This document is a Question and Answer (Q&A) related to Solicitation 12FPC324Q0066 for the restoration of a wetland easement in Christian County, Illinois. The solicitation is a Request for Quotes under Simplified Acquisition Procedures, with an estimated project value between $25,000 and $100,000. The work involves restoring the wetlands under a Floodplain Easement, with a 25-calendar day period of performance. The Q&A addresses a question about crossing a pipeline easement to move dirt from the excavation site to the spoil site. The response indicates the contractor will work with the pipeline owner to gain access, and if that is not feasible, will move the spoil location to the southeast corner of the field to avoid crossing the pipeline.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
12FPC324Q0066 – Christian County, IL
Question and Answer
1. Will the pipeline crossing the easement which will have to be crossed to move dirt from the excavation site to the spoil site?
a. We will work with the pipeline to gain access across the pipeline row with the equipment and if that is not feasible we will move the spoil location to the south east corner of the field as to not cross the pipeline. the dimensions and specs will stay the same and quantities will not change.