This document is a Statement of Work (SOW) for a federal contract opportunity issued by the U.S. Department of Agriculture (USDA) Natural Resources Conservation Service (NRCS) to hand plant bare root tree seedlings on Wetland Reserve Easement (WRE) sites in Kentucky. The SOW details the requirements for site preparation, purchasing and planting approximately 530,000 tree seedlings on 1213.8 acres across 11 sites in 8 Kentucky counties. The work is set aside for small businesses under NAICS code 115112, Soil Preparation, Planting, and Cultivating, with a size standard of $9.5M. The period of performance is September 31, 2024 to May 31, 2025. A firm-fixed-price purchase order will be awarded to the responsible offeror who submits the lowest-price technically acceptable quote. A site visit is scheduled for August 22, 2024 at the USDA Service Center in Campbellsville, KY.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USDA NRCS SOW
For
2024-2025 WRE Tree Planting KY
Background
NRCS in KY has a requirement for a wetland restoration consisting of hand planting bare root tree seedlings on WRE sites located in the following counties of Kentucky:
Fulton, Green, Hart, Hopkins, Lincoln, McLean, Taylor, and Whitley. The successful contractor will be required to perform site preparation work, purchase the bare root seedlings, and hand plant the tree seedlings according to NRCS contract specifications.
The contract calls for the purchase of 530,000 tree seedlings that will be hand planted on approximately 1213.8 acres. Types of site preparation will include the following:
PRE-PLANTING SITE PREPARATION
1) 843.2 acres of no pre-planting site preparation needed due to planting into agricultural crop stubble
2) 359.2 acres of mowing to a height of 8 inches within 14 days of contract award followed with a chemical application with 1.5 quarts of Roundup (41% Glyphosate base product or an equivalent labeled product) per acre no earlier than 2 weeks after mowing but before October 1, 2024. Two weeks after spraying but before November 1, 2024, plant with a no-till drill 90 lbs./acre of wheat to serve as a nurse crop prior to tree planting.
3) 11.4 acres of mowing to a height of 8 inches within 14 days of contract award followed with a chemical application with 1.5 quarts/acre of Roundup (41% Glyphosate base product or an equivalent labeled product) tank mixed with 16.0 oz/acre of Imazapyr (27.6 % base product or an equivalent labeled product) and proper oil surfactant no earlier than 2 weeks after mowing but before October 1, 2024.
POST-PLANTING SITE PREPARATION
1) 854.6 acres consisting of a chemical application of 1 ounce per acre of Oust XP (Sulfometuron methyl:{Methyl 2-[[[[(4,6-dimethyl-2pyrimidinyl)amino]-carbonyl]amino]sulfonyl]benzoate}. . . 75.0% or equivalent labeled product) at the time of planting, if the seedlings are planted after March 1, 2025. If seedlings are planted before March 1, 2025, the 1.0 ounce/acre Oust XP application should be completed after March 1, 2025, but before tree seedling buds break dormancy. The Oust XP application will not occur during or within 12 hours of a rain event.
Site Visit Information: Please see Solicitation 12FPC424Q0146
The Project is broken down by individual item below.
Item No. Supplies/Services Spec. No. Quantity Unit Unit Price Total Amount
A. Aldrich, James WRE Site – Taylor County, Kentucky 30.2 Acres
01 Pre- Planting site preparation Post- Planting preparation 8 1 Job $___________ $ ________ Planting Trees and Shrubs 402 Woody Plants and Other Materials 300
B. Brown/Bagley WRE Site – Hopkins County, Kentucky 126.6 Acres
02 Pre- Planting site preparation Post- Planting preparation 8 1 Job $___________ $ _________ Planting Trees and Shrubs 402 Woody Plants and Other Materials 300
C. Cox, Lawrence WRE Site – Hart County, Kentucky 11.4 Acres
03 Pre- Planting site preparation Post- Planting preparation 8 1 Job $___________ $ ________ Planting Trees and Shrubs 402 Woody Plants and Other Materials 300
D. Davis, Jeff/Troy WRE Site – Green County, Kentucky 13.9 Acres
04 Pre- Planting site preparation Post- Planting preparation 8 1 Job $___________ $ _________ Planting Trees and Shrubs 402 Woody Plants and Other Materials 300
E. Dillard, Roy Site – Fulton County, Kentucky 31.1 Acres
05 Pre- Planting site preparation Post- Planting preparation 8 1 Job $___________ $ _______ Planting Trees and Shrubs 402 Woody Plants and Other Materials 300
F. Faris, Sammy Joe WRE Site – Whitley County, Kentucky 38.7 Acres
06 Pre- Planting site preparation Post- Planting preparation 8 1 Job $___________ $ ________ Planting Trees and Shrubs 402 Woody Plants and Other Materials 300
G. Forward, John WRE Site – Taylor County, Kentucky 49.0 Acres
07 Pre- Planting site preparation Post- Planting preparation 8 1 Job $___________ $ _________ Planting Trees and Shrubs 402 Woody Plants and Other Materials 300
H. Keith/Williams WRE Site – Fulton County, Kentucky 133.8 Acres
08 Pre- Planting site preparation Post- Planting preparation 8 1 Job $___________ $ _________ Planting Trees and Shrubs 402 Woody Plants and Other Materials 300
I. Sallee, Thomas WRE Site – Lincoln County, Kentucky 94.9 Acres
09 Pre- Planting site preparation Post- Planting preparation 8 1 Job $___________ $ __________ Planting Trees and Shrubs 402 Woody Plants and Other Materials 300
J. SKP Holdings WRE Site –McLean County, Kentucky 103.5 Acres
10 Pre- Planting site preparation Post- Planting preparation 8 1 Job $___________ $ __________ Planting Trees and Shrubs 402 Woody Plants and Other Materials 300
K. Timberdoodle WRE Site – Fulton County, Kentucky 551.7 Acres
11 Pre- Planting site preparation Post- Planting preparation 8 1 Job $___________ $ __________ Planting Trees and Shrubs 402 Woody Plants and Other Materials 300
DESCRIPTION
1. Scope
The work consists of the contractor’s work force and equipment necessary for performing the work required under the contract. It does not include Pre-Planting site preparation and Post-Planting site preparation for specific items of work for which payment is provided elsewhere in the contract. Post-Planting site preparation will not be considered as work in fulfilling the contract requirements for commencement of work.
