs (including the estimated value).
The purpose of this requirement is to assist in securing the RUS/FFB loan with Brazos Electric Power Cooperative, Inc. The contractor is providing financial/restructuring advisory and appraisal/evaluation services to assist in retaining the security of the RUS/FFB loan and retaining receipts upon the loan. Services include evaluation of all the assets securing the RUS/FFB loans and an in-depth analysis of the financials of Brazos Electric Power Cooperative, Inc. to ensure maximal recovery for RUS. The current contract value is $3,299,775.00 and the modification to increase the value of the contract by $1,700,000.00 will result in a total contract value of $4,999,775.00.
4. The statutory authority permitting other than full and open competition.
41 U.S.C. 3304(a)(1), as implemented by FAR 6.302-1, titled "Only one responsible source and no other supplies or services will satisfy agency requirements."
5. A statement demonstrating the unique qualifications of the proposed contractor or the nature of the action requiring the use of the authority.
As part of their duties over the course of the first year of the contract, A&M provided technical expertise, analysis, and recommendations relating to: the valuation of the assets securing RUS loans, analysis of the company’s cash flow, analysis of Debtor-In-Possession (DIP) financing proposals, analysis of ERCOT, analysis of company’s financial derivatives and hedging obligations, and formal expert report as to valuation and testimony. Their expertise and experience were extremely beneficial to both the RUS as well as its legal representation, including attorneys from the Department of Justice and the USDA Office of General Counsel. In addition, analysis and recommendations provided by A&M have been critical to RUS and legal counsel during the course of the ongoing legal proceedings.
The bankruptcy is now entering a critical phase as litigation is moving toward a close and Brazos is preparing to submit its plan to exit bankruptcy. In addition, on March 3, 2022, the trial was suspended so that the parties could explore mediation. RUS will require analysis of the financial impact and risk it faces as the parties work through the mediation and the potential for additional litigation still exists. In addition, RUS will require technical and financial analysis of the proposed exit plan to ensure any risk to the Government is reduced or mitigated.
Given the unique qualifications A&M has, its knowledge of Brazos & ERCOT, and the numerous additional parties involved, its extensive knowledge of this complex bankruptcy case, and, most importantly, the potential $1.8 billion financial risk RUS faces, it is imperative that A&M’s contract be extended an additional year. The bankruptcy is at a critical juncture and A&M has gained extensive and unique knowledge of the parties and issues involved. A reopening of the contract to competition would lead to delays at this critical juncture and negatively impact the Government’s ability to fully and quickly respond to this dynamic and complex case and would place RUS at greater risk of financial loss.
6. A description of efforts made to ensure offers are solicited from as many potential sources as is practicable.
None. As described in the above paragraph, there is only one source available to satisfy the agency’s needs. Changing the financial/restructuring advisory and appraisal evaluation service vendor at this time would lead to delays at this critical juncture and negatively impact the Government’s ability to fully and quickly respond to this dynamic and complex case and would place RUS at greater risk of financial loss.
7. A determination by the Contracting Officer that the anticipated cost to the Government will be fair and reasonable.
The rates provided by A&M have been compared to the rates of the other financial/restructuring advisory and appraisal services vendors working on behalf of Brazos and ERCOT in the case which have been filed with the court. The rates submitted by A&M are consistant with the rates of the other two firms.
8. A description of the market research conducted and the results or a statement of the reason Market Research was not conducted.
No change from original justification.
9. Any other facts supporting the use of other than full and open competition.
No change from original justification.
10. A listing of the sources, if any, that expressed a written interest in the acquisition.
None
11. A statement of actions, if any, the agency may take to remove or overcome any barriers to competition if subsequent acquisitions are anticipated.
Due to the unique nature of this procurement and A&M’s extensive knowledge of the current case obtaining competition for continued support of this critical need is not feasible. If the Government determines this service will be required for other litigations the USDA/RD will research establishing Blanket Purchase Agreements (BPA) and/or Indefinite Delivery Indefinite Quantity (IDIQ) contract awarded based on competition.
Certifications & Approvals
Supporting data that form the basis for and included in this justification are certified accurate and complete.
James Elliot Director of Operations Rural Utilities Service – Electric Program
The information contained in this Justification for Other Than Full and Open Competition is certified accurate and complete to the best of my knowledge and belief.
Jerrod Schleis Contracting Officer
Advocate for competition for the procuring activity. The approval level has not changed from original J&A. In accordance with PGI 406.304 subsequent approval is not required.
| 2022-04-01T13:11:20-0400 | |
| JAMES ELLIOTT |
| 2022-04-01T12:36:55-0500 | |
| Jerrod J. Schleis |
File details come from the government source that posted it. Updated .