Responses to questions to solicitation 12RADA19Q0003
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 12RADA19Q0003_Attachments_with_Corrected_H_and_J.pdf | ||
| SF_30_Amendment_Modification.pdf | ||
| 12RADA19Q0003_Attachments.pdf | ||
| 12RADA19Q0003.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Responses to Questions Regarding Solicitation 12RADA19Q0003 February 13, 2019
| Q1. | Is the property management responsible for removing snow from the cul-de-sac? |
| A1. | The city is responsible. |
| Q2. | Do you have a current occupancy and turnover rate? |
| A2. | This information is not provided. |
| Q3. | Does this building have a permanent site manager? |
| A3. | There is no current permanent site manager. Although it is encouraged, it is not a requirement. |
| Q4. | Do you know how long the incumbent’s employees have been working on this contract? |
| A4. | 45 days |
| Q5. | Does the contracting company have to have “at least two years of experience and satisfactory performance in directing and overseeing the management of similar federally assisted multi-family housing” or just the project manager? |
| A5. | CFR 3560.102(e)(2) requires the Agency to deny approval of any proposed management agent that cannot provide evidence of at least two years of experience and satisfactory performance in directing and overseeing the management of similar federally-assisted MFH. |
and overseeing the management of similar federally-assisted MFH.”