2. Equipment and Material
The contractor shall include all activities and associated costs for transportation of contractor’s personnel, equipment, and operating supplies to the site; establishment of offices, buildings, and other necessary general facilities for the contractor’s operations at the site; premiums paid for performance and payment bonds including coinsurance and reinsurance agreements as applicable; and other items specified in section 4 of this specification.
Pre-Planting site preparation and Post-Planting site preparation shall include all activities and costs for transportation of personnel, equipment, and supplies not required or included in the contract from the site; including the disassembly, removal, and site clean up of and other facilities assembled on the site specifically for this contract.
This work includes Pre-Planting site preparation and Post-Planting site preparation required by the contract at the time of award. If additional Pre-Planting site preparation and Post-Planting site preparation activities and costs are required during the performance of the contract as a result of changed, deleted, or added items of work for which the contractor is entitled to an adjustment in contract price, compensation for such costs will be included in the price adjustment for the item of work changed or added.
3. Payment
Payment will be made as the work proceeds, after presentation of paid invoices or documentations of direct costs by the contractor showing specific Pre-Planting site preparation and Post-Planting site preparation costs and supporting evidence of the charges of suppliers, subcontractors, and others. When the total of such payments is less than the lump sum contract price, the balance remaining will be included in the final contract payment. Payment of the lump sum contract price for Pre-Planting site preparation and Post-Planting site preparation will constitute full compensation for completion of work.
Payment will not be made under this item for the purchase costs of materials having a residual value, the purchase costs of materials to be incorporated in the project, or the purchase costs of operating supplies.
All invoices must be submitted electronically through the U.S. Department of the Treasury’s Invoice Processing Platform System (IPP). The Contractor must use the IPP website (https://www.ipp.gov) for submitting invoices.
Invoices submitted by means other than IPP will not be accepted unless the Contracting Officer authorizes alternate procedures in writing.
4. Items of Work and Details
Items of work to be preformed in conformance with this specification and on the construction, details therefore are:
A.) Items 01 thru 11
1) This item shall consist of the following:
a. Ensuring contractor’s work force and equipment is at each site for Pre-Planting site preparation and Post-Planting site preparation.
b. Purchase of bonds if required by the items of the contract.
c. Purchase of liability insurance coverage for accidental injury to personnel on the work site and accidental damage to property located within the work sites and damage during the performance period of the contract.
d. Costs of moving equipment to the work sites and removal of equipment after completion of the work.
2) The contractor shall assume responsibility for protection of existing roads, overhead and/or buried utilities and fences that may be affected by the work.
3) All invoices submitted by the contractor shall be subject to approval of the Contracting Officer’s
Technical Representative.
4) Ingress and egress to the sites shall be provided by NRCS with specific instructions provided by the site landowner. Access roads shall be restored to original condition and grade after the work is completed.
5) Measurement and Payment: Payment will be made by the method in Section 3. Payment.
MATERIAL SPECIFICATION
300. WOODY PLANTS AND OTHER MATERIALS
1. SCOPE
This specification covers the quality of woody plants and other materials needed for planting.
2. PLANT MATERIALS
Unless otherwise specified, all plant materials used shall be true to name and size in conformity with the following standards:
AMERICAN JOINT COMMITTEE ON HORTICULTURE NOMENCLATURE. 1942
EDITION OF STANDARDIZED PLANT NAMES. (Published by Mount Pleasant Press, J Horace McFarland Company, Harrisburg, PA)
AMERICAN STANDARD FOR NURSERY STOCK. Copyright 1973 (current edition).
(Published by the American Association of Nurserymen, Inc., 230 Southern Building, Washington, DC 20005)
a. Verification of Sources of Supply. The contractor shall verify, prior to providing quote, that all sources of supply come from a certified nursery to insure that all of the items on the plant materials list, of size, species, variety, and quality noted and specified, can be supplied.
b. General Requirements. At least part of the plants in each type of group will be properly identified by name and size on legible weatherproof labels securely attached to plants.
All plants shall be nursery grown, unless otherwise specified.
All plants shall have normal, well-developed branches and vigorous root systems. They shall be sound, healthy, vigorous, free from defects, disfiguring knots, abrasions of the bark, sun scaled injuries, plant diseases, insect eggs, borers, and all other forms of infections.
Plants which have been held in storage will be rejected if they show signs of growth during storage.
Any tree with a weak trunk not capable of supporting itself in the open will be rejected.
c. Inspection. The Contractor shall notify the Government Representative of the source of plant materials at least one (1) week prior to delivery. The Government Representative may inspect the plants for acceptance at the place of growth. Inspection at the place of growth will not impair the right to reject plants at the planting site. Final acceptance of all plant materials shall be given only after the materials are planted and after all requirements are met.
Unacceptable plant material shall be removed at contractor’s expense from the jobsite immediately.
d. Delivery. All plants shall be packed in such a manner as to insure adequate protection against climatic, seasonal, or other injuries during transit. Special care shall be taken for prompt delivery and careful handling in loading and unloading.
No plant shall be pruned prior to delivery.
Each shipment of plants to the site shall be accompanied by a delivery slip indicating source of supply, exact quantities, sizes, and species delivered. A copy of all delivery slips shall be made available to the Government Representative.
