Attachment 5 Updated Bid Schedule.pdf

PDF 145 KB Posted

Attached to
Cox WRE, Hart County, KY Federal contract opportunity
Solicitation number
12FPC324Q0048
Issued by
Department of Agriculture Under Secretary for Farm Production and Conservation

About this file

This document is an Updated Bid Schedule attached to a federal solicitation for the Cox WRE project in Hart County, Kentucky. The solicitation is for the restoration of site hydrology through the construction of two dikes with two water control structures, and is being issued by the Department of Agriculture Under Secretary for Farm Production and Conservation.

The solicitation requires pricing to be submitted for all eight line items, which include clearing, seeding and mulching, mobilization/demobilization, earthfill, plastic pipe, rock riprap, water control structures, and non-woven geotextile. The quantities for several line items are estimated, and the FAR clause on Variation in Estimated Quantity applies. The solicitation will result in a single award for the aggregate of all items. It also includes requirements related to basic safeguarding of covered contractor information systems and federal acquisition supply chain security.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation Number: 12FPC324Q0048

Updated thru FAC 2024-05 dated May 22, 2024 5 of 39

PART I – THE SCHEDULE

B - SUPPLIES OR SERVICES AND PRICES/COSTS

WRE – Cox Property, Hart County, KY

This solicitation requires a price be submitted for all line items, failure to do so will disqualify the quote.

Line Item Description Spec

No. QTY Unit Unit Price

Extended Amount

001 Clearing 1 *10.0 AC $ $

002 Seeding and Mulching 6 *1.1 AC $ $

Mobilization and Demobilization 8 1 LS $ $

004 Earthfill 23 *1,306 CY $ $

005 Plastic Pipe – 6” ID, SCH 40, PVC 45 *20 LF $ $

006 Rock Riprap 61 *20 TN $ $

Water Control Structure 1 Ea – 3’ Tall 6” dia, Incline WCS 1 Ea – 3’ Tall 6” dia, Incline WCS

71 2 EA $ $

008 Non-Woven Geotextile 95 *20 SY $ $

TOTAL QUOTE $

SUBMITTED BY:_____________________________________ EUI#_____________________

COMPANY: _________________________________________

52.211-18 Variation in Estimated Quantity. (Apr 1984) If the quantity of a unit-priced item in this contract is an estimated quantity and the actual quantity of the unit-priced item varies more than 15 percent above or below the estimated quantity, an equitable adjustment in the contract price shall be made upon demand of either party. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above 115 percent or below 85 percent of the estimated quantity. If the quantity variation is such as to cause an increase in the time necessary for completion, the Contractor may request, in writing, an extension of time, to be received by the Contracting Officer within 10 days from the beginning of the delay, or within such further period as may be granted by the Contracting Officer before the date of final settlement of the contract. Upon the receipt of a written request for an extension, the Contracting Officer shall ascertain the facts and make an adjustment for extending the completion date as, in the judgement of the Contracting Officer, is justified.

(End of clause)

Quantities marked with an * above are estimated quantities and the clause FAR 52.211-18, Variation in Estimated Quantity, applies.

ONE AWARD FOR THE AGGREGATE OF ALL ITEMS WILL BE MADE AS A RESULT OF THIS

SOLICITATION

52.204-21 – Basic Safeguarding of Covered Contractor Information Systems (Nov 2021)
52.204-29 Federal Acquisition Supply Chain Security Act Orders—Representation and Disclosures.

File details come from the government source that posted it. Updated .