This amendment provides answers to the following questions received:

1. Q: When/where are the NRI trainings being held?

A: Training will be scheduled to occur in Canon City, CO on July 18th-21st. Otherwise, the location/time will depend on when the contractor can start.

1. Q: When is the data collection deadline?

A: September 31, 2023

1. Q: Are there any options to extend the data collection deadline based on precipitation from this year?

A: Not at this time, in accordance with Scientific integrity and data collection protocol.

1. Q: Due to the late release of the RFQ during the field season, would it be possible to roll over some points scheduled for 2023 into the 2024 field season?

A: No. the 2024 field season will have its own data set for collection.

1. Q: This would mean fewer points are collected in 2023, but all remaining 2023 points and all planned 2024 points would be collected in the 2024 field season?

A: The contractor shall complete the remaining 2023 field season segments, other than the points already collected (by the time a contractor is on board). The 2024 field season will have its own data set for collection; none of the remaining 2023 points shall be collected during the 2024 field season.