7. STOCK PREPERATION
a. Balled and Burlapped – Plants designated “B&B” in the Plant Materials List or schedule on construction drawings have balls lifted from the natural earth in which the plant has been growing. No manufactured or partially manufactured or repaired balls shall be accepted. All balls shall be firmly wrapped with burlap and those 18 inches or over in diameter tightly bound with twine, cord, or wire. All balls shall be firm, unbroken, and undisturbed before and during the process of planting. Balled and burlapped plants shall be lifted by the ball, not by the stems, branches, or trunks. Balled and burlapped plants shall not be moved at any time by rolling the balls. Balled and burlapped plants shall not be thrown or dropped.
b. Balled and Platformed - Plants designated “B&P” in the Plant Materials List shall have balls of roots as described for Balled and Burlapped plants, but the balls shall be mounted on sturdy platforms with the platforms securely bound to the balls.
c. Bare Root – Plants designated “BR” in the Plant Materials List shall have well branched root systems characteristic of the species. They shall be carefully dug such that the major portion of the root system, including the fibrous roots, remains intact. The soil shall be carefully removed from the roots, avoiding unnecessary loss or breakage of fibrous roots.
Any roots that are broken or which must be cut shall be cleanly cut. The roots of all plants shall be protected at all times to prevent injury or drying caused by heat, sun, wind, and freezing temperatures.
d. Container grown – Plants designated “CG” in the Plant Materials List shall have been grown in a container long enough for the root system to have sufficiently to hold its soil together, firm and whole. No plants shall be loose in the container.
e. Collected Material – Collected plant material is defined as plants collected from wild native stands, established plantings, or plants that have been collected and transplanted in a nursery row for less than two growing seasons.
Collected plant material will experience a much more severe shock when transplanted than the same kind of nursery-grown plants. Therefore, collected material should have considerably larger root spread or ball diameters than required minimums for transplanted nursery stock.
Plants designated collected material “CM” in the Plant Material List shall meet the following:
Bare Root Stock – The spread of roots of collected bare root trees and shrubs shall be 1/3 greater than the spread of roots, bare root nursery-grown stock as indicated in
1.2.1 for deciduous trees and 2.2.1 for deciduous shrubs. American Standards for Nursery Stock.
Ball and Burlap or Platform Stock – The minimum ball size for collected trees and shrubs shall be equal to or greater than those specified for the next larger size nursery stock in 1.3.1 for trees; 2.3.1 for shrubs; and 3.2.1 for coniferous plant material. The standard practice of root pruning one year in advance of lifting stock is required.
American Standards for Nursery Stock.
8. STORAGE
In the event that more plants are delivered to the site than will be planted the day of arrival, the excess shall be stored in a sheltered location, and properly cared for until planted.
All stored plant material shall be kept cool and moist and protected from sun, wind, and freezing temperatures.
Balled and Burlapped and Balled and Platformed stock shall be stored in an upright position with the ball completely covered with an approved moist mulching material immediately following delivery to the storage location.
Bare root stock not planted within the same day of delivery shall be heeled-in in a moist soil or protected with other approved material.
In heeling-in all bundles of bare root stock shall be opened and all plants separated before the roots are covered. Care shall be taken that no air pockets remain among the roots. Movement of stock shall be kept to a minimum.
Container-grown stock shall be stored in an upright position.
9. OTHER MATERIALS
a. Topsoil shall be a friable, fertile, natural topsoil of loamy character possessing characteristics of representative soils in the vicinity which produce heavy growth of crops, grass, other vegetation and shall be obtained from naturally well drained areas from which the topsoil has never been stripped. It shall contain normal amounts of decomposed organic matter and shall be reasonably free from heavy clay, subsoil, lumps, plants, roots, sticks, or other objects which might be a hindrance to planting operations.
It shall have a pH between 6.0 and 8.0, unless otherwise specified. The right is reserved to reject on or after delivery any material which does not meet the requirements for this specification. Topsoil shall not be delivered or handled in a frozen or muddy condition.
b. Peat Moss shall consist of shredded horticultural Sphagnum peat, low in content of woody materials, and free of mineral matter harmful to plant life. Peat moss shall have an acid reaction of not less than 4.5 pH. Peat moss shall be marked with the name of the manufacturer and furnished air dry.
c. Mulch – Acceptable mulch shall be the material listed below or any approved locally available material that is similar to those specified, free from matured seed of noxious weeds, or species detrimental to development of specified plants. Low grade, musty, spoiled, partially rotted hay, straw, or other materials unfit for animal consumption will be acceptable. The materials shall be air dry and not in such a condition as to be caked together. Straw or other mulch material which is fresh and /or excessively brittle, in such an advanced state of decomposition as to smother or retard the plant or contains noxious weed seeds will not be acceptable.
i. Hay - Hay shall be native hay, tame grass hay, legume hay, or similar hay or grass clippings.
ii. Straw – Straw shall be the threshed plant residue of oats, wheat, barley, rye, or rice from which grain has been removed.
iii. Forest Litter – Forest litter shall be the surface layer of leaves, twigs, needles, and small branches from local woods. Forest litter shall be removed in such a way as to avoid injury to the trees.
iv. Manufactured Mulch – Cellulose-fiber or wood pulp mulch shall be products commercially for use in hydraulic spray applications.
v. Sawdust – Sawdust must be well rotted and may be from either hard or soft wood.
d. Fertilizer, Lime, and Gypsum. Fertilizer, lime, and gypsum materials shall be uniform in composition, dry, and free flowing. Fertilizer shall be delivered to the project site in original unopened containers bearing the manufacturer’s guaranteed analysis, and in conformance to state and Federal law. If in bulk, a certificate indicating the above shall accompany each delivery.
e. Burlap. Burlap shall be new jute burlap free from rot or mildew.
f. Twine. Twine shall be coarse sisal yarn twine.
g. Layout Stakes. Layout stakes shall be pine or fir, ¾ inch by 1-3/4 inch by 18 inches or approved equal.
h. Lath. Lath for tightening wires and accident prevention shall be ¾ inch by 1-3/4 inch by
8 inches wood lath painted with 2 coats of white, oil base paint or approved equal.
i. Support Stakes. Support stakes shall be sound pine or fir of uniform size, free of large knots or cracks, or approved substitute.
Stake Sizes Width Length Staking Method 1 1-3/4” sq. 8 ft.
Or 2” dia. 8 ft.
Staking Method 2 1-3/4” sq. 2-1/2 ft.
Or 2” dia. 2-1/2 ft.
j. Guys. Guy wires shall be new, galvanized iron, malleable wire minimum 12 gauge.
k. Hose. Hose shall be fiber centered remnants of new or suitable secondhand material of
½-inch, 5/8-inch, or ¾-inch inside diameter.
l. Tree Wound Dressing. Paint for sealing plant wounds or cuts shall be a horticulturally approved commercial grade asphaltic base sealer containing no ingredient detrimental to the healing of the injury.
m. Wrapping Material. Wrapping material for trees shall be double thickness of crinkled paper cemented together with bituminous material in strips 4 inches wide or jute burlap at least 8 ounces in weight in strips 4 to 6 inches wide.
MATERIAL SPECIFICATION
402. PLANTING TREES AND SHRUBS
1. SCOPE
The work shall consist of site preparation, furnishing and planting all tree seedlings of the kinds specified at the locations shown on the drawings and maps provided following the procedures of Section 3 Care of Plants, Section 4 Planting, and Section 8 Items of Work and Construction Details. See the attached county road location map, marked aerial photograph tree planting map, and NRCS Field Office Technical Guide Tree Establishment Practice Standard for details. All field boundaries will be flagged at the time of site preparation or tree planting. A pre-construction conference between the successful contractor and NRCS or an agent acting for NRCS is required before work begins.
2. MATERIALS
All Bare Root Tree Seedlings provided under this solicitation will be provided by the successful Contractor and shall meet the following specifications.
1. All plants furnished shall be true to name and no substitution of species is permitted;
2. All plants are to be free of insect, disease, and mechanical injury;
3. All plants must be suitable in every way for field planting;
4. All plants shall be dormant when collected;
5. All plants shall be seedlings that have been grown in a nursery for at least one year and no more than three years.
6. All plants must be raised or propagated in a certified nursery.
7. The following plant species: Big Shellbark Hickory and Shagbark Hickory shall have the following dimensions;
- Minimum height of 8” inches and a maximum height of 36 inches
- Diameter at the root collar of at least 1/4 inch
- Roots shall be at least 5 inches in length and MUST be pruned to 10 inches, as necessary;
8. The following plant species: Pecan shall have the following dimensions;
- Minimum height of 10” inches and a maximum height of 36 inches
- Diameter at the root collar of at least 1/4 inch
- Roots shall be at least 5 inches in length and MUST be pruned to 10 inches, as necessary;
9. The following plant species: Overcup Oak, Swamp White Oak, Swamp Chestnut Oak, Bur Oak, Nutall Oak, Willow Oak, Pin Oak, Cherrybark Oak, Shumard Oak, Black Walnut, Persimmon, Silky Dogwood, and Bald Cypress, shall have the following dimensions;
- Minimum height of 14 inches and a maximum height of 48 inches
- Diameter at the root collar of at least 1/4 inch
- Roots shall be at least 5 inches in length and MUST be pruned to 10 inches, as necessary;
10. All plant materials shall confirm to the requirements in Material Specification 300 Woody Plants and Other materials.
11. The contractor shall guard against the introduction of noxious weeds, pests, both on equipment and plant materials brought to the site.
3. CARE OF PLANTS
Plant materials shall be inspected when received from the nursery and a determination made as to their condition relative to their suitability for planting. Seedlings should be protected from sun and wind during shipping and the planting operation. They should be kept moist during transportation, storage, and during the planting operation.
Seedlings should be planted immediately after they have been picked up. If the tree seedlings are not planted within five (5) days after they have been picked up from the designated nursery, the Contractor shall place them in cold storage at 35 to 45 degrees Fahrenheit. If cold storage is not available seedlings should be heeled in. Spread roots against the back of a trench that is slightly deeper than the root systems. Cover roots with soil and tamp the soil firmly to eliminate air space. The Contractor shall protect the seedlings from injury or theft.
4. PLANTING
Trees and shrubs that are bare root seedlings shall be planted between December 1, 2024 and April 15, 2025.
Planting shall consist of rows of trees in areas designated on the drawings, as specified herein, or as marked in the field. Trees shall be planted with conventional planting equipment such as the dibble or planting bar, spade, mattock, or shovel. Note this is a Hand Planting only contract. Plants shall be placed in a hole or slit of sufficient depth and width that the root system is fully accommodated in its natural form and position. They shall be set deep enough that the root collar is at, or slightly below, ground level and soil shall be packed firmly around the roots.
During planting, the plants shall be carried in a bucket or planting bag and the roots shall be kept moist with wet moss or similar material. When soil moisture conditions are such that they inhibit proper closure of the planting furrow and do not firmly pack the root system, planting shall cease, until the COTR authorizes the contractor to proceed. Trees shall not be planted when the ground is frozen. The ground shall be considered frozen when soil temperature (0-3) inches is below 33 degrees Fahrenheit. Seedlings will be planted upright with no more than a 20% lean and at the same depth as they grew in the nursery. Soil will be packed firmly around seedling roots to eliminate air pockets. Any seedlings that do not meet these specifications following inspection as defined in section 6. (Inspection Requirements) will require the Contractor to re-work the 10-acre plot prior to re-inspection.
5. SITE PREPARATION
PRE-PLANTING SITE PREPARATION
1) 843.2 acres of no pre-planting site preparation needed due to planting into agricultural crop stubble
2) 359.2 acres of mowing to a height of 8 inches within 14 days of contract award followed with a chemical application with 1.5 quarts of Roundup (41% Glyphosate base product or an equivalent labeled product) per acre no earlier than 2 weeks after mowing but before October 1, 2024. Two weeks after spraying but before November 1, 2024, plant with a no-till drill 90 lbs./acre of wheat to serve as a nurse crop prior to tree planting.
3) 11.4 acres of mowing to a height of 8 inches within 14 days of contract award followed with a chemical application with 1.5 quarts/acre of Roundup (41% Glyphosate base product or an equivalent labeled product) tank mixed with 16.0 oz/acre of Imazapyr (27.6 % base product or an equivalent labeled product) and proper oil surfactant no earlier than 2 weeks after mowing but before October 1, 2024
POST-PLANTING SITE PREPARATION
1) 854.6 acres consisting of a chemical application of 1 ounce per acre of Oust XP (Sulfometuron methyl:
{Methyl 2-[[[[(4,6-dimethyl-2pyrimidinyl)amino]-carbonyl]amino]sulfonyl]benzoate}. . . 75.0% or equivalent labeled product) at the time of planting, if the seedlings are planted after March 1, 2025. If seedlings are planted before March 1, 2025, the 1.0 ounce/acre Oust XP application should be completed after March 1, 2025, but before tree seedling buds break dormancy. The Oust XP application will not occur during or within 12 hours of a rain event .
See Section 8. Items of Work and Construction Detail for the specific information and requirements of each site.
6. INSPECTION REQUIREMENTS
Inspection by the government or its agents will be performed under this contract by measuring sampling plots. A sampling plot is defined as a 1/20 acre sample taken for every 10 acres of planted area. An area will be considered adequately planted when a minimum of 87% of the trees (19 trees for a 435 planting rate) in each sample plot meets contract-planting specifications. In the event, a sample plot fails to meet the contract requirements, the Contractor will be required to re-work the 10 acre area prior to re-inspection. A sampling plot for the container tree seedling planting is defined as a 1/10 acre sample taken for every 10 acres of planted area. An area will be considered adequately planted when a minimum of 71% of the trees (2 trees for a 28 planting rate) in each sample plot meets contract-planting specifications. In the event, a sample plot fails to meet the contract requirements, the Contractor will be required to re-work the 10 acre area prior to re-inspection.
7. MEASUREMENT AND PAYMENT
Method 1.
The acreage figure for each field or planting area is an estimate that was made on an aerial photograph. Payment will be made to the nearest 0.1 acre shown in the pricing schedule. The estimated acreage will not be re-measured or adjusted further. Contractor is responsible for providing and planting the number of trees necessary to achieving the specified spacing. Such payment will constitute full compensation for furnishing, transporting, planting trees complete and in place. For items of work for which specific unit prices are established in the contract, each area treated as specified will be measured to the nearest 0.1 acre. Payment for treatment will be made at the contract unit price for the designated treatment which will constitute full compensation for completion of the work.
The payment for planting trees and shrubs shall be paid for at the contract unit price as shown in the pricing schedule. Such payment shall constitute full compensation for all labor, tools, equipment, materials, and other necessary and incidental to completion of work.
Method 2.
For items of work for which specific lump sum prices are established in the contract, the quantity of work will not be measured for payment. Payment for this item will be made at the contract lump sum price for the item and will constitute full compensation for completion of the work.
Method 3.
For items of work for which lump sum prices are established in the contract, payment will be made as the work proceeds, after presentation of invoices by the Contractor showing related costs. If the total of such payments is less than the lump sum contract price for this item, the unpaid balance will be included in the final contract payment.
Payment of the lump sum contract price will constitute full compensation for completion of the work.
All Methods.
The following provisions apply to all methods of measurement and payment. Compensation for any item of work described in the contract but listed in the price schedule will be included in the payment for the item of work to which it is made subsidiary. Such items and the items to which they are made subsidiary are identified in Section 8.
Payment will be made by electronic transfer.
8. ITEMS OF WORK AND CONSTRUCTION DETAILS
Items of work to be performed in conformance with this specification and the construction details are:
Tree Planting Sites
A. Aldrich, James, Taylor County, Kentucky Planting of 30,250 Seedlings on Approximately 69.1 Acres.
Item 01 – Planting Trees and Shrubs
(1) This item shall consist of site preparation, furnishing, storing, transporting, and planting bare root tree seedlings in the areas shown on the attached drawings. The Contract Officer’s Technical Representative will determine the extent of areas to be planted.
(2) Pre- planting site preparation will consist of mowing a total of 69.1 acres to a height of 8 inches within 14 days of contract award followed with a chemical application with 1.5 quarts of Roundup (41% Glyphosate base product or an equivalent labeled product) per acre no earlier than 2 weeks after mowing but before October 1, 2024. Two weeks after spraying but before November 1, 2024, plant with a no-till drill 90 lbs./acre of wheat to serve as a nurse crop prior to tree planting. A chemical application is required over the entire 69.1 acres of this site with 1 ounce per acre of Oust XP (Sulfometuron methyl:
{Methyl 2-[[[[(4,6-dimethyl-2pyrimidinyl)amino]-carbonyl]amino]sulfonyl]benzoate}. . . 75.0% or equivalent labeled product) at the time of planting, if the seedlings are planted after March 1, 2025. If seedlings are planted before March 1, 2025, the 1.0 ounce/acre Oust XP application should be completed after March 1, 2025, but before tree seedling buds break dormancy. The Oust XP application will not occur during or within 12 hours of a rain event.
(3) Tree seedlings shall be planted between 12/1/24 and 4/15/25.
(4) The species and number of seedlings per acre to be planted in each area shall be as shown in the following Plant Materials List. All seedlings shall be bare root.
Quantity Species
1,750 Swamp White Oak 2,750 Swamp Chestnut Oak 2,750 Overcup Oak 1,750 Bur Oak 2,000 White Oak 2,000 Northern Red Oak 3,000 Cherrybark Oak 3,000 Pin Oak 3,000 Shumard Oak 1,750 Black Walnut 1,500 Shellbark Hickory 1,500 Shagbark Hickory 1,250 Persimmon 1,250 Wild Plum 500 Silky Dogwood 500 Bald Cypress
(5) Tree seedlings will be planted in a random mix of species specified on the enclosed map.
(6) Tree seedlings in all areas shall be planted at an approximate rate of 435 per acre. Seedlings shall be planted on a 10 foot by 10 foot spacing (plus or minus one-foot row spacing tolerance).
(7) Tree seedling diversity shall be achieved by planting at least two species per row. Tree seedlings shall be planted so that the root collar is just below the ground or at the same depth planted in the nursery.
(8) The following will be furnished to the Contracting Officers Technical Representative (COTR) or the
Government Inspector by the Contractor:
a. Copies of invoices and seedling chain of custody origination of each shipment of seedlings
b. Certification that all seedlings conform to the standards of the American Association of
Nurserymen.
c. Certification that the equipment to be used is of the proper type, sizes, capacity, and condition to do the work.
d. An inspection certificate for each shipment of seedlings cross-referenced with the invoice for each shipment.
(9) Areas shown on the maps or marked in the field as food plots, moist soil units, open water areas, native warm season grasses, or existing woodland shall not be planted.
(10) Measurement and Payment shall be by Method 2 of section 7 above and by electronic transfer.
B. Brown/Bagley WRE, Hopkins County, Kentucky
Planting of 55,250 Seedlings on Approximately 126.6 Acres.
Item 02 - Planting Trees and Shrubs
(1) This item shall consist of furnishing, storing, transporting, and planting bare root tree seedlings in the areas shown on the attached drawings. The Contract Officer’s Technical Representative will determine the extent of areas to be planted.
(2) Pre- planting site preparation is NOT required for this site due to the fact that the fields to be tree planted are currently in agricultural production with soybeans. A chemical application is required over the entire 126.6 acres with 1 ounce per acre of Oust XP (Sulfometuron methyl:
{Methyl 2-[[[[(4,6-dimethyl-2pyrimidinyl)amino]-carbonyl]amino]sulfonyl]benzoate}. . . 75.0% or equivalent labeled product) at the time of planting, if the seedlings are planted after March 1, 2025. If seedlings are planted before March 1, 2025, the 1.0 ounce/acre Oust XP application should be completed after March 1, 2025, but before tree seedling buds break dormancy. The Oust XP application will not occur during or within 12 hours of a rain event.
(3) Tree seedlings shall be planted between 12/1/24 and 4/15/25.
(4) The species and number of seedlings per acre to be planted in each area shall be as shown in the following Plant Materials List. All seedlings shall be bare root.
Quantity Species 7,500 Swamp White Oak 7,500 Swamp Chestnut Oak 2,500 Bur Oak 2,500 Overcup Oak 4,000 Cherrybark Oak 4,000 Pin Oak 3,000 Shumard Oak 4,000 Willow Oak 4,000 Water Oak 1,000 Nutall Oak 5,000 Pecan 3,000 Shagbark Hickory 3,000 Shellbark Hickory 1,000 Persimmon 250 Silky Dogwood 500 Wild Plum 2,500 Bald Cypress
(6) Tree seedlings in all areas shall be planted at an approximate rate of 435 per acre. Seedlings shall be planted on a 10 foot by 10 foot spacing (plus or minus one foot row spacing tolerance).
(7) Tree seedling diversity shall be achieved by planting at least two species per row. Tree seedlings shall be planted so that the root collar is just below the ground or at the same depth planted in the nursery.
(8) The following will be furnished to the Contracting Officers Technical Representative (COTR) or the Government Inspector by the Contractor:
a. Copies of invoices and seedling chain of custody origination of each shipment of seedlings
b. Certification that all seedlings conform to the standards of the American Association of
Nurserymen.
c. Certification that the equipment to be used is of the proper type, sizes, capacity, and condition to do the work.
d. An inspection certificate for each shipment of seedlings cross-referenced with the invoice for each shipment.
(9) Areas shown on the maps or marked in the field as food plots, moist soil units, open water areas, native
C. Cox, Lawrence WRE, Hart County, Kentucky
Planting of 5,000 Seedlings on Approximately 11.4 Acres.
Item 03 – Planting Trees and Shrubs
(1) This item shall consist of site preparation, furnishing, storing, transporting, and planting bare root tree seedlings in the areas shown on the attached drawings. The Contract Officer’s Technical Representative will determine the extent of areas to be planted.
(2) Pre- planting site preparation consists of mowing 11.4 acres to a height of 8 inches within 14 days of contract award followed with a chemical application with 1.5 quarts/acre of Roundup (41% Glyphosate base product or an equivalent labeled product) tank mixed with 16.0 oz/acre of Imazapyr (27.6 % base product or an equivalent labeled product) and proper oil surfactant no earlier than 2 weeks after mowing but before October 1, 2024. A chemical application is required over the entire 11.4 acres with 1 ounce per acre of Oust XP (Sulfometuron methyl:
{Methyl 2-[[[[(4,6-dimethyl-2pyrimidinyl)amino]-carbonyl]amino]sulfonyl]benzoate}. . . 75.0% or equivalent labeled product) at the time of planting, if the seedlings are planted after March 1, 2025. If seedlings are planted before March 1, 2025, the 1.0 ounce/acre Oust XP application should be completed after March 1, 2025, but before tree seedling buds break dormancy. The Oust XP application will not occur during or within 12 hours of a rain event.
(3) Tree seedlings shall be planted between 12/1/24 and 4/15/25.
(4) The species and number of seedlings per acre to be planted in each area shall be as shown in the following Plant Materials List. All seedlings shall be bare root.
Quantity Species
500 Swamp White Oak 500 Swamp Chestnut Oak 500 Overcup Oak 250 Bur Oak 250 Willow Oak 250 Water Oak 500 Cherrybark Oak 500 Pin Oak 500 Shumard Oak 250 Shellbark Hickory 250 Shagbark Hickory 500 Black Walnut 250 Persimmon
(6) Tree seedlings in all areas shall be planted at an approximate rate of 435 per acre. Seedlings shall be planted on a 10 foot by 10 foot spacing (plus or minus one foot row spacing tolerance).
(7) Tree seedling diversity shall be achieved by planting at least two species per row. Tree seedlings shall be planted so that the root collar is just below the ground or at the same depth planted in the nursery.
(8) The following will be furnished to the Contracting Officers Technical Representative (COTR) or the
Government Inspector by the Contractor:
a. Copies of invoices and seedling chain of custody origination of each shipment of seedlings
b. Certification that all seedlings conform to the standards of the American Association of
Nurserymen.
c. Certification that the equipment to be used is of the proper type, sizes, capacity, and condition to do the work.
d. An inspection certificate for each shipment of seedlings cross-referenced with the invoice for each shipment.
(9) Areas shown on the maps or marked in the field as food plots, moist soil units, open water areas, native
D. Davis, Jeff/Troy, Green County, Kentucky
Planting of 6,250 Seedlings on Approximately 13.9 Acres.
Item 04 – Planting Trees and Shrubs
(1) This item shall consist of site preparation, furnishing, storing, transporting, and planting bare root tree
Representative will determine the extent of areas to be planted.
(2) Pre- planting site preparation consists of mowing 13.9 acres to a height of 8 inches within 14 days of contract award followed with a chemical application with 1.5 quarts of Roundup (41% Glyphosate base product or an equivalent labeled product) per acre no earlier than 2 weeks after mowing but before October 1, 2024. Two weeks after spraying but before November 1, 2024, plant with a no-till drill 90 lbs./acre of wheat to serve as a nurse crop prior to tree planting. A chemical application is required over the entire 13.9 acres with 1 ounce per acre of Oust XP (Sulfometuron methyl:
{Methyl 2-[[[[(4,6-dimethyl-2pyrimidinyl)amino]-carbonyl]amino]sulfonyl]benzoate}. . . 75.0% or equivalent labeled product) at the time of planting, if the seedlings are planted after March 1, 2025. If seedlings are planted before March 1, 2025, the 1.0 ounce/acre Oust XP application should be completed after March 1, 2025, but before tree seedling buds break dormancy. The Oust XP application will not occur during or within 12 hours of a rain event.
(3) Tree seedlings shall be planted between 12/1/24 and 4/15/25.
1,500 White Oak 250 Swamp Chestnut Oak 250 Overcup Oak 750 Shumard Oak 500 Northern Red Oak 500 Cherrybark Oak 750 Pin Oak 500 Black Walnut
500 Shagbark Hickory 250 Pecan 250 Persimmon 250 Wild Plum
(6) Tree seedlings in all areas shall be planted at an approximate rate of 435 per acre. Seedlings shall be planted on a 10 foot by 10 foot spacing (plus or minus one foot row spacing tolerance).
(7) Tree seedling diversity shall be achieved by planting at least two species per row. Tree seedlings shall be planted so that the root collar is just below the ground or at the same depth planted in the nursery.
(8) The following will be furnished to the Contracting Officers Technical Representative (COTR) or the
Government Inspector by the Contractor:
a. Copies of invoices and seedling chain of custody origination of each shipment of seedlings
b. Certification that all seedlings conform to the standards of the American Association of
Nurserymen.
c. Certification that the equipment to be used is of the proper type, sizes, capacity, and condition to do the work.
d. An inspection certificate for each shipment of seedlings cross-referenced with the invoice for each shipment.
(9) Areas shown on the maps or marked in the field as food plots, moist soil units, open water areas, native
E. Dillard, Roy WRE, Fulton County, Kentucky
Planting of 14,000 Seedlings on Approximately 31.1 Acres.
Item 05 – Planting Trees and Shrubs
(1) This item shall consist of site preparation, furnishing, storing, transporting, and planting bare root tree
Representative will determine the extent of areas to be planted.
(2) Pre- planting site preparation is NOT required for this site due to the fact that the field to be tree planted is currently in agricultural production with soybeans. A chemical application is required over the entire 31.1 acres with 1 ounce per acre of Oust XP (Sulfometuron methyl:
{Methyl 2-[[[[(4,6-dimethyl-2pyrimidinyl)amino]-carbonyl]amino]sulfonyl]benzoate}. . . 75.0% or equivalent labeled product) at the time of planting, if the seedlings are planted after March 1, 2025. If seedlings are planted before March 1, 2025, the 1.0 ounce/acre Oust XP application should be completed after March 1, 2025, but before tree seedling buds break dormancy. The Oust XP application will not occur during or within 12 hours of a rain event.
(3) Tree seedlings shall be planted between 12/1/24 and 4/15/25.
2,000 Swamp White Oak 2,000 Swamp Chestnut Oak 500 Overcup Oak 500 Bur Oak 1,000 Nutall Oak 750 Willow Oak
750 Water Oak 1,000 Cherrybark Oak 1,000 Pin Oak 750 Shumard Oak 1,000 Pecan 250 Shellbark Hickory 250 Shagbark Hickory 500 Persimmon 500 Silky Dogwood
1,000 Bald Cypress
(6) Tree seedlings in all areas shall be planted at an approximate rate of 435 per acre. Seedlings shall be planted on a 10 foot by 10 foot spacing (plus or minus one foot row spacing tolerance).
(7) Tree seedling diversity shall be achieved by planting at least two species per row. Tree seedlings shall be planted so that the root collar is just below the ground or at the same depth planted in the nursery.
(8) The following will be furnished to the Contracting Officers Technical Representative (COTR) or the
Government Inspector by the Contractor:
a. Copies of invoices and seedling chain of custody origination of each shipment of seedlings
b. Certification that all seedlings conform to the standards of the American Association of
Nurserymen.
c. Certification that the equipment to be used is of the proper type, sizes, capacity, and condition to do the work.
d. An inspection certificate for each shipment of seedlings cross-referenced with the invoice for each shipment.
(9) Areas shown on the maps or marked in the field as food plots, moist soil units, open water areas, native
F. Faris, Sammy Joe WRE, Whitley County, Kentucky
Planting of 17,000 Seedlings on Approximately 38.7 Acres.
Item 06 – Planting Trees and Shrubs
(1) This item shall consist of site preparation, furnishing, storing, transporting, and planting bare root tree
Representative will determine the extent of areas to be planted.
(2) Pre- planting site preparation consists of mowing 38.7 acres to a height of 8 inches within 14 days of contract award followed with a chemical application with 1.5 quarts of Roundup (41% Glyphosate base product or an equivalent labeled product) per acre no earlier than 2 weeks after mowing but before October 1, 2024. Two weeks after spraying but before November 1, 2024, plant with a no-till drill 90 lbs./acre of wheat to serve as a nurse crop prior to tree planting. A chemical application is required over the entire 38.7 acres with 1 ounce per acre of Oust XP (Sulfometuron methyl:
{Methyl 2-[[[[(4,6-dimethyl-2pyrimidinyl)amino]-carbonyl]amino]sulfonyl]benzoate}. . . 75.0% or equivalent labeled product) at the time of planting, if the seedlings are planted after March 1, 2025. If seedlings are planted before March 1, 2025, the 1.0 ounce/acre Oust XP application should be completed after March 1, 2025, but before tree seedling buds break dormancy. The Oust XP application will not occur during or within 12 hours of a rain event.
(3) Tree seedlings shall be planted between 12/1/24 and 4/15/25.
1,000 Swamp White Oak 1,500 Swamp Chestnut Oak 1,500 Overcup Oak 1,000 White Oak 1,000 Bur Oak 2,250 Cherrybark Oak 1,500 Pin Oak 1,500 Shumard Oak 750 Northern Red Oak 1,500 Black Walnut 1,500 Shagbark Hickory 750 Shellbark Hickory 250 Pecan 500 Persimmon
(6) Tree seedlings in all areas shall be planted at an approximate rate of 435 per acre. Seedlings shall be planted on a 10 foot by 10 foot spacing (plus or minus one foot row spacing tolerance).
(7) Tree seedling diversity shall be achieved by planting at least two species per row. Tree seedlings shall be planted so that the root collar is just below the ground or at the same depth planted in the nursery.
(8) The following will be furnished to the Contracting Officers Technical Representative (COTR) or the
Government Inspector by the Contractor:
a. Copies of invoices and seedling chain of custody origination of each shipment of seedlings
b. Certification that all seedlings conform to the standards of the American Association of
Nurserymen.
c. Certification that the equipment to be used is of the proper type, sizes, capacity, and condition to do the work.
d. An inspection certificate for each shipment of seedlings cross-referenced with the invoice for each shipment.
(9) Areas shown on the maps or marked in the field as food plots, moist soil units, open water areas, native
G. Forward, John WRE, Taylor County, Kentucky
Planting of 17,250 Seedlings on Approximately 39.1 Acres.
Item 07 – Planting Trees and Shrubs
(1) This item shall consist of site preparation, furnishing, storing, transporting, and planting bare root tree
Representative will determine the extent of areas to be planted.
(2) Pre- planting site preparation consists of mowing 39.1 acres to a height of 8 inches within 14 days of contract award followed with a chemical application with 1.5 quarts of Roundup (41% Glyphosate base product or an equivalent labeled product) per acre no earlier than 2 weeks after mowing but before October 1, 2024. Two weeks after spraying but before November 1, 2024, plant with a no-till drill 90 lbs./acre of wheat to serve as a nurse crop prior to tree planting. A chemical application is required over the entire 39.1 acres with 1 ounce per acre of Oust XP (Sulfometuron methyl:
{Methyl 2-[[[[(4,6-dimethyl-2pyrimidinyl)amino]-carbonyl]amino]sulfonyl]benzoate}. . .
75.0% or equivalent labeled product) at the time of planting, if the seedlings are planted after March 1, 2025. If seedlings are planted before March 1, 2025, the 1.0 ounce/acre Oust XP application should be completed after March 1, 2025, but before tree seedling buds break dormancy. The Oust XP application will not occur during or within 12 hours of a rain event.
(3) Tree seedlings shall be planted between 12/1/24 and 4/15/25.
1,000 Swamp White Oak 750 Swamp Chestnut Oak 1,250 Overcup Oak 2,000 White Oak 1,250 Bur Oak 1,500 Cherrybark Oak 1,500 Pin Oak 2,000 Northern Red Oak 1,500 Shumard Oak 2,000 Black Walnut 1,000 Shagbark Hickory 500 Shellbark Hickory 500 Persimmon
(6) Tree seedlings in all areas shall be planted at an approximate rate of 435 per acre. Seedlings shall be planted on a 10 foot by 10 foot spacing (plus or minus one foot row spacing tolerance).
(7) Tree seedling diversity shall be achieved by planting at least two species per row. Tree seedlings shall be planted so that the root collar is just below the ground or at the same depth planted in the nursery.
(8) The following will be furnished to the Contracting Officers Technical Representative (COTR) or the
Government Inspector by the Contractor:
a. Copies of invoices and seedling chain of custody origination of each shipment of seedlings
b. Certification that all seedlings conform to the standards of the American Association of
Nurserymen.
c. Certification that the equipment to be used is of the proper type, sizes, capacity, and condition to do the work.
d. An inspection certificate for each shipment of seedlings cross-referenced with the invoice for each shipment.
(9) Areas shown on the maps or marked in the field as food plots, moist soil units, open water areas, native
H. Keith/Williams WRE,…